October 30, 2024

NJ Shoots for 4 GW+ in 3rd OSW Solicitation

New Jersey is seeking projects totaling 1.2 to 4 GW — and potentially larger — in the state’s third offshore wind project solicitation planned for early 2023, according to a draft document released by the New Jersey Board of Public Utilities (BPU) on Thursday.

The Solicitation Guidance Document seeks proposals that are significantly larger than in the first two solicitations, which awarded projects totaling 1.1 GW and 2.658 GW, and expands the state’s already aggressive effort to become a key player in the growing offshore wind sector. The document presents a new solicitation schedule shaped to accommodate Gov. Phil Murphy’s decision in September to increase the state’s OSW target capacity from 7.5 GW by 2035 to 11 GW by 2040.

“The board seeks to promote robust competition in this third solicitation and future solicitations to support the continued development of the offshore wind industry in New Jersey,” the draft says.

The new schedule envisions four more solicitations after the third one next year, with each additional solicitation expected to award capacity of about 1.2 GW, though the BPU “may award projects above or below the target.”

The first project is expected to come online in the 2024-2025 period, with the final project up and running by 2038. The draft says that for the 2023 solicitation, the BPU “reserves the right to select less than 1,200 MW or more than 4,000 MW of qualified projects if circumstances warrant.”

The BPU will seek stakeholder input on the draft solicitation at a public hearing on Dec. 13.

Building an Industry

The requirements set out in the draft solicitation for project applicants show that New Jersey is looking to build upon the state’s OSW infrastructure already in development.

New Jersey awarded its first offshore wind project, the 1.1-GW Ocean Wind 1 developed by Denmark-based Ørsted, in 2019, and in 2021 awarded two more: the 1.148-GW Ocean Wind 2, and the 1.51-GW Atlantic Shores project, developed by a joint venture between EDF Renewables North America and Shell New Energies US. (See NJ Awards Two Offshore Wind Projects.)

The state has accompanied the project awards with an effort to position itself to serve other parts of the East Coast offshore wind sector by developing a logistics, marshalling and manufacturing hub. The heart of the effort is the development of what New Jersey officials say is the first custom-built wind port in the nation, committing $478.2 million to the project with bonding for another $160 million underway.

The wind port, located at Alloways Creek in Salem County, will include a 30-acre marshalling area for component assembly and staging; a dedicated, overland, heavy-haul transportation corridor; and a heavy-lift wharf with a dedicated delivery berth and an installation berth that can accommodate jack-up vessels. (See NJ Wind Port Draws Heavy Hitters.)

The BPU on Oct. 26 approved the expenditure of $1.07 billion for transmission upgrades to deliver 6,400 MW of OSW generation to the grid. The BPU picked the projects — the largest of which is an onshore substation known as Larrabee Tri-Collector Solution — from among 80 proposals submitted by 13 developers in response to a solicitation issued by PJM under FERC Order 1000’s State Agreement Approach. (See related story, FERC Approves PJM Tariff Revisions for SAA Cost Allocation.) However, the BPU largely awarded contracts for onshore work and left the offshore infrastructure mostly unallocated.

The draft solicitation seeks to fill that gap by requiring applicants to outline a “prebuild infrastructure” that would interconnect with the recently approved onshore infrastructure. Applicants would have to provide plans to build duct banks and access cable vaults for transmission to run to onshore interconnection points.

“Developers of future qualified projects would then install their cables through the prebuilt duct banks utilizing the prebuilt cable vaults, with minimal further disruption to the communities” around the interconnection points, the solicitation says.

Qualified project connections (NJ BPU) Content.jpgDiagram of qualified project connections to point of interconnection (POI) with and without prebuild | NJ BPU

 

Economic Impact

The solicitation also seeks to generate a range of project alternatives, requiring applicants to submit at least one 1.2-GW project while adding that they are “highly encouraged to submit applications covering a range of project sizes up to approximately 4,000 MW.”

Applicants would have to submit a package with a completed application form and an explanation of their project, as well as an in-depth analysis of its economic impact on the state. They would have to detail the “proposed investment in New Jersey offshore wind infrastructure, supply chain, labor force development” and other investments. They would also have to outline the economic development impact on communities in the state and provide detailed job creation information, including location, types and number of jobs it would generate, and wage or salary levels.

The proposal must also say whether the planned project will use the New Jersey Wind Port or “alternative infrastructure” located in the state or elsewhere.

“The BPU encourages use of the New Jersey Wind Port for project marshalling and for locating Tier 1 manufacturing facilities, where feasible,” the solicitation says.

The heart of the application, however, is the cost of the project and its underlying economics. Applicants must set out the level of the OSW renewable energy certificate (OREC) at which the developer believes the project would be commercially viable.

“OREC pricing will be on a pay-for-performance basis,” the solicitation said. “Payments will be made on a dollar-per-megawatt-hour basis.”

The OREC must reflect the total capital and operating costs for the project over 20 years, “including costs of equipment, construction, financing, operations and maintenance, and taxes,” offset by any state or federal grants or subsidies, according to the draft solicitation. “The OREC pricing proposal shall specify the nameplate capacity, expected energy output and assumed capacity factor for the proposed project, along with the number of ORECs that the project will produce.”

Climate Activists Take Over Small Piece of ISO-NE

Climate activists managed to successfully take over a small piece of ISO-NE last week, winning control of a significant portion of the committee that controls the grid operator’s official platform for interacting with the public.

Six activists organized by the anti-fossil fuel group No Coal No Gas were elected to two-year terms on the Consumer Liaison Group’s (CLG) Coordinating Committee on Wednesday, securing a say in how the group operates, as ISO-NE officials looked on with what one attendee described as “grim” faces.

While the CLG carries little formal power, it’s an important (and FERC-mandated) piece of how the grid operator communicates with the public. CLG holds four meetings a year, which provide a rare opportunity for the public to hear from and interact with high-level officials at ISO-NE and other key energy policymakers in the region.

