November 18, 2024

PJM Reducing Transmission Spending by $3.2B

By Rich Heidorn Jr.

Flat load growth, the lapse in federal subsidies for wind generators and a slowdown in coal plant retirements have caused PJM to reduce its transmission construction plans by $3.2 billion.

pjm
Generator deactivations announced in 2014 (left) and selected baseline upgrades driven by retirements (right).

PJM’s 2014 Regional Transmission Expansion Plan report, released last week, provides details of the $1.7 billion in transmission projects approved by PJM’s Board of Managers. The board approved 197 baseline projects totaling $1.1 billion and 148 network upgrades to address reliability criteria violations at a cost of $605 million.

But these new projects were more than offset by the removal of 651 network upgrades totaling $4.7 billion and 40 baseline projects estimated at $177 million, resulting in a net reduction of $3.2 billion from the spending anticipated at the end of 2013.

Generation Withdrawals

PJM said the network upgrade cancellations resulted from the withdrawal of 212 generation interconnection requests totaling 15,302 MW, one-quarter of them for wind turbines.

Generation withdrawals can reflect developers’ response to capacity auction prices. PJM also took note of the boom-bust cycle of wind development, based on the availability of the federal Production Tax Credit. The most recent iteration of the PTC covered only projects under construction by the end of 2014.

Network upgrades allow customers to interconnect to the PJM grid and obtain capacity rights. Such upgrades are recommended to the PJM board based on system impact studies, after developers receive facility study agreements.

Slowdown in Retirements

Baseline upgrades include both market efficiency projects to reduce congestion and reliability projects needed to correct violations, such as those identified in thermal and voltage analyses.

PJM said the reduction in baseline upgrades reflects flat load growth and a slowdown — perhaps temporary — in retirements of coal-fired generation. The RTO received 31 generator deactivation requests in 2014, totaling about 4,300 MW, down from 14,444 MW in 2012 and 7,745 MW in 2013.

pjm

The retirements were largely driven by the Environmental Protection Agency’s Mercury and Air Toxics Standards, which take effect this year. PJM has begun analyzing the impact of EPA’s proposed limits on generator CO2 emissions, which are expected to create a new wave of retirements. (See related story in PJM Transmission Expansion Advisory Committee Briefs.)

The 2014 RTEP includes 27 transmission upgrades in PJM’s Mid-Atlantic and Western regions to address retirements. The upgrades include both new and upgraded transmission lines, transformers, shunt capacitors and substation improvements.

Since 1999, PJM’s board has approved almost $25.7 billion in transmission projects, including $21.5 billion of baseline transmission upgrades and $4.1 billion in facilities needed to connect more than 60,000 MW of new generation. Almost $10 billion of those projects are in service with an additional $4.2 billion under construction.

Federal Briefs

AlgonquinSourceSpectraThe Federal Energy Regulatory Commission last week approved a much-needed natural gas pipeline expansion project to supply New England.

Spectra Energy’s Algonquin Incremental Market Project, which will run from New York to Massachusetts through Connecticut and Rhode Island, still needs approval from the New York Department of Environmental Conservation before construction can begin.

FERC discounted opponents’ concerns about the pipeline’s proximity to Entergy’s Indian Point nuclear generating station. “I’m dumbfounded that FERC could just be blithely going ahead,” said Susan Van Dolsen of the group Stop the Algonquin Pipeline Expansion.

More: The Journal News

Sen. Alexander Blasts NRC for Not Asking for More Yucca Mountain Funding

Alexander
Alexander

U.S. Sen. Lamar Alexander (R-Tenn.) criticized the Nuclear Regulatory Commission for failing to request additional funding that he says will be required to license the Yucca Mountain nuclear waste repository in Nevada.

Alexander said in a Senate Appropriations subcommittee hearing last week that the NRC has unspent funds in its budget to start the licensing process, but will need more resources. “So I think it’s fair to ask the question: Knowing that there are additional steps and they will cost money, why would you not request additional funds in your budget?”

Alexander, a nuclear power proponent, has said it is crucial to break the “25-year stalemate” over nuclear waste.

More: The Hill

Judge Criticizes EPA’s Response to Foundation’s Records Request

A federal judge criticized the Environmental Protection Agency’s “fumbled” response to a Freedom of Information Act (FOIA) request by a conservative group, but ruled that the group failed to prove the agency acted in bad faith and declined to award damages.

Judge Royce Lamberth in D.C. said the EPA allowed some records, including emails, to be destroyed in spite of pending discovery requests from the Landmark Legal Foundation, which sought the records to determine if the agency delayed issuing regulations before the 2012 election for political purposes.

“Despite admonitions from this court and others … EPA continues to demonstrate a lack of respect for the FOIA process,” Lamberth wrote in his opinion. “Neither EPA nor its counsel has offered Landmark or this court any indication of regret.”

More: The Hill

PennEast Pipeline Opponents Say FERC Consultant has a Conflict of Interest

(Source: PennEast Pipeline)The mayor of a New Jersey town in the path of the proposed PennEast Pipeline has called on the Federal Energy Regulatory Commission to replace an environmental consultant hired to review the project, saying the consultant’s ties to the shale-gas industry present a conflict of interest.

