November 17, 2024

NJ Backs $20 Million Spend on Tx Link for Offshore Wind Port

The board of the New Jersey Economic Development Authority (EDA) voted this month to back a $20 million purchase agreement with Atlantic City Electricity (ACE) to ensure the utility avoids potential supply chain delays in the delivery of construction materials needed to develop the 12-mile transmission line tying the New Jersey Wind Port to the grid.

The EDA also started the process of issuing $160 million in tax exempt bonds to pay for construction of the wind port through 2023. The agency’s board voted Nov. 16 to support an “Official Intent Resolution” that sets the bonding process in motion, but the board would have to take another vote for the bond issue to move ahead, according to the memo.

The project has so far obtained $478.2 million in state funds, and the bonded finance would “secure the balance of funding” needed for completion of the first two phases of the projects, according to a Nov. 16 memo from EDA CEO Tim Sullivan to the board.

The two board votes reflect the EDA’s commitment to pushing aggressively ahead with the project, which officials say will be the nation’s first custom-built port serving the wind. It is the cornerstone of the state’s drive to become a manufacturing and logistics hub for the nascent industry, not only in New Jersey but for other East Coast offshore wind projects as well.

The purchase agreement is designed to ensure the smooth advancement of the wind port project, which broke ground in September 2021. The agreement “is necessary to safeguard the purchase of materials with long lead times or are at risk of delays due to global supply chain disruption,” Sullivan said in the memo outlining the expenditure.

The deal will bring the total cost of the connection — a 69-kV transmission line on a greenfield site — to $25.88 million. The board in April approved an expenditure of $5.14 million for the utility to move ahead with a detailed design of the line. The design is 60% complete and on schedule, according to the memo.

Providing Power for Tenants

The wind port, located at Alloways Creek in Salem County, will include a 30-acre marshalling area for component assembly and staging; a dedicated, overland, heavy-haul transportation corridor; and a heavy-lift wharf with a dedicated delivery berth and an installation berth that can accommodate jack-up vessels.

The port was conceived to serve New Jersey’s own offshore wind industry. The state Board of Public Utilities (BPU) has so far awarded three wind projects in two solicitations since 2019: the 1,100-MW Ocean Wind 1 and 1,148-MW Ocean Wind 2, both developed by Ørsted, and the 1,510-MW Atlantic Shores, a joint venture between EDF Renewables North America and Shell New Energies US. The BPU is planning to hold a third solicitation early in 2023.

The developers of the three approved offshore projects have agreed to use the port, but the state also wants to attract business from non-New Jersey projects. The EDA said in October 2021 that it had received 16 non-binding offers for companies looking to become tenants at the port, among them Siemens Gamesa Renewable Energy (OTCMKTS:GCTAY). (See NJ Wind Port Draws Offshore Heavy Hitters.)

Nacelle manufacturers MHI Vestas and General Electric have committed to creating nacelle plants at the port, and German manufacturer EEW Group is building a monopile factory in the nearby Port of Paulsboro.

The ACE agreement is important to the wind port because it is located in a remote part of South Jersey, adjacent to three nuclear plants operated by PSE&G, and has no tie to the grid, according to the EDA.

“The approval of long lead items ahead of full construction is necessary to safeguard the construction schedule with materials facing long lead times or risks of disruption due to broader supply chain volatility,” according to Sullivan’s memo. “It also recognizes the authority’s negotiated cost obligations to staff’s recommended inaugural subtenant should a power line connection not be in place by the start of the sublease.”

If the link isn’t ready on time, the project could have no power supply to provide tenants and would have to share the cost of providing temporary power solutions, “such as diesel generators,” the memo said.

Sullivan laid out the expenditures anticipated to be made from the $20 million, which include: $16.9 million for steel poles and anchor bolt cages; $204,00 for conductors; $71,000 for circuit breakers and $62,000 for static wire.

ISO-NE Finalizing Changes to Economic Study Process

ISO-NE is finalizing changes to its economic study process as it works through the NEPOOL stakeholder gauntlet.

The changes are intended to improve responses to stakeholder requests for economic studies to fill gaps not covered by the ISO’s reliability studies. Such requests have evolved to more and more complex topics, such as ancillary services, resource adequacy, high-level transmission reliability and capacity markets.

Under the current process, ISO-NE puts together a rough scope for all the studies requested by stakeholders and then prioritizes them based on the region’s needs.  

