November 15, 2024

ERCOT Board of Directors Briefs: Aug. 16, 2022

Board Agrees to Lower Unsecured Credit Limit for Counterparties

AUSTIN, Texas — ERCOT’s Board of Directors last week unanimously eliminated unsecured credit limits for counterparties in the grid operator’s markets, rejecting stakeholder approval of a protocol change tabled since April.

The Technical Advisory Committee in April had modified ERCOT’s original nodal protocol revision request (NPRR1112) by reducing the unsecured credit limit from $50 million to $30 million, rather than cut the limit to zero. The grid operator then appealed that vote to the board in April, only to see it sidelined with a request for information on other RTOs’ unsecured credit practices. (See “ERCOT’s Credit Limits Align with Others,” ERCOT Technical Advisory Committee Briefs: May 25, 2022.)

According to ERCOT staff, the decision leaves the grid operator as the only one without unsecured credit limits between counterparties. ERCOT currently has $1.36 billion in outstanding unsecured credit.

Kenan Ögelman, the grid operator’s vice president of commercial operations, told the board during its Aug. 16 meeting that staff continue to recommend eliminating unsecured credit. Using unsecured credit moves credit costs from those receiving unsecured credit to the rest of the market and ultimately load, he said.

Ögelman also apologized for staff’s error during the June board meeting, when he said lowering the credit limit to zero would eliminate about $1 billion in the outstanding amount. “Actually, it was more in the $300 million range,” he said. (See “Maintenance Outage Scheduling Methodology Approved,” ERCOT Board of Directors Briefs: June 21, 2022.)

Kenan Ogelman Darrell Cline 2022-08-16 (RTO Insider LLC) Alt FI.jpg

ERCOT’s Kenan Ögelman (left) listens as Garland Power & Light’s Darrell Cline lays out TAC’s position on unsecured credit.  | © RTO Insider LLC

Darrell Cline, general manager for Garland Power & Light, advocated TAC’s position before the board. He said other “more appropriate” vehicles exist to target credit risk, pointing to NPRR1067, which sets market entry qualifications, continued participation requirements and credit risk assessments. The measure has been open since January 2021.

“Staff continues to believe that reducing unsecure credit is best for ERCOT. No other sophisticated markets allow for that,” interim CEO Brad Jones said, ticking off the Intercontinental Exchange, New York Stock Exchange and New York Mercantile Exchange as examples. “The very fact that the other” grid operators allow it is not “a compelling argument that we should do it as well. We know there’s a risk there.” He offered NPRR1067 as an opportunity to revisit the discussion.

The measure now goes before the Texas Public Utility Commission; it would become effective Oct. 1, 2023, allowing municipal utilities with fiscal years that end Sept. 30 to first close their books.

[EDITOR’S NOTE: An earlier version of this article incorrectly said that the board had reduced the unsecured credit limit to $30 million from $50 million.]

Staff Studying 17 GW of Crypto Load

ERCOT staff told directors that they are studying more than 17 GW of crypto mining load as it prepares its mid- and long-term forecasts.

Jeff Billo 2022-08-16 (RTO Insider LLC) FI.jpgJeff Billo, ERCOT | © RTO Insider LLC

Alluding to the Texas bitcoin rush, Jeff Billo, director of operations planning, said crypto load has grown since the studies began.

“Not all of that will be constructed, but the challenge is how much will be there in three to four years,” he said. “Midterm, it’s a challenge because [crypto load] is very price-responsive, more price-responsive than we have seen with other demand response in the past.”

ERCOT’s midterm load forecast uses two vendor models and five staff models to take an hourly look seven days into the future. It is updated hourly.

The long-term forecast uses one staff-developed model to provide an hourly forecast 10 to 30 years out and is updated annually.

Crypto miners have been drawn to Texas by its relatively low wholesale energy prices and because ERCOT pays industrial users to shut down during tight conditions. Their data farms typically use enormous amounts of power.

Billo said the amount of crypto load is not “constructive” to ERCOT’s planning models. He said staff are working with stakeholders to understand how much of it will show up. “We have to improve our processes to understand that behavior and build that into our model.”