Hopewell Township Mayor Harvey Lester says the FERC consultant, Tetra Tech, is a paid member of the Marcellus Shale Coalition, an industry trade group that supports the proposed 114-mile pipeline to carry natural gas from the Marcellus Shale region in Pennsylvania into New Jersey.

The New Jersey chapter of the Sierra Club also objected to FERC’s hiring of Tetra Tech to review the project’s environmental impact statement. “This is an outrageous conflict of interest and a violation of the FERC rules,” wrote Director Jeff Tittel.

More: NJ.com

House Committee Chair Seeks Deleted EPA, McCarthy Texts

U.S. Rep. Lamar Smith (R-Texas), chairman of the House Science Committee, said he’ll seek a subpoena to obtain text messages to and from Environmental Protection Agency Administrator Gina McCarthy if the agency doesn’t give them up voluntarily.

Smith said the agency declined to provide the text messages to the Competitive Enterprise Institute in response to a public records request. The agency provided emails but has said it did not believe that text messages were required to be retained.

More: The Hill

NRC’s Annual Reviews Show 94% of US Reactors in Top Performance Categories

NRCThe Nuclear Regulatory Commission’s annual assessment letters show that 75% of the nation’s 100 nuclear reactors met all safety and security objectives in 2014, and 94 of those reactors were in the top two performance categories.

Nineteen reactors were identified as needing one or two “low significance” items. They are Calvert Cliffs 2 (Maryland); Clinton (Illinois); Davis-Besse (Ohio); Diablo Canyon 1 and 2 (California); Fermi 2 (Michigan); Fitzpatrick (New York); Limerick 1 and 2 (Pennsylvania); Millstone 3 (Connecticut); Oconee 1 (South Carolina); Oyster Creek (New Jersey); Palisades (Michigan); Point Beach 2 (Wisconsin); River Bend (Louisiana); Salem 1 (New Jersey); St. Lucie 1 (Florida); Waterford (Louisiana) and Wolf Creek (Kansas).

Two reactors — Pilgrim (Massachusetts) and Point Beach 1 (Wisconsin) — fell into the “degraded” performance category and will be the subjects of increased oversight. The twin-unit Arkansas Nuclear One reactors fell into a fourth category of oversight after the NRC made safety findings of “substantial significance.”

More: NRC

EPA Designates Mahomet Aquifer as ‘Sole Source’

The Environmental Protection Agency has designated the Mahomet Aquifer system in east-central Illinois as a “sole source” aquifer, raising the possibility of heightened federal review of projects in an area that may be targeted for natural gas development involving hydraulic fracturing.

The “sole source” designation, which means more than half of the population depends on the aquifer as its drinking water source, allows the EPA to review the effect that any federally funded project might have on the aquifer.

Gas exploration companies have leased mineral rights in the region, although the amount of drilling is less than the state first anticipated.

More: EPA

DOE Report Sets National Wind Energy Goal of 35% by 2050

A Department of Energy report says that wind energy could provide 35% of the nation’s electricity by 2050, up from the current 4.5%, if the cost of wind turbines comes down and new territories are opened up for development.

The report, “Wind Vision: A New Era of Wind Power in the United States,” makes no policy recommendations, but it does provide what it calls a “roadmap of targeted actions.”

The American Wind Energy Association said the goal is within reach. “We can do this,” said Tom Kiernan, CEO of the association. “The industry stands ready to achieve these numbers.”

More: USA Today; Energy Department

NRC’s Burns Touts Safety Improvements, but Public Citizen Accuses it of ‘Sluggishness’

Stephen Burns
Stephen Burns

The chairman of the Nuclear Regulatory Commission said the agency and the nuclear industry have improved safety at U.S. reactors since the 2011 Fukushima disaster, but a watchdog group accused the NRC of “sluggishness” in improving standards.

NRC Chairman Stephen Burns said that “both the NRC and the U.S. nuclear industry took swift and decisive action to address many of the key lessons learned from that event.” He said the main safety improvements would be completed by the end of 2016.

But Allison Fisher, outreach director of Public Citizen, said the NRC “has yet to require nuclear power plant operators to complete implementation of a single one of the post-Fukushima safety upgrades recommended by the agency’s own staff.”

More: The Hill

NRC to Review Korea Electric’s APR1400 Nuclear Reactor

The Nuclear Regulatory Commission announced that it will conduct a full design certification review of the APR1400 nuclear reactor design from Korea.

The NRC said a design for a 1,400-MW reactor submitted in December by Korea Electric Power Corp. and Korea Hydro and Nuclear Power met the requirements for a full certification review. The agency’s review will determine whether the reactor design meets U.S. safety requirements.

The APR 1400 is a pressurized water reactor based on the Korean Optimized Power Reactor 1000.

More: Penn Energy

McConnell Urges US Governors to Defy Clean Power Plan

McConnell
McConnell

U.S. Sen. Mitch McConnell (R-Ky.) wrote an op-ed urging governors to refuse to implement the Environmental Protection Agency’s proposed emissions reduction regulations, calling the regulations an “attack on the middle class.”

McConnell, a coal proponent and Obama administration foe, said governors could simply refuse to submit their state plans to the government.