The new proposal would change that process by setting up an analysis framework and using it to run “consistent reference scenarios.” After that initial run, stakeholders and the ISO could request new sensitivities to test the effect of a specific change to the study’s assumptions.

ISO-NE is also proposing to change the cycle of economic studies to align with the regional system plan (RSP) cycle, moving from every year to every two years.

At the NEPOOL Transmission Committee meeting on Tuesday, ISO-NE presented some minor revisions to its proposed tariff changes, which were approved by the committee.

The grid operator is aiming to get a final vote on the study changes at the January Participants Committee meeting, with a FERC filing to follow shortly after.

DECR Tariff Changes

Also at the TC meeting, ISO-NE presented its latest work on aligning buyer-side mitigation rules to allow distributed energy capacity resources (DECR) to take part in Forward Capacity Auction 18, set for Feb. 5,  2024.

The tariff updates will reflect the minimum offer price rule (MOPR) changes accepted by FERC in May and the ISO’s compliance filing for FERC Order 2222, which has not yet been approved by the federal agency.

The tariff changes would modify buyer-side mitigation rules throughout the post-MOPR process to ensure that DERs can be included in the FCA.

They would also modify proposed DECR qualification rules in Section III.13.4A and address the qualification process cost reimbursement deposit requirement.

The tariff changes also clean up some definitions, dates and cross references related to the 2222 compliance proposal.

The ISO is working to get those changes finalized by March 2023 to be ready for FCA 18.

Former Regulators: Demand Response Key to Midwest Capacity Crisis

Two former FERC chairmen and a state commissioner are pessimistic that MISO will be able to rein in shortages or high capacity prices anytime soon and said demand-side management would assuage the situation.

Former FERC chair and Voltus Chief Regulatory Officer Jon Wellinghoff said during a Nov. 21 webinar, sponsored by his company, that today’s grid fragility in the Midwest can be traced to an increased amount of renewable energy and extreme weather conditions.

“We’ve got a situation now in which our grid is being increasingly tested by extreme weather events that are being driven by climate change, but the steps that we need to take to combat climate change and mitigate our emissions include increased dependency on weather-dependent resources,” former FERC chairman Neil Chatterjee said. “This is a challenging conundrum, and it’s one that policymakers and grid operators have really been wrestling with.”

Voltus CEO Gregg Dixon said an ongoing transition to renewable resources and increased electrification demand alongside severe weather are “putting an even greater strain on an already antiquated grid.”

“We are a month away from winter, and the headline is: ‘It does not look good’ … And summer of 2023 does not look a whole lot better,” Dixon said, referencing NERC’s recent reliability assessment.

The agency has warned that MISO risks winter blackouts after its most recent capacity auction uncovered a 1.2-GW deficit heading into the June 1, 2023, planning year. The Independent Market Monitor has said the footprint’s real risk lies in summer 2023.

Chatterjee said with “the absence of federal legislative guidance” on decarbonization, states must devise their own strategies to cut carbon while ensuring resource adequacy.

Ted-Thomas-2021-11-17-(RTO-Insider-LLC)-FI.jpgFormer Arkansas PSC Chairman Ted Thomas | © RTO Insider LLC

Former Arkansas Public Service Commission chairman Ted Thomas said MISO’s role as reliability coordinator and states’ obligation to ensure resource adequacy can never be “cleanly” separated.

“So, there’s always this tension that plays out with all of these policy issues,” he said.

Thomas said until now, state regulators have always resisted the downward-sloping demand curve in the MISO capacity auctions, viewing it as a “slippery slope” to a mandatory, PJM-style auction.

He said that when the price “shot up” during the 2021-22 planning year auction, regulators’ response was, “MISO, what are you going to do about it?” Thomas said a few years ago, changing the demand curve’s slope would have been viewed by regulators as an overstep.

He said a sloped demand curve will produce gradually increasing capacity prices, instead of extremely low prices one year that skyrocket the next.

“To me, the issues we’re seeing in MISO are simple: There’s just not enough generation,” Chatterjee said. “States have made it clear that they are primarily responsible for resource adequacy … Yet for years, merchant generators have been sounding the alarm that they couldn’t continue to lose money year-over year and that market revenues were not sufficient.”

Chatterjee said some states and load-serving entities believed they could continue to buy capacity from the MISO auction at rock-bottom prices.

“Why pay to build or contract for generation when it’s available for a fraction of the cost in the MISO auction?” he said. “And the end result of that is that badly needed generation has retired, and now the entire region is going to be at an elevated risk of load loss for the foreseeable future.”