Climate advocacy groups in New England have criticized how ISO-NE conducts its work, calling out the organization for policies they say are maintaining the grip of fossil fuels on the region’s grid and hampering the clean energy transition.

No Coal No Gas built support for a slate of candidates and encouraged its members to attend last week’s meeting and vote. More than 100 members of the advocacy group attended the meeting.

Nathan Phillips, a Boston University ecologist from Newton, Massachusetts, was one of the activists who was elected.

“It was the incredible feeling of being in the belly of the beast but having a hundred friends who had your back,” he told RTO Insider. “It felt like democracy. It felt like people power.”

No Coal No Gas laid out its plan in the weeks before the meeting in emails to members.

“We believe that the CLG could be a more productive forum and a space to build power among communities and ratepayers from across New England who are advocating for themselves regarding electricity (how it is generated, the cost, how the markets are structured),” the group wrote.

The group’s priorities include more closely connecting CLG’s work to people in New England who are, for example, struggling to pay their energy bills.

If they have their way, the forum’s name might also change.

“I think it should be called the Ratepayer Liaison Group,” said Phillips “It became apparent to me in the meeting, the words and the language matter.”

To him, the term “ratepayers” gives more agency and power to the people it’s describing than “consumers.”

“Until now, the CLG has mostly been a space where ISO-NE presents to the public about what they are doing. There has been little actual input from the public, and even less from everyday ratepayers and environmental justice communities,” No Coal No Gas told its members ahead of the meeting.

The other activists elected were Sonja Birthisel, a University of Maine researcher and nonprofit director; Kendra Ford, a Unitarian Universalist minister from New Hampshire who recently made a strong impression at ISO-NE’s public board meeting; Regine Spector, an associate political science director at the University of Massachusetts, Amherst; Ian McDonald, an activist from Killingly, Conn.; and Jacob Powsner, co-owner of a farm in Rutland, Vt.

Two incumbents were ousted from the committee: Associated Industries of Massachusetts executive Robert Rio and former Harvard University energy supply official Mary Smith.

Along with allies from state consumer advocacy offices and environmental groups who make up several incumbents on the committee, the group pushing for change has gained a majority.

“It will now be much harder for ISO New England to keep the CLG from getting feisty,” wrote Donald Kreis, New Hampshire Consumer Advocate and an incumbent who was re-elected. (Kreis has called for the CLG to be abolished altogether.)

ISO-NE spokesperson Matt Kakley said in an email to RTO Insider that the grid operator is “pleased to see the increased interest in the Consumer Liaison Group and hope people continue to attend meetings, gain insight into the regional energy landscape, and engage in the discussions.”

Solar Industry Pushes for Bigger Incentives from NJ Program

Solar advocates last week urged the New Jersey Board of Public Utilities (BPU) to maintain or increase the incentives offered for new solar installations under the state’s Administratively Determined Incentive (ADI) Program.

As part of the Garden State’s 2021 Successor Solar Incentive (SuSI) Program, the BPU is required to conduct a reevaluation of SuSI incentive levels after the first year of its implementation. The ADI half of the program targets net metered residential, community solar projects and net metered non-residential projects under 5 MW. The second prong, the Competitive Solar Incentive (CSI) program, creates a competitive bidding process for solar renewable energy credits for their projects.

The BPU could recommend changes to the incentive levels, the share of incentives available to each block of eligible projects or other program rules based on public comment, modeling done by the Cadmus Group, and other factors. Written comments can be filed on the board’s Public Document Search page until 5 p.m. on Dec. 9 under Docket QO20020184.

While the program is on target to meet its net metered residential goal of 150 MW subscribed, it has struggled to attract non-residential and interim subsection grid investments, the latter of which consist of solar installed on brownfield, infill or landfill sites. Of the nearly 289 MW available for net metered non-residential, less than 55 MW was subscribed as of Nov. 10, while just one application has been received for the interim subsection market segment, accounting for a bit more than 5 MW of the 75 MW available.

The BPU says the significantly higher incentives offered under the state Transition Incentive Program likely account for the lackluster interest in net metered non-residential installations under than the ADI program. 

At a stakeholder meeting hosted by the BPU Friday, Scott Elias, director of Mid-Atlantic state affairs for the Solar Energy Industries Association, said most of the non-residential developments that have come online did so under the TI program. However, he believes the “market underperformance” of the ADI is also due to historic price increases in the industry and commercial incentives being too low.

“It’s critically important for the BPU to pay attention to some of the justifications for increased incentive levels,” Elias said. “This year was successful from a solar installation point of view, but most, if not all, of those installations coming online are from the TI program, not the ADI program, and the long-term health of the New Jersey solar industry and our ability to meet New Jersey’s ambitious solar goals are really contingent upon the health of the ADI program.”

Elias noted that, since the start of 2021, costs for commercial installations have increased 15% while residential costs have gone up 12%, largely due to shipping constraints and other supply chain issues stemming from the pandemic and trade instability. He said those factors should be incorporated into the modeling done by the Cadmus Group, which is used to generate a report the BPU relies on to set its incentives. He recommended that the BPU increase incentives for the non-residential segment and at least maintain them at current levels for residential.

“The residential sector is the only sector performing well right now. But labor rates for the residential segment are increasing due to skilled labor shortages, and increased module pricing is increasing residential system prices. And that alone justifies increasing the incentive level — or at the very least maintaining the incentive level, which is my recommendation,” Elias said. “I want to be clear that it would be a mistake if the BPU reduced the residential solar incentive to moderate market activity and throttle development to avoid reaching arbitrary market segment allocation.”

‘So Many Variables’

Fred DeSanti, executive director of the New Jersey Solar Energy Coalition, said he trusts Cadmus to identify proper figures and metrics for its recommendations to the BPU, but he’s concerned the board will choose to throttle residential incentives to push for the rate of installations under the program to remain at the target. He encouraged the BPU to find a flexible approach in the middle of the two options of reducing incentives or leaving them in place and closing the market when subscriptions reach the 150-MW mark.