“Think twice before submitting a state plan — which could lock you in to federal enforcement and expose you to lawsuits — when the administration is standing on shaky legal ground and when, without your support, it won’t be able to demonstrate the capacity to carry out such political extremism,” he wrote in the Lexington Herald-Leader.

More: Lexington Herald-Leader

Study: PJM Has Most at Stake in Fate of Order 745

PJM stakeholders face the greatest potential disturbance in the use of demand response in the wholesale capacity market if a D.C. Circuit Court of Appeals ruling limiting the jurisdiction of the Federal Energy Regulatory Commission is allowed to stand, according to a report released by EnerKnol Research, an energy policy analytics company.

However, the study concluded DR resources would continue to grow. “Demand response resources could still thrive in retail and ancillary markets if Order 745 is vacated, but with varying impacts to industry,” Chief Policy Strategist Erin Carson said in the report, “Demand Response to Grow Under Alternate Scenarios Regardless of FERC Order 745.”

PJM is set to receive more than $20 billion in demand response value through future capacity commitments.

FERC and PJM have petitioned the U.S. Supreme Court to hear the case. (See FERC Files EPSA DR Appeal with Supreme Court.) The RTO in January submitted to FERC a contingency plan to incorporate DR in May’s Base Residual Auction if the Supreme Court allows the ruling to stand.

More: EnerKnol Research

Compiled by Ted Caddell

Hydro-Quebec Seeks to Boost Exports to Northeast

By William Opalka

quebecCROMWELL, Conn. — Hydro-Quebec is looking to expand its exports to its long-standing customers in the Northeast power markets, Marianne Bonnard, spokeswoman for the Quebec Government Office in Boston, told the winter meeting of the Connecticut Power and Energy Society on Wednesday.

From 2008 to 2013, the provincial utility doubled its net exports of hydroelectricity. “In 2013, out of 32.2 TWh of electricity exported out of Quebec, HQUS [HQ Energy Services U.S.] delivered 15.7 TWh of power here to New England. This is a figure which represents about half of Connecticut’s annual electricity consumption,” Bonnard pointed out.

Increasing exports further will require more transmission.

HQ is a partner with Eversource Energy on the proposed 1,200-MW Northern Pass transmission line from Quebec to New Hampshire.

In addition, the proposed Champlain Hudson Power Express, a 1,000-MW merchant transmission line, would connect Quebec with New York City. The line would run underneath Lake Champlain for part of its 330-mile route.

Bonnard noted that New England and the Eastern Canadian provinces share climate goals, with a common target of reducing emissions by 10% below 1990 levels by 2020.

The province is already one of the most active governments on the continent in a nascent carbon market. Quebec began a cap-and-trade system for CO2 emissions linked to California at the beginning of 2014. “This is the first market ever to be run by sub-national governments of different countries,” she said.

The first joint carbon auction in November delivered $33 million for initiatives in the province’s Climate Change Action Plan. The second joint auction, Feb. 18, produced more than $190 million for Quebec.

FERC Seeking Its Role on Carbon Rule ‘Safety Valve’

By Rich Heidorn Jr.

ferc
FERC Chairman Cheryl LaFleur says the commission is seeking a way for it to help ensure reliability is not threatened by EPA’s carbon plan. “You get on thin jurisdictional ice pretty fast,” she said.

WASHINGTON — Members of the Federal Energy Regulatory Commission said last week they are trying to craft the commission’s role in administering a “safety valve” to ensure reliability is not threatened by the Environmental Protection Agency’s proposed carbon emission rule.

Speaking at the third of four FERC technical conferences on the EPA Clean Power Plan, Commissioner Philip Moeller said he hopes the commission will reach consensus on a “very specific” safety valve proposal to the agency.

Janet McCabe, EPA’s acting Assistant Administrator for the Office of Air and Radiation, repeated her promise — also made at FERC’s first conference Feb. 19 — that the agency’s final regulations this summer will be responsive to criticism of its initial proposal. (See EPA on Carbon Rule: We’re Listening.)

Responding to Moeller, McCabe said that although she couldn’t yet provide specifics on a safety valve, she expected “that we will be able to have a conversation as the rule moves closer to final on how to handle that both within the rule and … as we look at implementation expectations.”

FERC Chairman Cheryl LaFleur said the commission could work with RTOs and the North American Electric Reliability Corp. to “develop a record” on the reliability impact of shuttering individual power plants and the time needed to construct pipelines or transmission.

But she said she had misgivings about the commission having a formal adjudicatory role in disputes between state officials seeking deadline extensions and environmental groups pushing them to do more. “I don’t see us comfortably looking at, ‘How good is your rooftop solar program? Have you really maximized [it]? What are you doing with energy efficiency?’” she said. “… You get on thin jurisdictional ice pretty fast.

“I think we either need to develop a list of questions we’ll answer and stick to those questions and the EPA will, I guess, weigh them, or work out an approach with others such as the states which have their fingers on other parts of it,” she added.

The ISO-RTO Council has said that EPA’s final rule must include provisions for reliability reviews to address problems that may arise during implementation.