Dixon said Voltus expects that MISO Midwest capacity prices will continue to “cap out” at the cost of new generation entry, making Midwestern capacity “perhaps the most expensive in the world.”

“Which is really ironic because it used to essentially be for free,” Dixon said.

Thomas said MISO is better preparing for “oddball weather any time of the year” by shifting focus from a summer peak and switching to capacity accreditation based on unit availability.

He also said MISO South members’ continuing resistance to adding more transfer capability between MISO Midwest and the South regions “balkanizes the RTO footprint” to the detriment of resource adequacy.

Thomas prescribed large customer aggregation to leverage demand response to address reliability crises. He said residential and commercial customers need a combination of renewable energy, demand response and energy efficiency measures “to escape the hit of these commodity prices.” Third-party aggregators can apply competitive pressure to utilities to “up their game,” he said.

“I think utilities are going to have to recognize that they’re going to have to compete and evolve their business models or continue to face pressure. Pressure from regulators, pressure from consumers,” Chatterjee said.

Wellinghoff said customers in states that have opted out of demand response and are unable to participate in a wholesale market’s aggregation should register their displeasure with FERC. He said the commission should revoke the ability for states to opt-out, especially considering the flexible load that tomorrow’s electric vehicle fleets can supply.

Chatterjee agreed that FERC should remove the demand response opt out, saying that tight supply conditions are not going to resolve themselves.

“We tend to only react after bad things happen. And to me right now, we’re seeing FERC drag its heels on the DR opt out; we’re seeing resistance at the state level,” Chatterjee said. “To me, it’s going to take something negative to trigger change, to trigger movement.”

He added that there’s “real risk in MISO right now of not having enough capacity on one or two very, very hot days.”

“To me, it seems like a few factories turning off could make a real difference. Sadly, it will probably take an event like that to, in my view, lead to policy changes that are necessary,” Chatterjee said.  

Thomas said the Midwest could use universal access to advanced metering infrastructure and aggregation alongside a faster roll out of MISO’s proposed 2030 compliance with Order 2222, which allows aggregators of distributed resources into the wholesale energy markets. (See MISO Stakeholders Protest RTO’s Order 2222 Implementation Timeline.)

After that, Thomas said, the grid operator could probably “have a cold one and lean back and watch entrepreneurs and business looking out for their own interests” help decarbonize the grid, reduce costs and bolster system reliability.

“If you’re going to have scale-variable resources, you’ve got to have scale-variable load,” he said. “That’s the cheapest option, and we need to make that happen.”

FERC Approves New England Generation Deal Over Competition Objections

Federal regulators last week signed off on a Japanese company’s plan to buy three gas-fired generators in New England, despite opposition from consumer advocates who had argued that the deal would lead to undue consolidation in the region.

The investment firm Stonepeak asked FERC this summer for approval to sell two units at Canal Generating Station in Sandwich, Mass., totaling 1,457 MW, and another 160-MW unit in Bucksport, Maine, to JERA, a joint venture between two Japanese utilities, Tokyo Electric Power’s TEPCO Fuel & Power and Chubu Electric Power (EC22-71).

Massachusetts Attorney General Maura Healey and the advocacy group Public Citizen had both challenged the acquisition saying that it would give JERA — which already owns 50% of two other gas units totaling more than 400 MW in Massachusetts — too large a share of the generation market. (See Mass. AG, Public Citizen Raise Alarm Over Proposed Generation Deal).

But FERC sided with the buyer and seller, accepting their argument that the transaction would not have an adverse effect on vertical or horizontal competition.

Although JERA will own more than 18% of the capacity cleared in the Southeastern New England zone, FERC wrote that “Applicants’ analysis shows that, when considering ISO-NE as a whole, the proposed transaction does not increase market concentration such that there will be an adverse effect on competition.”

FERC also shot down protests arguing that the deal could have adverse effects on rates and on regulations. And it refused a request from Public Citizen to make public the confidential purchase price of the deal, finding no reason to break with the standard of allowing the submitter to keep prices confidential.

NY Slaps Moratorium on Certain Crypto Mining Permits

New York has imposed the nation’s first moratorium on permitting for certain new cryptocurrency mining operations.

The move drew criticism from business advocates and the digital currency industry but was applauded by environmental advocates concerned about the greenhouse gas emissions generated to feed the huge electrical demand of crypto mining.