“That’s of great concern to me because nobody knows what the build rate’s going to be next year. Nobody knows if a recession’s going to come,” DeSanti said. “There’s so many variables out there that no one can predict accurately. I really am concerned about the fact that we could end up getting to a tipping point” with large-scale layoffs for residential solar companies.

Kyle Wallace, vice president of public policy and government affairs at PosiGen, shared those concerns, saying the Cadmus models seem reasonable and aligned to what he’s been seeing in the residential market, with cost estimates increasing 10% to 20% to reflect the rising costs of capital and labor.

“I’m a little concerned now that we’re seeing that success and, from what I see, the ADI succeeded in a lot of its objectives on the residential side. And now we’re seeing that success as kind of a problem and we need to throttle that back,” he said.

The scale of incentives provided to solar projects has long been a point of contention in the formation of New Jersey’s clean energy initiatives, with developers arguing they’re too low compared with past programs and the state Division of Rate Counsel arguing they’ve tilted too far in favor of developers. The SuSI program combines incentives set at rates determined by the BPU with competitive solar renewable energy certificates through the CSI program to reduce the cost to ratepayers while still advancing the state’s aggressive solar goals. (See Proposed NJ Solar REC Program Wins Initial Support.)

Though the state remains behind on reaching its goal of 12.2 GW in solar capacity by 2030, the pace of development has picked up. The state reached a 4 GW milestone in July and as of Oct. 31 had increased to 4.2 GW, according to the latest figures from the state’s Clean Energy Program. (See NJ Faces Challenges as Solar Sector Hits 4 GW.)

New York State Clean Energy Jobs Hit Record High in 2021

New York’s clean energy sector reached record-high employment in 2021, rebounding from the COVID-19 pandemic much further than the general workforce.

The 2022 New York Clean Energy Industry Report, released last week by the New York State Energy Research and Development Authority, paints clean energy as one of the fastest-growing job classifications in the state.

From 2016 to 2021, the number of people working in such jobs increased 13%, and the number full-time equivalents rose 33%, meaning that not only are there more people working in the field, more of them are devoting all of their time to clean energy-related work.

The NYSERDA report counts 165,055 people working in clean energy statewide in December 2021, 0.8% higher than in December 2019, shortly before the pandemic caused the temporary or permanent loss of 2 million jobs statewide.

The New York State Department of Labor meanwhile counted the statewide nonfarm workforce at 9.29 million in December 2021, down 5.3% from December 2019.

The state’s general workforce has regained additional jobs in 2022 but as of October was still 2.7% below its pre-pandemic total.

With all the policy initiatives and funding being directed to the energy transition this year, it is likely that the clean energy workforce grew again in 2022.

NYSERDA President Doreen Harris said the numbers showed progress not only toward the state’s decarbonization goals but toward building a green economy that benefits the state and its residents.

“We are leading the way with an orderly and equitable transition so that all New Yorkers can participate in our clean energy future, while creating family-sustaining jobs and providing meaningful economic opportunities for our communities all over our great state,” she said in an introduction to the report.

The Alliance for Clean Energy New York, whose member organizations are doing some of the hiring reflected in the NYSERDA report, said the news was good but not surprising.

“The solar and building efficiency sectors are bouncing back after the pandemic, and investment in New York continues,” ACE NY President Anne Reynolds said.

“The report also shows over $10 billion in investment over the last 10 years, and we hope and expect that job growth will continue as more wind and solar power projects reach construction in the coming year. The offshore wind sector and the clean vehicle sectors are especially promising, and we applaud and support efforts to build a clean energy supply chain in New York.”

Details and Statistics

Delving into the report, several details jump out:

  • Some of the biggest job gains were in solar power and in alternative transportation such as battery-electric and hybrid-electric vehicles, registration of which has increased fivefold in five years in New York.
  • Clean-energy installation firms saw the largest job loss when the pandemic hit and the largest rebound as it began to ease.
  • Energy efficiency is the only clean-energy subsector in which employment had not recovered to pre-pandemic levels by the end of 2021, with lighting and HVAC lagging furthest behind.
  • Clean-energy work was credited in the report with supporting the net creation of 13,010 jobs outside the field in 2021, with employers as diverse as software developers, civic organizations and wholesalers expanding their payrolls.

The actual size of the clean-energy workforce in New York at the end of 2021 was likely larger than indicated in the report: The authors note that jobs in nuclear power or electric transmission, while clean and/or integral to the clean-energy transition, are not explicitly labeled “clean” and therefore were not counted.

Other workers split their time between “clean” and “other” duties; work in uncategorized technologies; or work for companies that did not supply information. They also were not counted as “clean.”

Clean energy job growth in New York is expected to ramp up as billions of dollars are spent annually on infrastructure.

Potential Shortcomings

The job growth and the surrounding details are not without some caveats.

The Just Transition Working Group of the New York State Climate Action Council projects an increase of 211,000 clean energy workers from 2019 to 2030, countered by a loss of 22,000 jobs in job sectors that shrink as a result of clean energy’s growth.

The final scoping plan being prepared by the council is expected to address ways to help those displaced workers transition to new jobs.

NYSERDA’s report notes a significant loss of “traditional energy” jobs from 2019 to 2021 but does not ascribe this to the pandemic, the rise of clean energy or any other cause.

Before the pandemic, from 2016 to 2019, the traditional energy workforce in New York showed minor growth (4%) even as the clean energy workforce racked up a 16% gain. However, the traditional energy workforce shrank 14% in 2020 and nearly 1% in 2021 for a total two-year loss of 14.7%, which the clean-energy workforce saw a net 0.8% gain in the same two years.

The NYSERDA report flags other potential sticking points as New York’s government and industries attempt to expand the green workforce.

Nine in 10 employers had difficulty hiring in 2021, particularly in the energy-efficiency field. Workforce shortage already is an issue in New York, which has a lower labor participation rate — the percentage of civilian residents aged 16 and older who are employed or seeking employment — than most states: 60.3% in July 2022, compared with 62.1% nationwide.