“Because of the limited nature of the scenarios we studied — and the fact that the rule itself is not yet final, nor have state plans been developed — we are simply not in a position to make definitive conclusions as to the reliability impacts of the Clean Power Plan on the PJM footprint,” Mike Kormos, PJM executive vice president of operations, said in written testimony.  “… The answer to the question, ‘is it reliable?’ is not a ‘once-and-done’ inquiry.”

Ohio Public Utilities Commissioner Asim Haque said he supports the concept of FERC, NERC or RTOs performing a “reliability check” on state implementation plans. But he said the third-party review must be one of “mediation” rather than mandatory.

“If the states cannot [resolve the reliability concerns], then in my mind the [emission] rates need to be adjusted … so that the reliability concern is allayed,” he said.

MidAmerican’s Fingerprints on Shakeup at Iowa Utilities Board?

By Chris O’Malley

midamericanGov. Terry Branstad last week shook up the Iowa Utilities Board, demoting Chairman Elizabeth “Libby” Jacobs and removing board member Sheila Tipton.

The unexplained move came after officials of MidAmerican Energy met with the governor to complain about the board’s February ruling requiring the company to refund $2 million annually to consumers over a wind project.

Branstad appointed Iowa Finance Authority official Geri Huser to replace Jacobs, whose term as chair was set to expire next month.

Jacobs, appointed by Branstad in 2011, declined to comment on the reason for the governor’s actions, but she told RTO Insider she plans to complete her term on the three-member board, which runs through April 2017.

“I’ll continue as [Organization of MISO States] president through Dec. 31, 2015, and I’ll also continue to serve [the National Association of Regulatory Utility Commissioners] as the co-vice chair of the Electricity Committee and as a member of the Task Force on Environmental Regulation and Generation,” she said.

Tipton was appointed by Branstad in 2013 to fill an unexpired term ending next month.

In February, the board ordered MidAmerican Energy to return $2 million annually to customers following a review of a $280 million wind turbine project that had been publicly praised by Branstad.

The board said the rewards of the project were “skewed too much towards MidAmerican” without the extra payment. The order modified a settlement that MidAmerican had negotiated with the Office of Consumer Advocate.

MidAmerican has confirmed that it met with Branstad to complain about the board’s decision but insisted it did not press the governor for personnel changes.

Branstad’s spokesman, Jimmy Centers, declined to discuss the speculation. He said Huser, a former state legislator, was chosen by the governor “because he’s been impressed with her career in public service.”

RGGI Auction Prices Rise 4%

rggiClearing prices for the latest Regional Greenhouse Gas Initiative CO2 allowances auction rose 4%, continuing a recent upward trend while the number of bidders declined.

The 27th auction, held on Wednesday, showed a clearing price of $5.41/ton for the 15.3 million in allowances offered and sold. The auction netted more than $82 million, putting the total proceeds over the $2 billion mark for the nation’s first cap-and-trade program, which has held quarterly auctions since late 2008.

Bids for the CO2 allowances ranged from $2.05 to $12.50 per allowance. The ratio of bids to initial supply was 2.8, up from 2.5 in the December 2014 auction.

The auction proceeds will fund various programs, including energy efficiency, renewable energy, direct bill assistance and greenhouse gas abatement in the nine Northeastern and Mid-Atlantic states participating.

All of the allowances were purchased by compliance entities — electric generators of 25 MW or larger — and their corporate affiliates. Compliance entities and affiliates have purchased 78% of allowances over the history of the auctions.

Auction 26, which offered 18.2 million allowances, cleared at $5.21/ton, generating $95 million.

The 2015 RGGI cap is 88.7 million tons. The RGGI cap declines by 2.5% annually until 2020.

A regulated power plant must hold CO2 allowances equal to its emissions for each three-year control period. RGGI’s third control period began on Jan. 1, 2015, and extends through Dec. 31, 2017.

Fuel-Burn Allegation Meant to Force Settlement of Unrelated Cases, Maxim Says

By William Opalka

maxim
FERC accused Maxim Power of overcharging ISO-NE for power from its Pittsfield, Mass., generator in 2010.

Maxim Power says market manipulation allegations by the Federal Energy Regulatory Commission are an attempt to gain leverage for a settlement of charges from subsequent, unrelated cases.

In a 57-page response to FERC’s Order to Show Cause, the Canadian-based generation owner said allegations that it overcharged ISO-NE in 2010 were revived only after later disputes were unresolved (IN15-4).

FERC issued the order last month, accusing the company of billing the RTO for more expensive oil at its 181-MW plant in Pittsfield, Mass., while actually burning cheaper natural gas. The order, on which Commissioner Tony Clark dissented, seeks a $5 million fine. (See FERC Seeks $5M from Maxim Power; Clark Dissents.)

The company said it offered its Pittsfield plant into the day-ahead market on oil due to pipeline restrictions that indicated it would not be able to obtain enough gas if ISO-NE ordered it to run for 24 hours.

When asked by ISO-NE’s Internal Market Monitor, Maxim said it later acknowledged having burned gas. It said the IMM recovered $3 million over the incident but declined to forward the case to FERC for investigation though it was “certainly cognizant of its Tariff obligation to refer manipulative conduct to [Office of Enforcement] staff.”

“This was no fraud, but … a simple hedge against the possible financial exposure associated with a receipt of a day-ahead award,” Maxim said.