Gov. Kathy Hochul signed the two-year moratorium into law Nov. 22, and it took effect immediately. It blocks approval or renewal of air emissions permits for carbon-fueled power plants that provide behind-the-meter electricity to operations that use proof-of-work authentication methods to validate blockchain transactions.

Existing operations and applications filed before Nov. 23, 2022, are not subject to the moratorium. Nor are those that rely on zero-emissions sources of electricity, such as New York’s abundant hydropower.

New York is widely regarded as one of the most expensive and highly regulated states in the nation. Its upstate region, where crypto mining operations have been established or proposed, has seen a decades-long loss of industry and population.

Hochul acknowledged this in her memorandum of approval.

“As the first Governor from Upstate New York in nearly a century, I recognize the importance of creating economic opportunity in communities that have been left behind,” she wrote.

She said the effort to support economic development and job creation upstate would continue but gave priority in this case to protecting communities from greenhouse gases and addressing the global climate crisis.

Crypto mining uses huge amounts of electricity.

Greenidge Generation Holdings (NASDAQ:GREE) in its 2021 10-K filing said its Dresden, N.Y., and Spartanburg, S.C., datacenters are rated at a combined 51 MW.

The Dresden facility has become a poster child or a flashpoint of sorts for the debate over the environmental impact of crypto mining. Its re-permitting process attracted nearly 4,000 public comments.

The circa-1937 plant sits on the west shore of the largest of the Finger Lakes, squarely in the middle of one of upstate New York’s most scenic and tourist-friendly regions.

It was coal-fired for most of its existence, but Greenidge converted it to natural gas and bought it back online at 106 MW in 2017, with a claimed 70% reduction in emissions. Greenidge says it is committed to carbon-neutral crypto mining by using low-carbon energy sources and offsetting its carbon footprint.

That’s not enough for climate activists, whose opposition is due not just to the emissions from burning natural gas but the environmental impact of extracting it with hydrofracking. New York has banned fracking, but it is in widespread use in Pennsylvania, 50 miles south of Dresden. The Marcellus Shale formation underlies the entire region.

Opponents cheered in June when the New York state Department of Environmental Conservation denied Greenidge’s application to renew its Title V permit for the Dresden plant on the grounds that it did not meet the requirements of the state’s Climate Leadership and Community Protection Act.

Greenidge decried the “arbitrary and capricious” decision and said DEC never once engaged it in discussion in the three months after it proposed an additional 40% reduction in greenhouse gas emissions at the Dresden plant.

The facility continues in operation while Greenidge appeals the denial.

But opponents are hoping that is only temporary.

Seneca Lake Guardian, one of the groups advocating for the moratorium on new crypto mining, called on Hochul to take the next step and shut down Dresden and similar facilities.

The group’s vice president, Yvonne Taylor, said in a prepared statement: “Thank you, Gov. Hochul, for stepping up to protect New Yorkers from corporate bullies who want to exploit communities like mine in the Finger Lakes … Gov. Hochul did the right thing by putting real New Yorkers over the failing outside speculators who choose not to mine crypto in more efficient ways that don’t destroy the climate, environment, and local economies.”

The environmental group Earthjustice said it hoped New York’s moratorium would be a precedent for the rest of the nation, as “crypto mining is a major threat to climate security and needs to be closely regulated.”

Others have supported the Dresden operation as a high-tech infusion of good new jobs and new property tax revenue in a region that is often lacking in both.

“The Business Council does not believe the legislature should seek to categorically limit the growth and expansion of any business or sector in New York,” said Heather Briccetti Mulligan, CEO of the Business Council of New York State. “We plan to further engage and help educate them regarding this industry and the benefits it provides to the local, regional, and state economy.”

And the digital community was aggrieved.

“We are severely disappointed in Gov. Hochul’s decision to approve a moratorium on digital asset mining operations that use proof-of-work (PoW) authentication methods to validate blockchain transactions,” the Chamber of Digital Commerce said. “To date, no other industry in the state has been sidelined like this for its energy usage. This is a dangerous precedent to set in determining who may or may not use power. The PoW mining industry has been spurring economic growth, job creation, and inclusion for historically underrepresented populations in New York, while also creating financial incentives for the buildout of renewable energy infrastructure.”

TVA to Repurpose Coal Ash Dump with Solar Generation

The Tennessee Valley Authority will embark on a $216 million pilot project to install solar panels on top of a sealed coal ash dump following the Board of Directors’ funding approval earlier this month.