Some members of the new green workforce will need specialized skills gained through extensive training and experience. For example, in 2030, New York expects it will need 6,000 people working in offshore wind, an industry that barely exists in the U.S. Two recent studies by the National Renewable Energy Lab lay out the disconnects reported by would-be employers and by would-be employees as they attempt to close the workforce gap.

Meanwhile, other states with ambitious climate-protection goals of their own will be competing for the same workforce; the final scoping plan is expected to acknowledge this and attempt to address it.

NYSERDA meanwhile has committed to spending more than $120 million to address the need for skilled workers, partnering with numerous organizations to create a pipeline for a workforce ranging from entry-level to highly skilled. New York is also creating multiple pathways for traditionally underrepresented groups to be part of the clean-energy transition, as employees or entrepreneurs.

Finally, the report says there needs to be a continued stream of money to make all this happen. It notes that 81% of the $11 billion invested in New York’s clean energy industry came through the public sector from 2011 through 2021, jumping to 91% public-sector funding in 2019-2021. A major infusion of federal money through the Inflation Reduction Act and other streams is expected in the coming years.

Data for the NYSERDA report were drawn from the U.S. Energy and Employment Report, in which more than 1,900 businesses participated. The margin of error is 2.23% at a 95% confidence level.

Duke: NC Outages from Attacks May Last Until Thursday

More than 33,000 customers remained without power Monday afternoon in Moore County, N.C., following apparent attacks on two of Duke Energy’s (NYSE:DUK) substations over the weekend, and the company said some customers may not see their electricity restored until Thursday.

Ronnie Fields (WRAL-TV) Content.jpg

Moore County Sheriff Ronnie Fields at a press conference Sunday afternoon

| WRAL-TV

The outages began near the town of Carthage about 7 p.m. Saturday. They “shortly thereafter … spread to the greater majority of central and southern Moore County,” Sheriff Ronnie Fields said in a press conference Sunday afternoon. At the height of the outages, more than 45,000 customers had lost power, Duke said in a press release on Sunday; the utility’s outage map has been updated since then to reflect the restoration of some customers as crews work in 24-hour shifts, Duke confirmed to RTO Insider.

‘Pretty Sophisticated Repair’

Crews and sheriff’s deputies investigating the outages discovered “extensive damage” to two substations. Fields said the deputies found evidence indicating that firearms had been used to disable the facilities with “multiple shots” fired by attackers who “knew exactly what they were doing.” Duke said parts of the substations had been damaged “beyond repair,” requiring technicians to completely replace the affected equipment.

Duke spokesperson Jeff Brooks said at Sunday’s press conference that “we are looking at a pretty sophisticated repair with some fairly large equipment,” and that Duke is “pursuing multiple paths of restoration [to] restore as many customers as possible, as quickly as possible.”

The county implemented a 9 p.m.-5 a.m. curfew Sunday night “to best protect our citizens and … businesses of our county,” Fields said. Additionally, most county operations were shut down on Monday except emergency services, along with limited transportation for medical needs. County Manager Wayne Vest said that the county would probably be working “a skeletal operation” through Monday and hope to “get back up to full speed” by Wednesday.

“We faced something [Saturday] night here in Moore County that we’ve never faced before, but I promise you we’re going to get through this, and we’ll get through it together,” Fields said at the press conference. “We’re very united here in Moore County, and we’re not going to let this hold us back, and I can promise you, to the perpetrators out there, we will find you.”

No Known Motivation

Law enforcement has not publicly identified any culprit or motivation for the attacks so far. Fields said that “every available officer” in his office is doing “what we can to try to determine what happened,” with municipal and state officials contributing to the effort, along with the FBI.

The Electricity Subsector Coordinating Council (ESCC) said in a statement Monday that it was “working closely with … law enforcement officials” in their investigation into the attacks. Participants in an ESCC-hosted conference call Monday night included FERC Chairman Richard Glick; Brandon Wales, executive director of the Department of Homeland Security’s Cybersecurity and Infrastructure Security Agency; and Deputy Energy Secretary David Turk.

The ERO Enterprise has also mobilized in response to the incident. SERC Reliability CEO Jason Blake said in a statement that the regional entity is “in close coordination” with Duke, NERC, federal agencies and “appropriate industry members across our 16-state footprint [so that] information is shared as it becomes known and that utilities across our footprint are in a heightened security posture.”

Asked about online rumors that the attacks were meant to shut down a local drag show that was planned to occur Saturday night, Fields said that while “anything’s possible,” the office had “not been able to tie anything back” to the show. Calling the perpetrators “cowards,” he acknowledged that no person or group had stepped forward to take responsibility for the attacks, adding that while the targeting of the power grid “wasn’t random,” he could not say at this point whether the incident should be considered an act of domestic terrorism.

The suspected connection to the drag show was apparently strengthened by a series of provocative Facebook posts by Emily Grace Rainey, a self-proclaimed conservative activist living in Moore County who served in the U.S. Army before resigning amid an investigation of her participation in the Jan. 6, 2021, attack on the U.S. Capitol.

Before the outage began, Rainey had posted the contact information of the drag show’s sponsors, adding, “You know what to do.” After the outage started she wrote, “The power is out in Moore County, and I know why,” later posting a picture of the theater where the show was supposed to be held with a caption saying, “God will not be mocked.”

However, Fields said on Sunday that while deputies had interviewed and “had a word” with Rainey, the lead “turned out to be nothing.” He urged citizens not to post false information online, reminding listeners that it “takes time for us to run that down.”

History of Physical Security Threats

The idea of domestic terrorists attacking the power grid has gained credibility in recent years, especially following the announcement in February that three men had pleaded guilty to planning to damage substations with high-powered rifles. (See FBI: Conspirators Planned Grid Attack to Start Race War.) According to their confessions, the men hoped to spark “confusion and unrest” that would lead to a civil war, inspired by “racially or ethnically motivated violent extremist views.”