In 2013, however, Maxim said FERC Enforcement staff began an unrelated investigation. “In what certainly looks like an effort to gain leverage in that investigation, OE staff decided to resurrect the 2010 fuel-burn issue,” the company wrote. “Then, in late 2014, when Maxim declined to enter into a tolling agreement, OE staff decided to pursue the 2010 issue separately and on a fast track.”

These are apparent references to allegations contained in the Office of Enforcement’s Notice of Alleged Violations issued in November, which accused Maxim of collecting “millions of dollars of inflated make-whole payments” from ISO-NE between 2012 and 2013 by gaming market mitigation rules for generators needed for reliability. The notice did not elaborate on how this was allegedly done.

The November notice also alleged that Maxim collected inflated capacity payments between 2010 and 2013 by using “extraordinary measures” to boost the output of its three New England plants during testing.

February’s Order to Show Cause did not mention either of these allegations.

Maxim called on the commission to terminate the case, saying that if it proceeds, “OE staff will have to present its case before a neutral federal district court judge based on a novel theory, old incomplete facts and an alleged ‘omission’ that allegedly left the wrong ‘impression’ even though Maxim had no duty to disclose what was allegedly omitted and did not hesitate to provide such information when asked! And it will have to explain why the mitigation imposed over four years ago was insufficient.”

In addition to the Pittsfield plant, Maxim operates two other plants in ISO-NE: CDECCA, a 62-MW cogeneration plant in Hartford, Conn., and Pawtucket Power, a 63.5-MW cogeneration plant in Pawtucket, R.I.

PJM: PSEG’s Remedy for Artificial Island Bid Process ‘Draconian,’ ‘Self-Serving’

By Suzanne Herel

The Federal Energy Regulatory Commission should reject Public Service Electric and Gas’ claim that PJM erred in its solicitation of a stability fix for Artificial Island, the RTO said in a March 11 filing (EL15-40).

Barring that, the commission should wait to rule on the matter until PJM has chosen a bidder for the project, which it expects to do “in a matter of months,” it said.

If FERC does find merit in the complaint, PJM asked that it not adopt PSE&G’s “draconian remedy” of reposting the project, which would require the RTO to “throw out two years of PJM work.”

Artificial Island, home to the Salem and Hope Creek nuclear reactors, is the second largest nuclear complex in the country. Historically, special operating procedures have been employed to maintain stability in the area. However, according to PJM, those procedures have become increasingly difficult to implement while respecting the system’s other operational limits.

PJM issued a solicitation for a stability fix — its first competitive transmission project under FERC Order 1000 — in April 2013.

PJM staff initially selected PSE&G as the winning bidder but reopened the process after being widely criticized for its choice by losing applicants and environmentalists.

PSE&G is one of four finalists for the job, along with Transource Energy, Dominion Resources and LS Power. In January, it lodged a complaint with FERC accusing PJM of breaking its own rules in refereeing the competition by allowing contenders to modify their proposals. (See PSE&G: PJM Broke the Rules in Artificial Island Solicitation.)

In its response last week, PJM said the Artificial Island solicitation process began months before the Order 1000 procedures were finalized.

“Because the Artificial Island solicitation commenced prior to the effective date of the Operating Agreement and Tariff provisions that establish PJM’s new competitive solicitation Tariff, PJM was not bound to those provisions in conducting the solicitation,” it said.

“Instead, PJM has been conducting the Artificial Island solicitation consistently with its commission-approved transition for implementing its Order No. 1000 process.”

Even if the Order 1000 provisions were deemed to apply, PJM said, PSE&G “has not shown that PJM has acted inconsistently with its Order No. 1000 process and, similarly, has provided no basis for the drastic and self-serving remedy it seeks.”

PJM also defended its right to combine aspects of various proposals, saying that if PSE&G’s “interpretation of the Tariff were accepted, anytime that PJM cannot conclude that a picture-perfect project has been proposed that is the ‘more efficient or cost-effective’ solution, PJM must repost the violation and accept rebids or, if there is no time to repost and rebid, give a PJM-specified project to an incumbent.”

State Briefs

PSC Commissioner Nominated for Superior Court Judgeship

ClarklDelawareSourceGovJeffrey J. Clark, a Dover attorney and member of the Public Service Commission since 2005, has been nominated to fill a vacancy on the Superior Court, Delaware’s main civil and criminal trial court.

Gov. Jack Markell is expected to nominate a new commissioner for the five-member PSC if the Senate confirms Clark’s nomination. Clark, an Army veteran, received his bachelor’s degree from the U.S. Military Academy at West Point and his law degree from Widener University School of Law.

More: Delaware State News

ILLINOIS

Cleanup Continues Following Fiery Oil Train Derailment

The U.S. Environmental Protection Agency is supervising an elaborate cleanup of wetlands after a BNSF freight train hauling 103 tanker cars carrying crude oil from North Dakota derailed March 5 near the riverfront town of Galena and burst into flames, prompting an evacuation.

Twenty-one tanker cars left the track, seven ruptured, and five caught fire. Firefighters were unable at first to put out the flames and concentrated on keeping the fire from spreading. No injuries were reported.

The site is near where the Galena River meets the Mississippi and the historic home of President Ulysses S. Grant.