TVA plans to close in place a 300-acre coal ash dump at its 1.2-GW Shawnee Fossil Plant in Paducah, Ky., with a patented system that includes a geosynthetic liner and closure turf. The federal agency said it will attach a 100-MW solar array to the site without disturbing its integrity.

The Shawnee project is “a first-of-its-kind project in the nation that could potentially be duplicated at other suitable locations,” TVA said. It said the project will support its decarbonization goal and will preserve greenfield sites for other economic developments.

TVA still must submit the project for review under the National Environmental Policy Act and other regulatory and environmental approvals.

TVA doesn’t yet know when the solar project will achieve commercial operation.  

“At this time, it is premature to know a specific timeframe, but the process is underway,” TVA spokesperson Ashton Davies said in an emailed statement to RTO Insider. She said TVA intends to begin the solar installation as it wraps up the site’s closure.

During the November board meeting, TVA COO Don Moul called the pilot a “revolutionary new approach to install utility-scale solar on closed landfills.”

“Directly attaching the mounting mechanisms to the turf layer without penetrating the liner maintains the integrity of the closed coal combustion residual impoundment,” Moul said. “This makes available to us the potential to use similar sites across the TVA footprint.”

Moul said the project alleviates “land constraints” while advancing TVA’s goal of building 10 GW in solar generation by 2035.

The agency’s goal is to achieve net-zero carbon emissions by 2050, which some conservation groups have called too gradual. The agency’s decarbonization target drew scrutiny from the U.S. House of Representatives’ Committee on Energy and Commerce. (See TVA Defends Rates, CO2 Reduction Plans in House Inquiry.)

Next year, TVA will contract with a third party to conduct a decarbonization study to analyze how it can further slash emissions.

“Moving quickly on this solar cap installation at the Shawnee site allows us to move further and faster as we build out towards our renewable generation goals,” Moul said.

Moul said Shawnee was “by and far” best situated for an initial project. He said TVA’s footprint has the potential to house up to 1,000 MW in solar generation atop sealed coal ash dumps.

“We’re very excited that this is a first step in some of the intentional actions we’ll be taking towards decarbonization,” he said.

Moul said while he wouldn’t “presuppose” the environmental review process, he said TVA estimates having the system online within two years.

He also said TVA will look into whether the Inflation Reduction Act will cover the project’s funds.

California CCAs Add 1.4 GW to Clean Energy Portfolios in 2021

California’s community choice aggregators expanded their long-term procurement of clean energy by 1,431 MW over the past year, a 14% increase that includes 119 MW of long-duration storage.

The new power purchase agreements bring the overall long-term procurement by the state’s CCAs to 11,258 MW, up from 9,827 MW in November 2021. The figures are included in an annual report released this month by the California Community Choice Association (CalCCA), an organization representing the state’s community choice electricity providers.

The 243 long-term contracts are for “new-build” resources, including solar, wind, geothermal, demand response, biogas and energy storage. The clean energy projects are spread across California, and some are in Arizona, New Mexico and Nevada.

“CCAs are procuring the diversity of resources that are needed for the state to achieve a 100% clean electricity system, with a focus on affordability, reliability and resilience,” CalCCA Executive Director Beth Vaughan said in a statement.

Vaughn said previously that the state’s CCAs “continue to drive a clean energy project-building boom throughout California and the West.”

The purchase agreements, ranging in length from 10 to 25 years, are for power from newly built clean energy resources. More than 4,000 MW are in operation now and almost all the rest is expected to be online by 2026.

Solar paired with storage is the largest category of long-term clean energy procurement, contributing 4,232 MW to the total. Storage that accompanies solar is the second-largest category, providing 2,451 MW.

CCAs increasingly are turning to solar-plus-storage rather than standalone solar in solar energy contracts, according to CalCCA. The 2,016 MW of standalone solar energy procurement in this year’s report is a 71 MW decrease from last year’s figure.

Even with the reduction, standalone solar is the third largest clean energy procurement category for the CCAs, followed by wind, with 1,376 MW.

Long-duration Storage

The 119 MW of long-duration storage reported this year came from two contracts approved in early 2022 by California Community Power, a joint powers agency representing nine CCAs. One contract is with REV Renewables for 69 MW at the company’s Tumbleweed project in Kern County. The other is for 50 MW at Onward Energy’s Goal Line project in Escondido. The lithium-ion battery projects will have an eight-hour discharge duration.