The tactics of Saturday’s incident also resemble those of the 2013 attack on Pacific Gas and Electric’s Metcalf substation near San Jose, Calif. In that event, whose perpetrators have never been identified, snipers fired an estimated 150 rounds at transformer radiators in the facility, hitting 10 of the 11 targets and resulting in the loss of about 52,000 gallons of cooling oil. (See Substation Saboteurs ‘No Amateurs’.) The attackers are also believed to have cut underground fiber optic cables near the substation, temporarily disabling phone and 911 service for the area.

Physical security for bulk electric system facilities is addressed in NERC’s Critical Infrastructure Protection (CIP) reliability standards, most notably CIP-014-3 (Physical security), the first version of which was introduced two years after the Metcalf attacks. Asked about security preparations at Duke’s substations on Sunday, Brooks said that “we take security extremely seriously” and that the utility was confident its security requirements were in place at the affected facilities.

“We understand that we’re critical infrastructure, and so we do incorporate multiple layers of security at all of our facilities and across our system to help protect the grid and … restore power when we have disruptions,” Brooks said. “We can’t provide specific information on security measures at a critical facility, but I can say that certainly we’re one of the most highly regulated industries in the country. There’s a lot of protocols around security that we follow, and we believe we followed those in this case.”

FERC Approves PJM Tariff Revisions for SAA Cost Allocation

FERC on Friday approved revisions to PJM’s tariff that assign the full costs of constructing transmission upgrades necessary for the installation of 7,500 MW of offshore wind in New Jersey to the state (ER22-2690).

The commission affirmed that the proposal conforms with Order 1000’s State Agreement Approach, which permits a state to take on the cost of transmission upgrades for generation projects supporting their public policies. The order allows the installation of an estimated $1.07 billion in grid upgrades to go forward.

FERC found that the tariff revisions would not result in costs being passed to customers outside New Jersey, a concern raised by Long Island Power Authority; New York Power Authority; and three merchant transmission facilities (MTFs), Neptune Regional Transmission System, Linden VFT and Hudson Transmission Partners, which filed a protest as the “MTF Parties” on Oct. 31. (See NY Stakeholders Balk at NJ OSW Cost Allocation.)

The groups argued that the proposed language left open the possibility that a portion of the costs could be indirectly passed on to New York customers through border rate service. They called for more explicit clarifications to be added to preclude that possibility and specify that costs can only be applied to firm point-to-point transmission service.

The commission ruled that PJM adequately addressed those concerns in the revisions, as well as in a settlement agreement that FERC approved the same day between the RTO, its TOs and the MTF Parties, pertaining to point-to-point border rates (ER19-2105).

“We do not agree with MTF Parties that the crediting under the border rate revenue requirement, as proposed in the border rate settlement, may still result in New Jersey SAA project costs being passed through to entities that did not voluntarily agree to pay for those costs,” the commission said. “The border rate settlement specifically provides that the revenue requirement will not include the costs of state agreement public policy projects. Passing on such costs would violate that term.”

The order was unanimously approved, though Chair Richard Glick did not participate. Commissioner James Danly wrote in a concurring statement that he believes the order addresses the MTF Parties’ concerns, but if they continue to believe there are issues with the approved revisions, they should seek a rehearing.

“To the extent to which the MTF Parties find that the language set forth in today’s order fails to allay their concerns, they should pursue rehearing by citing the specific tariff language to which they object and should enumerate the specific misinterpretations that they fear, along with the consequences of those misinterpretations,” he wrote.

The FERC approval now allows for PJM and the New Jersey Board of Public Utilities to shift their attention to filing amendments to the SAA. During a Nov. 4 meeting of the PJM Transmission Expansion Advisory Committee, Assistant General Counsel Pauline Foley said filing those amendments with FERC first required the approval of a cost allocation methodology from the commission.

Solar Industry Slams Commerce Decision Extending Solar Tariffs

Criticism from the U.S. solar and clean technology sector was almost instantaneous on Friday after the Commerce Department issued a preliminary decision that could extend tariffs on solar cells and panels imported from 22 companies in Cambodia, Malaysia, Thailand and Vietnam.

According to a Commerce Department investigation — begun in February after a complaint from Auxin Solar, a U.S. manufacturer — those companies are using key components from China in a way that allows them to circumvent existing tariffs, called anti-dumping and countervailing duties (AD/CVD).

Four companies — New East Solar in Cambodia; Hanwha Q Cells and Jinko Solar Technology in Malaysia; and Boviet Solar Technology in Vietnam — were found not to be circumventing and are exempted from the duties. Other companies can avoid the tariffs through a certification process.

Abigail Ross Hopper, CEO of the Solar Energy Industries Association (SEIA), called the preliminary decision “a mistake we will have to deal with for the next several years.”

While “Commerce didn’t target all imports from the subject countries,” Hopper said, “this decision will strand billions of dollars’ worth of American clean energy investments and result in the significant loss of good-paying, American, clean energy jobs.”

US Solar Imports (ClearView Energy Partners) Content.jpgU.S. solar product imports by exporting nation. The Commerce Department preliminary decision could result in tariffs on these imports. | ClearView Energy Partners

 

Following industry outcry about the investigation, President Biden ordered a two-year moratorium on AD/CVD on solar cells and panels from the four countries, which will end in June 2024. But, Hopper said, even that breathing space “is simply not enough time to establish manufacturing supply chains that will meet U.S. solar demand.”

Gregory Wetstone, CEO of the American Council on Renewable Energy, also called the decision “a major step backward.”

The preliminary decision “creates new challenges that threaten to undermine Biden administration efforts to address climate change and accelerate the clean energy transition,” Wetstone said. “The Commerce Department appears to be doubling down on constricting solar availability and imposing massive new red tape with certification requirements that could further chill the industry and thwart the administration’s clean energy objectives.”

Others, like JC Sandberg, interim CEO of the American Clean Power Association, argued that the tariffs would undercut efforts to build out a domestic supply chain for solar, including the tax credits for solar and other clean energy manufacturing in the Inflation Reduction Act.