The accident was the latest fiery derailment of a train hauling oil from mid-continental shale fields, which are underserved by pipelines.

More: EPA

INDIANA

IPL Seeking Charges Not Recoverable in Basic Rate Case, Customers Argue

misoThe Indiana Office of Utility Consumer Counselor objects to an Indianapolis Power & Light proposal to add three rate adjustment mechanisms and new accounting treatment, which the consumer advocate says are outside the scope of a basic rate case IPL filed in December (44576).

IPL’s proposals include an “RTO adjustment.” IPL said it is being allocated $15.9 million in MISO-related MTEP 13 project costs through 2019. IPL also said in filings with the Indiana Utility Regulatory Commission that it expects to be allocated $91.7 million in Schedule 26A multi-value project costs in that time period.  Among other mechanisms, IPL seeks to create a “major storm damage reserve” account.

But the OUCC, along with industrial and consumer ratepayer groups, told the Indiana commission that such mechanisms and accounting treatment are not changes to IPL’s “basic rates and charges” and should not be included in the rate case proceeding. IPL could be forgiven for perhaps being a little rusty — it hasn’t filed a basic rate case for 20 years, not since 1995. The utility seeks an annual increase in revenues of nearly $68 million, an overall jump of 5.6%.

IPL is in the midst of several major capital projects. It’s adding $511 million in new pollution controls at its coal-fired plants. It’s building a new, natural gas-fired generating station in Morgan County. IPL also is converting some of its coal-powered units at its Harding Street station, south of downtown Indianapolis, to natural gas.

More: IOUCC

LOUISIANA

Study Cheers Anti-Net Metering Crowd, Outrages Solar Industry Proponents

A draft economic study that questions the value of residential solar tax credits is eliciting howls of protest from the state’s solar supporters.

The report, prepared by David Dismukes, a Louisiana State University economist, concludes that the state’s 50% home-solar installation tax credit cost Louisiana $89 million more than the benefits it brought. Solar advocates say the study did not consider impacts on transmission and production costs and focused only on the tax credits.

The study was released in an email blast by a pro-utility member of the Public Service Commission, Eric Skrmetta, whose re-election was strongly opposed by solar advocates. “This study is a blatant attempt to undermine the rights of Louisiana residents and to prevent the growth of the solar industry,” said Barry Goldwater Jr.,  former congressman, son of the 1964 GOP presidential nominee and solar advocate.

More: WWL-TV

MARYLAND

House Panel Rejects Tree-Trimming Restrictions

A House committee defeated legislation Friday that would have prohibited electric utilities from removing trees on private property unless they were considered hazardous and the property owner had consented. The bill also would have required utilities to comply with the International Society of Arboriculture’s “Best Management Practices for Utility Pruning of Trees.”

After the House Economic Matters defeated the proposal, the sponsor of a similar Senate bill withdrew his version of the legislation.

The bills were filed after homeowners unsuccessfully sought an injunction last fall to bar Pepco Holdings Inc. from removing trees from their properties. Pepco has defended its tree-trimming practices as an effort to comply with the state’s 2011 electric reliability law.

More: Bethesda Magazine

MICHIGAN

Lansing Joining With Developer on 20-MW Solar Project

The Lansing Board of Water and Light quadrupled the size of a proposed solar project after reviewing proposals to build a photovoltaic system on the grounds of a former GM plant.

The utility chose Vermont-based groSolar to construct the 20-MW solar farm, which initially was envisioned as a 5-MW project. “We got a whole lot of bids, there was a lot of interest,” said George Stojic, the utility’s director. “It just made sense to scale this thing up.”

The project would be built on the former Verlinden plant in Lansing.

“We are a summer-peaking utility,” Stojic said. Solar fits into that very well for two reasons, he said: “It’s there in the summertime if we need it, and it helps offset transmission costs.”

Michigan currently has 23 MW of solar generation online, none larger than 1.5 MW.

More: Midwest Energy News

MINNESOTA

Supreme Court Rules CapX2020 Tx Builders Must Buy Whole Farm

CapX2020SourceCapXThe builders of the CapX2020 transmission line – which would run from South Dakota to Minnesota – must buy an entire farm owned by recalcitrant landowners rather than simply acquiring an easement, according to the state Supreme Court.

The court ruled that a 1977 “Buy the Farm” law that requires utilities to offer to purchase entire farms when traversing properties for power lines applied to the Great River Energy project.

Landowners Dale and Janet Tauer balked at granting permission to build the transmission line through their property and argued that Great River should be forced to buy the entire farm.

More: Minnesota Public Radio

MISSISSIPPI

Former Gov. Barbour Backs Troubled Kemper Plant

HaleyBarbourSourceWikiFormer Gov. Haley Barbour, now working for an economic development firm, said Mississippi Power’s costly Kemper gasification and carbon capture plant eventually will be a valuable asset to the region.

Barbour compared the project, already years behind schedule and nearly $4 billion over budget, to the Grand Gulf nuclear generating station, which he said was delivered late and over budget but has become an economic source of base load generation. “There has been a couple of billion dollars in cost overruns,” Barbour said, “but the stockholders of the Southern Co. paid every dime of that.”