Another addition to this year’s list was demand response, which accounted for 23 MW of the power purchases.

In addition, geothermal power procurement increased this year to 287 MW, up from 14 MW as of November 2021. In one of the agreements, announced in May, Fervo Energy will supply 40 MW of geothermal power to East Bay Community Energy from a project in Churchill County, Nevada.

In April, Ormat Technologies announced an agreement with Peninsula Clean Energy to buy 26 MW of energy from the company’s Heber 2 geothermal facility in Imperial Valley, California.

RPS Requirements

Community choice aggregators are nonprofit providers of energy within the territory of investor-owned utilities. Customers who choose to buy power from a CCA still receive transmission and distribution service from the IOU.

This year, CCAs served about a third of the load in the territories of the state’s three primary IOUs, CalCCA said. That figure is expected to increase to 36% in 2023.

And according to the California Public Utilities Commission, CCAs are playing “an increasingly significant role” in meeting state and local greenhouse gas reduction goals.

CalCCA said that the long-term contracts for clean energy are helping the CCAs meet requirements of the state’s renewables portfolio standard (RPS).

In 2021, CCAs achieved an RPS percentage of 50%, when considered in aggregate, the CPUC said in an annual RPS report released this month. That’s well above the 44% RPS requirement for the 2021-2024 compliance period.

“The CCAs’ generation has increased to keep pace with RPS requirements through 2023, even exceeding the 2023 forecasted target,” CPUC said in the report.

But current forecasts show online generation starting to drop in 2024 for 16 of the 25 CCAs, the report said. Considered in aggregate, the RPS percentage is projected to drop to 41% in 2024. CPUC said that’s due to expiring contracts and the launch of new CCAs that have little to no RPS procurement.

The RPS target grows to 60% in 2030, and most CCAs will need more renewable resources, CPUC said.

Another RPS requirement is that 65% of procurement should come from long-term contracts, considered to be 10 years or longer.

All the CCAs are expected to meet the long-term procurement requirement for the 2017-2020 compliance period, CPUC said. And most have met, or are close to meeting, the long-term procurement requirement for 2021-2024.

FERC Staff Finds Dynegy Manipulated 2015 MISO Capacity Auction

FERC’s Office of Enforcement has concluded that Dynegy “knowingly engaged in manipulative behavior” during MISO’s 2015/16 capacity auction — rejecting the commission’s 2019 order that cleared the company.

As a result of  enforcement staff’s heavily redacted 85-page report, the commission will now consider briefs on whether Dynegy should refund $429 million to Illinois ratepayers (EL15-70).

The commission announced a second look at Dynegy’s behavior in June after the D.C. Circuit Court of Appeals ruled that FERC hadn’t sufficiently supported its decision to accept the Southern Illinois capacity price produced in the 2015/16 auction. (See FERC to Take 2nd Look at 2015 MISO Capacity Auction.)

OE’s report, issued in September, said Dynegy participated in a fraudulent scheme to “corner the relevant portion of the market, consisting of those megawatts that MISO would likely need to clear the auction and that could be offered into the auction at a zero price if not held on Dynegy’s unsold books.”

Dynegy, which was acquired by Vistra in 2018, took four steps outside of market fundamentals to make sure it could set prices in the capacity auction, FERC said. Staff described the utility’s actions in the report’s redacted portion and said Dynegy made sure it increased the odds that one of its resources offered into the auction at a non-zero price would become the marginal resource and set the clearing price for Southern Illinois.

FERC staff said Dynegy’s malfeasance began a year ahead of the 2014/15 auction when it purchased 3,152 MW in MISO Zone 4 in Illinois, and 1,241 MW in a neighboring zone, from Ameren. FERC said Dynegy failed to set the price in that auction, when no zone cleared above $16.75/MW-day.

“After failing to set the price in the 2014/15 auction, Dynegy saw an opportunity to set the price in the 2015/16 auction,” FERC staff said.

In the April 2015 auction for 2015/16, MISO saw clearing prices of $3.48/ MW-day or lower in all zones except Zone 4, which  cleared at $150/MW-day.

2015-16-MISO-PRA-results-(MISO) Alt FI.jpg2015/16 MISO PRA results | MISO

 

The OE report was compiled using evidence from a three-year, non-public FERC investigation that included testimony from 11 Dynegy witnesses and more than 500,000 pages of documents. The original investigation, which began on a vote by the entire commission in 2015, was ended by then-chair Neil Chatterjee in 2019 without giving notice to his fellow commissioners.