“American solar companies are making critical 2024 procurement decisions now, and today’s decision casts greater uncertainty about the future of the solar industry in the U.S. that could lead to higher electricity bills,” Sandberg said.

Not all reactions were negative. Michael Stumo, CEO of the Coalition for a Prosperous America, a nonprofit focused on trade issues, welcomed the decision as “an important win for the rule of law” and criticized Biden’s tariff moratorium.

“At a time when American manufacturers are investing billions of dollars to boost domestic production as a result of the Inflation Reduction Act, it is unconscionable that the White House wants to continue to give Chinese manufacturers a pass for illegally violating U.S. trade law to the detriment of American companies and American workers,” Stumo said.

The Commerce Department will be verifying the information in the preliminary decision and accepting comments from industry stakeholders, according to a Friday press release. A final decision is now scheduled for May 1, 2023.

‘Minor or Insignificant’

The Commerce Department first slapped tariffs on Chinese solar panels in 2012, siding with U.S. solar companies that argued that Chinese companies, heavily subsidized by the Chinese government, were undercutting domestic manufacturers and dumping cheaper panels in the U.S. market. Tariffs — from 31 to 250% at the time — would level the playing field and spur the buildout of a domestic supply chain, they argued.

Ten years on, solar manufacturing has migrated to Cambodia, Malaysia, Thailand and Vietnam; the solar industry and federal government continue to fight over solar trade policy, and the U.S. still does not have a comprehensive domestic supply chain. In 2018, former President Donald Trump expanded the Chinese tariffs to the four Southeast Asian countries, where solar panels are manufactured using Chinese components. Biden decided in February to continue the tariffs, later adding the two-year moratorium.

Arguments for and against the current decision hinge on differing perceptions of the manufacturing processes occurring at solar companies in the four countries, the extent of Chinese involvement and the U.S. solar industry’s ability to build out a comprehensive domestic supply chain.

According to industry analysts ClearView Energy Partners, the preliminary decision reflects the Commerce Department’s “protectionist leanings.” The decision generally concludes “that the value of the merchandise produced in China before it was sent to the Southeast Asian nations represented a ‘significant portion of the total value’ of the final product exported to the U.S.,” ClearView said in a research note released Friday.

Further, Commerce said, the processes for assembling and completing cells and panels in these countries were “minor and insignificant,” according to ClearView.

As outlined in the preliminary decision, Commerce based its findings on information gathered in response to questionnaires sent to companies in the four countries. Companies that did not provide the information requested on time and “failed to cooperate to the best of their abilities” were subject to an “adverse inference” that they were circumventing the AD/CVD tariffs.

But SEIA’s Hopper said Commerce had “elected to exceed its legal authority. As a basic fact, solar cell and module manufacturing greatly exceed the anticircumvention statute’s ‘minor or insignificant processing’ limitation.”

George Hershman, CEO of SOLV Energy, a utility-scale solar installer, also argued that the processes being penalized in the decision are the same as those the IRA seeks to incentivize. The preliminary decision is “inherently hypocritical” and “doesn’t pass the common sense test,” Hershman said.

“This ruling will further constrict a challenged supply chain and undercut our ability to fulfill the promise of the Inflation Reduction Act,” he said.

ClearView agreed the decision “could add to solar product trade risk.”

IRA tax incentives could “encourage domestic manufacturing, but our review of solar products demand and recently announced U.S. investments suggests the U.S. market is likely to remain partially reliant on imported solar modules and heavy reliant on overseas solar supply chains after the AD/CVD might take effect,” ClearView said.

New solar installations in the U.S. hit 18.9 GW in 2021, ClearView said, and the U.S. Energy Information Administration expects that number to more than double, to 39.7 GW in 2023.

Exceptions 

In a report released in August, SEIA predicted that building out a full domestic supply chain for all solar components, from polysilicon wafers to inverters, could take five years or longer. The group is targeting a U.S. supply chain capable of producing 50 GW of “domestic solar manufacturing capacity” by 2030.

Domestic supply chains for solar (SEIA) Content.jpgSEIA projects the U.S. can build out key domestic supply chains for solar by 2027. | SEIA

 

According to the report, “the United States currently has no domestic solar ingot, wafer or cell manufacturing capacity and only modest capacity to produce solar modules, inverters and trackers. … Practical timelines for siting, permitting, constructing and commissioning new factories [will] influence how quickly domestic manufacturing can scale.”

Ingots are blocks of polysilicon, which are then sliced into the superthin “wafers” that go into the solar cells used to produce panels. According to industry analyst Bernreuter, seven of the top 10 polysilicon producers in the world are Chinese companies.

But another industry analyst, who requested anonymity because he is not authorized to speak publicly, said that the details of the decision provide a range of loopholes for companies to avoid the tariffs once Biden’s moratorium expires.

First, the exclusion of Hanwha and Jinko, both major U.S. suppliers, provides some certainty for the industry, he said.

The decision also excludes solar cells and panels made with wafers not specifically produced in China, even if the silicon ingots they are sliced off of are. “That means that all the … production [of wafers] that is online and coming online in Southeast Asia can be made into cells that are not subject to duties,” he said.

Another big loophole is the exclusion for cells and panels where four of six key components — silver paste, aluminum frames, glass, backsheets, ethylene vinyl acetate (EVA) sheets and junction boxes — are not made in China. Silver paste is a conductive material used to improve electricity production in solar panels, and EVA sheets are used to “encapsulate” and protect solar cells in panels.

“If you have four of the six … made outside of China, no duties. That’s not going to be hard to comply with,” the analyst said. “You can make aluminum frames anywhere; you can make glass a lot of places; backsheets, EVA; there’s no reason you have to make this stuff in China. … And then suddenly — boom — all of those modules aren’t subject to duties.

“This was a much better decision for the industry than people may realize,” he said. “The fine print here is really positive for us to continue to have module supply for the next few years.”

But, the analyst cautioned, building out a U.S. supply chain, especially for ingots and wafers, will face challenges. Setting up the new factories will be capital intensive, “and you need somebody who’s got the know-how to do them,” he said. “That ingot and wafer knowledge is now concentrated in Asia, so you have the same problem.”