The State Supreme Court recently ordered Mississippi Power, a Southern Company subsidiary, to refund more than $200 million of a rate increase related to the Kemper project because it was improperly approved by the state Public Service Commission.

More: Mississippi Business Journal

MONTANA

Senator Writing Bill to Save Colstrip Plants from Closing

A state senator is preparing a bill that would exact a penalty from power plants near the Colstrip coal mines if they shut down, a response to legislative efforts in neighboring states to curtail the consumption of fossil fuels.

Sen. Duane Ankney, whose district borders four power plants fueled by Colstrip coal, is crafting a bill mandating the owners of a power plant that closes prematurely to pay “impact fees” for up to 20 years. “If they want to close Colstrip, then they’re going to pay,” he said. “Pay to play.”

Ankney’s proposal is a response to legislation pending in Washington state aimed at replacing fossil-fueled plants with renewable energy. Many of the Colstrip power plants are owned by utilities in the Pacific Northwest. Puget Sound Energy in Washington state denied that it planned to retire its Colstrip plant. The other owners of Colstrip plants include PPL Montana, NorthWestern Energy, Portland General Electric, Avista and PacifiCorp.

More: Missoulian

NEW YORK

Wind Power Sets New Record at 1,524 MW, 7% of NYISO Load

nyisoWind generators in the state set a record on March 2 when they churned out 1,524 MW, about 7% of NYISO’s 20,894-MW load. The previous record was 1,513 MW on Nov. 18, 2014.

“Wind power continues to grow as a power resource, and the NYISO continues to optimize our electric system’s use of renewable power,” said NYISO President and CEO Stephen G.  Whitely.

NYISO enhances its wind management system by letting wind generators submit offer prices, the first RTO in the nation to use a competitive bid process in this way. There currently is 1,744 MW of wind generation in New York, up from 48 MW in 2005. Another 2,000 MW in proposed projects is under review.

More: NYISO

NORTH CAROLINA

Duke Wants to Pay Solar Producers 15% Less on Projects 5 MW or Smaller

Duke Energy is asking the Utilities Commission to allow it to pay 15% less for the electricity it buys back from solar producers. The commission sets the price for solar every two years.

The Duke request, filed with the commission last week, is the utility’s latest effort to curb the amounts it pays solar producers. Duke pressured the commission to reduce the size of eligible projects from 5 MW to 100 kW, a proposal the commission rejected in January.

More: Charlotte Observer

Duke Fined Another $25 Million for Power Plant Ash Contamination

DukeSuttonSourceDukeThe state environmental agency assessed a record $25 million fine against Duke Energy for allowing coal ash ponds and dumps to contaminate groundwater for years.

The Department of Environment and Natural Resources sued Duke in 2013, a year before the company’s massive coal ash spill into the Dan River. That suit alleged that Duke allowed coal ash at its power plants to contaminate groundwater and waterways. Those suits remain undecided.

But the company acknowledged in late 2013 that it allowed coal ash from its Sutton plant to contaminate wells in the area, and agreed to pay up to $1.8 million for a water line to a nearby low-income community.

The water line and the fine, however, do little to ease the minds of others who may be in the path of the spreading plume of contaminated groundwater. “Until the state actually forces Duke to clean up the mess that people are sitting in right next to that plant, $25 million doesn’t mean anything to them,” said Kemp Burdette of the environmental group Cape Fear Riverkeeper.

More: Charlotte Observer

NORTH DAKOTA

Massive Wastewater Spill Spurs Move Toward Regulating ‘Gathering’ Pipelines

Legislators have introduced two bills to regulate “gathering lines” that collect oil, gas and wastewater from well sites after a ruptured pipe discharged 2.2 million gallons of salty wastewater into a creek for 12 days.

The bills call for future gathering lines to be installed with leak monitoring systems and to be secured by bonds. Gathering lines are not regulated by any state agency, nor the U.S. Pipeline and Hazardous Materials Safety Administration.

The leak of the Meadowlark Midstream pipeline near Williston contaminated a creek and two rivers before it was stopped Jan. 6. Officials say the spill doesn’t pose a health threat, and no water wells were impacted. The North Dakota Department of Health estimates it will take at least five years to clean up. The state Department of Mineral Resources is investigating why the company wasn’t using an automated leak detection system.

More: Inside Climate News; Jamestown Sun

OHIO

PUCO Approves Two 138-kV Lines for AEP Improvement Plan

The Power Siting Board of the Public Utilities Commission of Ohio approved two 138-kV transmission lines as part of a reliability improvement plan proposed by American Electric Power.

A 17.3-mile line in Ross County will connect to a new substation at Biers Run. The second project, a 19-mile line, will connect the Biers Run sub to an existing substation in Circleville. The projects are designed to improve reliability in the Chillicothe and Circleville areas.

More: Chillicothe Gazette

PENNSYLVANIA

Sunoco Withdraws Petition to Have Pipeline Declared Public Utility

Sunoco Logistics Partners LP has withdrawn the last of its petitions before the Public Utilities Commission seeking exemption from local zoning ordinances for its 300-mile Mariner East pipeline, which will carry natural gas liquids from the Marcellus Shale region.