That prompted a dissent by current Chair Richard Glick when the commission voted 3-1 in July 2019 that Dynegy had not committed market manipulation and that the $150/MW-day clearing price was just and reasonable. The commission said a clearing price isn’t unjust simply because it’s higher than expected (EL15-70).

Glick contended Chatterjee prematurely “cut short” the investigation. Chatterjee said he was acting within his purview as chair and did not need to consult with his colleagues. (See FERC Clears MISO 2015/16 Auction Results.)

Staff’s report gives no indication of Chatterjee’s reason for closing the probe. The report said the original investigators agreed in mid-2017 that Dynegy had engaged in market manipulation and that the company’s responses in 2017 and 2018 failed to change staff’s conclusion.

Vistra Rejects Staff Findings

Vistra said last week it “strongly disagrees with staff’s allegation in this report” and contends that it “acted in accordance with all applicable market rules and procedures.”

“This matter has thoroughly been investigated several times and adjudicated,” Vistra spokesperson Meranda Cohn said in an emailed statement to RTO Insider. “When FERC cleared Dynegy in 2019, they found that no market manipulation occurred and that the MISO 2015/2016 capacity auction results were just and reasonable. No new facts, circumstances or evidence have come to light in the three years since this decision.”

Cohn said in the “years-long process, the same allegations have been periodically repeated but have routinely been disproved by experts and independent regulatory authorities, including FERC and the Independent Market Monitor for MISO.”

Financial Impact not Disclosed

OE staff calculated the financial impact of Dynegy’s actions,  but the details were redacted.

Public Citizen and the Illinois Attorney General asked FERC in February to recoup $428.6 million, plus interest from June 1, 2015, to load serving entities in Illinois in MISO Zone 4 to reimburse their customers.

Tyson Slocum, the director of Public Citizen’s energy program, told RTO Insider he believed the company raised capacity costs by about $100 million, an estimate he said was “confirmed by reams of non-public Enforcement staff conclusions.”

In addition to the $100 million in direct rate impacts, Slocum said, there are “hundreds of millions of dollars in cascading rate impacts.”

In ordering OE staff to reconsider Dynegy’s actions in June, the commission said it would determine any remedy in a later phase of the proceeding. On Oct. 7, the commission ordered initial briefs on the remand report by March 1, 2023, and reply briefs on May 1, 2023.

Cohn said that Vistra will “continue to vigorously defend Dynegy’s conduct.” She said FERC staff’s actions are “unwarranted, without merit, beyond the scope of the remand order and inconsistent with prior decisions and action by FERC.”

NY CAC Debates the ‘Nomenclature’ of Natural Gas

ALBANY, N.Y. — New York Climate Action Council (CAC) members clashed last week over definitions of natural gas during discussions of potential edits to the Gas System Transition portion of its draft scoping plan.

Jessica Waldorf, director of policy implementation at the New York Department of Public Service, on Nov. 21 presented a summary of feedback given at earlier sessions, which included proposals to both change the term “fossil gas” to “natural gas” and to use the term “fossil natural gas” to differentiate from renewable natural gas (RNG) in the plan.

Waldorf explained that part of the thinking is that the distinction struck a middle ground between members who want the term “fossil natural gas” while addressing members’ concerns around public perception of the use of the term.

RNG refers to biogas produced by a variety of processes, such as anaerobic digestion or capturing agricultural waste emissions. Critics of labeling it “renewable” say it is misleading, as it is not produced naturally, and argue that “recycled” or “sustainable” would be better substitutes. According to EPA, “RNG is a ‘term of art,’ and there is not at present a standard definition.”

Some CAC members expressed opposition to the proposed revisions, however, based on the fact that RNG projects can still result in increased emissions.

Although he believed the proposal was a fine compromise, Bob Howarth, a professor at Cornell University, thought that too much weight was being given to RNG, which he said was an untested resource whose decarbonization role would likely be limited.

Raya Salter, executive director of the Energy Justice Law & Policy Center, expressed discomfort with the proposal, saying that the fossil fuel industry wants us to move forward with untested fuel models.

Meanwhile, supporters of the proposal argued that the distinction would enable flexibility within the scoping plan and that any debate was moot because these wider disagreements would not be resolved by the council.