NYISO Investigating Tariff Changes to Improve Interconnection Processes

RENSSELAER, N.Y. — NYISO officials said Wednesday they will begin stakeholder discussions early next year on revising the interconnection process to make it more efficient, calling it one of their top priorities for 2023.

Zach Smith, vice president at NYISO, told the Management Committee that the ISO is considering a “queue window-based approach,” where each stage of the study would be more meaningful and potentially binding.

The new approach would replace the current three-step study structure, which includes an optional feasibility study and a non-binding system reliability impact study (SRIS) before the facilities study, which results in binding cost allocations.

Smith said the ISO envisions a “clustering approach” where projects are put into a study together to evaluate their joint impact. Smith emphasized, however, that this was simply a preview of what will be discussed with stakeholders and that nothing is settled.

Smith said the additional changes would require tariff revisions and FERC approval, unlike changes the ISO has already made — adding interconnection support liaisons and project managers; improving the interconnection portal; streamlining the SRIS — and ones in process — developing templates to shorten SIS reports and improving handling of material modification requests. (See NYISO Identifies 35 Projects for Narrowed SRIS Scope.)

The ISO expects to begin discussions in the MC, the Transmission Planning Advisory Subcommittee and Electric System Planning Working Group as soon as January and no later than February. “We do not intend to hold up on any improvements waiting” for an order from FERC’s June Notice of Proposed Rulemaking on interconnection generator interconnection procedures and agreements (RM22-14), Smith said. (See FERC Proposes Interconnection Process Overhaul.)

Smith said NYISO is acutely aware of potential tradeoffs stemming from pursuing faster methodologies but is committed to ensuring that project reliability is never sacrificed.

“Do you want speed or do you want flexibility?” Smith said. “One will have to be sacrificed for the other.”

Smith added that it is important for FERC to maintain “independent entity variations” enabling RTOs to tailor solutions to their own regional problems.

CEO Rich Dewey said that the ISO is committed to addressing both the effectiveness of these processes and the customer communication around them. Dewey told stakeholders he understands trade-offs will occur as further changes are made to find the “sweet spot” between flexibility and efficiency.

Mark Reeder, representing the Alliance for Clean Energy New York, commended the ISO for its continued focus on improving the interconnection process: “That’s greatly appreciated.”

Texas Politicians Assert Themselves in PUC’s Market Redesign

Texas lawmakers have jumped into the middle of the Public Utility Commission’s effort to redesign the ERCOT market, saying they are concerned the PUC’s proposals don’t do enough to incent investment in new gas-fired generation.

The commission had been quietly working with consultants behind closed doors to develop new market designs that would protect ERCOT against a repeat of 2021’s disastrous winter storm. But when the PUC unveiled the results of its work last month, it quickly drew pushback from the market and energy experts over its close resemblance to capacity markets. (See Proposed ERCOT Market Redesigns ‘Capacity-ish’ to Some.)

The lead proposal, a performance credit mechanism (PCM) that would require load-serving entities to buy performance-based credits from generation resources that meet reliability standards, has never been tried by a U.S. grid operator. The PUC has asked ERCOT stakeholders and the general public to provide feedback on the PCM and five other market designs by Dec. 15.

However, Texas lawmakers, who see adding more gas-fired, or dispatchable, generation as the solution to the problem (They define dispatchable resources as those not “controlled primarily by forces outside of human control.”) have stepped into the fray.

On Wednesday, Lt. Gov. Dan Patrick, who presides over the state Senate and has tremendous influence over its legislation, unveiled his list of priorities for the Texas Legislature’s 88th session, which begins Jan. 10. They include improving the grid’s reliability; he threatened to keep lawmakers in Austin until they pass legislation that encourages gas-fired power plants to be built.

“Whether it is incentivizing them; whether it’s building them; whatever the plan is, I personally cannot see myself leaving this building knowing that another [winter storm] can happen,” Patrick, who called renewable energy “a luxury,” said during a press conference. “We have to level the playing field so that we attract investment in natural gas plants.”

Observers have noted that would put Patrick at odds with Gov. Greg Abbott and Peter Lake, his handpicked commission chair. Both have said the grid is better than ever because of weatherization, coordinated communication and other operational changes put in place at the end of last year.

The bipartisan Senate Business and Commerce Committee followed up Patrick by sending a letter Thursday to the PUC’s commissioners, urging them to stick to the directives in Senate Bill 3. The omnibus bill, passed last year following the winter storm that almost brought down ERCOT’s grid and left millions of Texans in the dark for days, called for “adequate incentives” for dispatchable generation. It also instructed the PUC to incentivize that dispatchable generation by establishing a reliability standard for the market and using that standard to develop or procure a new ancillary or reliability service for the generators. (See Abbott Signs Texas Grid Legislation into Law.)

The committee had already heard from the PUC, ERCOT and stakeholders, having held a hearing on the plan Nov. 17. It said the testimony that day indicated the PCM was an “administratively complex and novel concept” that would “deter new investments in the ERCOT market until it is fully in place.” (See Legislators, Stakeholders Pan Proposed ERCOT Market Design.)

“By the commission’s own admission, [that] could be several years down the road,” committee members wrote. “There is significant concern the proposals being considered by the commission … not only failed to meet the directives clearly stated in SB3, but more importantly will not guarantee new dispatchable generation in a timely and cost-effective manner. …

“It is not in the best interest of our constituents to support any proposal that further delays investments in new dispatchable generation, and the commission should carefully consider the unintended consequences of any type of proposal that creates more uncertainty for market participants.”

The committee directed the PUC to define ERCOT’s reliability goals before moving forward with any “significant” market redesign and to evaluate creating a new market-based ancillary or reliability service to meet reliability standards.

“Any holistic market design change, including the PCM, that goes beyond the scope of SB3 should not be adopted by the commission without further consultation with the legislature,” the committee said in concluding its letter.