Sunoco had sought to use its public utility status to bypass local zoning laws to build structures around 31 pump stations and valve stations on the pipeline route, which prompted a backlash from some municipalities and anti-fossil fuel activists. Now, Sunoco says it has negotiated zoning approvals or is modifying its plans to comply with local zoning regulations and no longer needs the exemptions.

Some opponents said the news represents a victory. Sunoco began pumping propane through the pipeline in December and says it is on schedule to install the pumping capacity to deliver 70,000 barrels of ethane, propane and butane later this year.

More: The Patriot-News

PUC Approves PPL’s Spinoff of Generating Units to Form Talen

pplThe Pennsylvania Public Utility Commission approved the spinoff of PPL Corp.’s generation and pipeline assets.

The greenlight resolves one regulatory impediment to the move, which involves the combination of PPL’s assets with those of Riverstone Holdings LLC into a new publicly traded entity, Talen Energy Corp. PPL shareholders will own 65 percent of Talen.

PPL Electric Utilities, which provides electric distribution service to approximately 1.4 million customers in Pennsylvania, is not affected by the transaction.

More: PPL; The Morning Call

VIRGINIA

Dominion Slammed for Trying to Shield Information from Audits

State officials turned down a request from Dominion Virginia Power to keep some financial information secret during an upcoming public review.

Dominion made the request just weeks after the General Assembly took away the State Corporation Commission’s authority to order customer rate cuts or refunds through 2022. Opponents said that Dominion’s request reinforced their fears that that the utility would use the legislation to hide certain financial information, despite a vow from the company that its filings would be transparent.

The SCC ruled against Dominion’s request and ordered the company to submit a complete financial filing in time for its 2015 review. Dominion said it would comply.

More: Washington Post

WEST VIRGINIA

Gov. Signs Bill Giving Legislature Final Say in Clean Power Plan

tomblin
Tomblin

West Virginia is coming up with its own plan to meet emissions reductions proposed by the Environmental Protection Agency’s Clean Power Plan. But the state Legislature, not state environmental regulators, will have the final say.

Gov. Earl Ray Tomblin last week signed H.B. 2004, taking away the rule-making role from the state Department of Environmental Protection.

The move was lauded by the coal industry. “This law will ensure West Virginia’s elected officials have a say in the regulations that ultimately impact their state’s families and businesses,” said Mike Duncan, president and CEO of the American Coalition for Clean Coal Electricity. “Legislation like H.B. 2004, as well as similar actions by other state Legislatures, underscores broad opposition across the country to EPA’s overzealous and illegal proposal.”

More: State Journal

Compiled by Ted Caddell

Eversource to Sell New Hampshire Plants

By William Opalka

eversourceEversource Energy will sell its New Hampshire power plants to satisfy regulators’ divestiture demands and resolve a long-standing dispute over how much it should recover from ratepayers for pollution controls on its largest coal-fired generator.

Under an agreement announced Thursday, Eversource’s subsidiary, formerly “Public Service of New Hampshire,” will seek to sell three fossil fuel plants and nine hydroelectric stations, exiting the power generation market in the state. Eversource said it will join the state’s other utilities in purchasing energy on the open market.

Legislation enacted last year directed the state Public Utilities Commission to investigate ways to expedite the company’s sale of its electric generation as a means to develop energy markets and save consumers money.

An April report by the PUC said that the plants had a book value of $660 million but could only expect to bring in $225 million in any sale.

Eversource and state negotiators said the agreement will save consumers $300 million over the next five years due to securitization of those stranded costs. Realizing the savings will require legislation approving low-cost bond financing.

The settlement also resolves the long-standing issue over pollution upgrades made to the 439-MW Merrimack Station in Bow. Eversource agreed to forgo recovery of $25 million of the $422 million it spent on a scrubber on the 55-year-old generator.

The PUC in 2011 authorized a temporary charge of $0.98/kWh while the case remained on its docket, but the charge was insufficient to cover the entire cost of the scrubber. The PUC late last year was prepared to enter an order determining how the costs would finally be split when legislators and the company requested a delay to continue negotiations. The PUC agreed to the delay but denied a PSNH request to stay the divestiture proceeding.

“This agreement represents an opportunity to create real savings for PSNH customers, avoids protracted litigation with uncertain outcomes for all parties and moves the operation of PSNH generating plants to competitive markets rather than remaining an ongoing ratepayer obligation,” said Senate Majority Leader Jeb Bradley, who led the negotiations with the company.

In addition to Merrimack, the sale includes the 400-MW oil-gas Newington Station, built in 1974, and the 63-year-old 150-MW Schiller Station in Portsmouth, which burns coal, oil and biomass. The nine hydroelectric plants total 69 MW.

The agreement also includes a freeze on distribution rates through July 2017, and requires the plant buyers to honor current collective bargaining agreements and to keep the plants in operation for 18 months.

The agreement also calls for three years of property tax stabilization payments if a plant sells for less than its assessed value.

Eversource shareholders will also provide $5 million to capitalize a clean energy fund, which will target investments in energy efficiency and distributed generation projects.

The deal disappointed the New Hampshire Sierra Club, which sought the closure of Merrimack. Marc Brown, president of the New England Ratepayers Association, said he feared savings from the plants’ sale would be short-lived and that prices will rise as the state becomes more reliant on natural gas-fired generation.