Donna DeCarolis, president of the National Fuel Gas, stressed that it was important that the scoping plan include all available fuel options for the state to meet its energy goals.

Gavin Donohue, CEO of the Independent Power Producers of New York, agreed with DeCarolis’ assessment and added that he objected to the inclusion of the word “fossil” anywhere in the scoping plan because the word is not contained nor defined anywhere within the Climate Leadership and Community Protection Act.

Thomas Falcone, CEO of Long Island Power Authority, told the CAC that he supported the compromise, understanding both sides of the argument, but that it was more of a symbolic issue that, although important, would not be solved through the scoping plan.

Peter Costello, general counsel of the New York State Energy Research and Development Authority (NYSERDA), explained that the scoping plan is not a legally binding document, but, from a legal standpoint, these clarifications would help inform those who may be required to legally contextualize these terms in an effort to avoid any legal action.

Doreen Harris, CEO of NYSERDA, argued for the CAC to include a glossary at the end of the scoping plan that defines unresolved terminology or better contextualizes contentious topics. Paul Shepson, dean of the College of Marine and Atmospheric Sciences at Stony Brook University, agreed, saying readers could be confused.

Climate Protesters in NY (Allison Considine Sierra Club) Alt FI.jpgClimate protesters call for the end of gas usage in New York. | Allison Considine, Sierra Club

 

The debate around natural gas was fortuitous, as the start of the meeting was interrupted by protesters carrying a long string of photographs and signs calling for the end of gas usage across New York. Protesters told NetZero Insider that the photos were of individuals calling the governor’s office throughout the day to demand for the elimination of gas from the CAC’s final scoping plan.

“The actions we take today will have major implications for our future,” one protester said, adding that they were disheartened by the CAC’s debate around the “nomenclature” of gas.

Only two more CAC meetings remain, with Dec. 5 being the final day to resolve any outstanding items before the final vote on the scoping plan on Dec. 19.

NY PSC Accepts NYSEG Proposal to Address Gas Leak Fire

The New York Public Service Commission this month approved New York State Electric and Gas’ (NYSE:AGR) proposed plan to address the installation errors that caused a natural gas explosion that destroyed a two-family home in the village of Brewster last February (22-G-0425).

The PSC on Nov. 17 directed NYSEG to repair and remediate all errors identified in the 450 randomly selected inspection sampling sites no later than May 17, 2024, and submit quarterly progress reports.

The commission indicated that it may fine NYSEG a “civil penalty not exceeding the greater of $250,000 or ‘[0.03%] of the annual intrastate gross operating revenue of the corporation’” for each established violation.

The incident at 2592 Carmel Ave. was caused by “an underground gas leak, which contributed to a residential fire and ultimately led to the complete destruction of the duplex residence,” according to the PSC.

The commission’s investigation determined that efforts to prevent the fire were complicated because NYSEG employees lacked proper equipment to effectively respond to the leak, installed the nearby tapping tee improperly and failed to maintain reliable record keeping.

Specifically, NYSEG informed the PSC it could not “ascertain from its own historical records the specific personnel involved in installing the PermaLock Tapping Tee” related to February explosion, leading the PSC to write that additional “opportunistic inspections” are likely.

NYSEG intends to perform inspections “before the 2023 winter season, and subsequently completing the project by spring 2024,” but if additional “anomalies and defects are detected,” the company “may be required to increase its sampling size.”

If additional evidence is found that NYSEG has not maintained reliable “record keeping pertaining to piping and component installation,” the PSC “has the regulatory authority to order changes to internal utility protocols and procedures.”

The commission stressed that it expects that “utilities maintain their distribution systems and components to ensure public safety and that they avoid or replace components whose failure can harm to public.”

In a statement to NetZero Insider, the PSC said that they are currently focused “on testing before any next steps are decided” in response to questions about whether it planned on tightening the rules or regulations surrounding tapping tees.

Earlier this year, one person died and many more were injured due to gas leak explosion in a Bronx three-story home.

Meanwhile, National Grid recently agreed to pay approximately $650,000 to settle a 2018 natural gas explosion in Herkimer County that destroyed an entire home and settled a 2018 gas explosion in Long Island for nearly $2 million (18-G-0716 and 15-G-0298).

According to a report released by the U.S. Public Interest Research Group’s Educational Fund, a gas pipeline incident occurred roughly every 40 hours in the U.S. between 2010 and 2021, with 2,600 of those incidents being serious enough to report to the federal government and resulting in the death of 122 people.