The hits could keep coming. On Monday, the House of Representatives’ State Affairs Committee will hold a public hearing to review the proposed market changes.

The PUC seemed unfazed by the legislative comments. It still plans to present a final recommendation to the legislature next year before allowing ERCOT to begin the implementation process.

A spokesman said the commission will develop a reliability service, “as we’ve said since the beginning of this process.”

“The [PUC] published multiple options for consideration and eagerly awaits public comments on all options,” Rich Parsons said in an emailed statement. “Once the commission holds a vote on a preferred reliability service, we will present it to the legislature next session.”

Alison-Silverstein-2022-11-01-(RTO-Insider-LLC)-FI.jpgAlison Silverstein, Silverstein Consulting | © RTO Insider LLC

“The PUC should take this legislative brushback of the chairman’s preferred solution very seriously. It’s a bad idea to tick off the folks who approve the commission’s budget, appointments and headcount,” Alison Silverstein, an energy consultant with experience at both the PUC and FERC, told RTO Insider on Friday.

She said the PCM proposal is “barely articulated, poorly analyzed, ill-supported and precedent-free, with little evidence that it will produce new gas plants.”

“I wouldn’t risk the Texas economy and energy affordability for [the PCM],” Silverstein said.

She put in a plug for the backstop reliability service, one of the other five designs. The ancillary service would meet specific reliability needs not met by ERCOT’s real-time and ancillary service markets during high uncertainty periods. Silverstein said it would act as an insurance policy that would better manage plant retirements.

Stoic Energy principal Doug Lewin said that building new gas plants will only lead to higher customer bills.

“If you want to lower bills, you need to integrate more renewables and increase energy efficiency,” he tweeted, noting that a consultant for the PUC has shown that high renewable generation reduces energy costs by 20%.

“No one thing will solve any, much less all, of these problems,” Lewin added. “Unfortunately, some policymakers are trying to solve a different problem. They don’t like renewables and want more gas plants. That won’t solve any of the problems.”

MISO: 200 GW in New Capacity Necessary by 2041

CARMEL, Ind. — MISO said last week its members may need to build 200 GW in new installed capacity by 2041 to meet reserve requirements and achieve renewable targets and emissions-cutting goals, according to the RTO’s annual regional resource assessment.

The grid operator used this year’s report, which draws on members’ public generation plans and MISO’s own capacity expansion estimates, to repeat warnings of continuing capacity shortages and plead for more controllable generation. Staff said members may need to construct more than 100 GW of new capacity within the next 10 years alone to meet “publicly announced plans and goals in a reliable manner.”

After the inaugural assessment in 2021, MISO said it would need to add 140 GW of new capacity over the next two decades to meet state carbon-reduction targets while also maintaining reliability. Carbon reduction goals have only become more aggressive in the last year, with utilities frequently revising net zero goals. (See MISO Resource Assessment: 140 GW Needed Within 20 Years.)

This year, MISO focused on accredited capacity numbers. Although it expects members to add 30 GW of net installed capacity by 2041, it said accredited capacity will be at least 10 GW lower than what is available today.

The RTO projects members will likely need to add 47 GW in accredited capacity above the 141 GW of planned and accredited existing resources it expects to have in 20 years. It has approximately 162 GW in total accredited capacity today.

MISO said it will likely approach 30% of its annual energy coming from renewables within five years, with penetration levels increasing by about 10% every five years.

Systemwide resources (MISO) Content.jpgSystemwide existing, planned, and needed resources | MISO

 

Its modeling “indicates a continued near-term capacity risk, highlighting the urgent need for coordinated resource planning and additional investment.” Staff stressed that the assessment captures a snapshot in time that relies on publicly available resource planning and isn’t necessarily MISO’s future. They emphasized that MISO members do not produce “detailed” resource plans on a 20-year time horizon.

“In the absence of a coordinated transition plan, having a holistic assessment of our entire operating region is important for our members, policymakers and MISO as we all work to anticipate and manage the complex issues facing our industry,” CEO John Bear said in a Wednesday press release accompanying the report.

According to the report, wind and solar generation will serve 60% of MISO’s annual load by 2041, reducing emissions by nearly 80% relative to 2005 levels. The RTO said that generation mix will “sharply increase the complexity of reliably operating and planning the system.”

The footprint will “have a much greater need for controllable ramp-up capability,” MISO said. It said its short-duration ramp needs will increase three-fold from current levels by 2031, and four-fold by 2041.

MISO also said that by 2031, it will encounter resource adequacy risks in all seasons, not just summer. The grid operator said the risk will mostly be concentrated in the evenings when solar generation tapers off and wind generation is still ramping up.

The RTO found that as more solar capacity is added to the system, the capacity contribution of solar generation “is forecast to decline rapidly,” while wind generation’s contribution remains stable with additions.

“As the MISO region rapidly transitions to a decarbonized fleet, the system will become more interconnected and interdependent,” Jordan Bakke, director of strategic insights and assessments, said. “The task of resource planning is becoming more complex and having a shared understanding of future trends and risks is necessary to ensure reliability.”

MISO has a staggering amount of proposed capacity in the interconnection queue after fielding in September a record 171 GW of proposed renewable generation and storage projects from 956 requests. (See MISO Insists it can Handle Record-setting Interconnection Queue.)

The rub is MISO’s supply of accredited capacity. And while capacity increases, its share of on-demand capacity is drying up.

During a Nov. 10 stakeholder workshop, policy studies engineer Hilary Brown said members are largely planning investments in solar and wind capacity as they schedule more coal generation retirements.

“A one-for-one megawatt replacement is likely not sufficient,” Brown said of members’ plans.

She said MISO expects the near-term capacity risk to continue with the growing need for flexible resources to reinforce intermittent resources.

The RTO’s system simulation showed it will likely need a yet-unknown combination of low-emission, high-capacity grid-enhancing technologies by 2030, including carbon capture and sequestration, small modular reactors, green hydrogen and long-duration energy storage.

Stakeholders have pressed MISO to provide a megawatt value of how much new storage it might need over the next 20 years.