The 2023 load forecast will be included in ERCOT’s December capacity, demand and reserves report, which projects 10 years into the future.

Directors Exert Control over Bylaws

The board’s Human Resources and Governance (HR&G) Committee agreed during its Aug. 15 meeting to modify ERCOT’s governing bylaws and other organizational documents, moving the authority for making future bylaw changes from corporate members to the directors and taking away members’ ability to veto the revisions.

Director Peggy Heeg, the committee’s chair, said that legislation passed last year after the February winter storm laid out “checks and balances” for ERCOT’s governance. She said it also required the PUC to approve all bylaws and their changes.

“While legislators and the governor clearly intended this board to have control over ERCOT, they were also very clear that corporate members are also valued contributors … and should have a voice in the bylaw-amendment process,” she said.

“It’s very clear from [the legislation] that this is what we’re directed to do,” board Chair Paul Foster said in agreeing with Heeg.

The committee urged the board to engage with members as it modifies the bylaws. Heeg also proposed the board to “move forward deliberately” in revising TAC’s reporting relationship and its structure.

“The market participants and corporate members have a very valuable place in contributing to this board,” Heeg said.

Under the suggested changes, members will still be able to propose amendments or comment on those under consideration. Board Vice Chair Bill Flores also said TAC will keep a seat at the table, “where it’s most valuable.”

ERCOT’s legal staff said it will take the board’s input and produce a redlined version of bylaw changes that can be shared with members. Their goal is to produce a final document by year-end for approval by the board and PUC.

Board Approves Tx Projects

The board approved two transmission projects with a combined capital cost of more than $760 million previously endorsed by TAC and recommended by the Regional Planning Group. (See “Members Endorse Two Tier 1 Transmission Projects,” ERCOT Technical Advisory Committee Briefs: July 27, 2022.)

The Bearkat-North McCamey-Sand Lake project in West Texas — consisting of two double-circuit, 345-kV transmission lines totaling about 165 miles — has an estimated cost of $477.6 million in 2021 dollars, up from $371 million in 2019 dollars. Oncor, Lower Colorado River Authority Transmission Services and Wind Energy Transmission Texas expect to complete the project in June 2026.

The Roanoke upgrade project north of the Dallas-Fort Worth area involves 7 miles of 138-kV lines, 26 miles of 345-kV lines, four 345/138-kV transformers and five 138-kV low-voltage buses. Oncor, the incumbent transmission service provider, expects to complete the upgrades by May 2025 at a projected capital cost of $285.9 million.

The projects are classified as Tier I builds because their costs exceed a $100 million threshold. Their status requires they receive TAC endorsement and the Board of Directors’ approval.

The directors also approved ERCOT’s proposal to change the reliability unit commitment cost-scaling parameter from 20% to 100%, effective Sept. 1. The grid operator’s greater use of the RUC process under its conservative operations posture this year has led to operators making many of their decisions outside of the process’s economic-based recommendations, leading to inefficient commitments.

The board also approved eight NPRRs, two other binding requests (OBDRRs), single revisions to the Planning Guide (PGRR) and the Retail Market Guide (RMGRR), and a system change request (SCR):

  • NPRR1085: changes the physical responsive capability calculation and dispatch’s validity by requiring quicker updates from qualified scheduling entities (QSEs) on telemetered resource status, high sustained limit and other relevant information.
  • NPRR1131: changes controllable load resource’s participation in non-spinning reserve from offline to online non-spin. The change sets a bid floor of $75/MWh, equivalent to generation resources’ offer floor when providing online non-spin. If a QSE also assigns responsive reserve (RRS) and/or regulation up service to a controllable load resource that has been assigned non-spin, the sum of RRS, reg-up and non-spin ancillary service resource responsibilities will be assigned a $75/MWh offer floor.
  • NPRR1133: clarifies the responsibilities of DC tie facility owners and operators for reporting DC tie model data.
  • NPRR1134: removes references to first available switch date (FASD) after recent mass transition/provider of last resort events indicated ERCOT’s use of FASD when processing switch transactions created an unintended negative experience for customers being transitioned from a bankrupt retailer.
  • NPRR1135: modifies the definition of real-time generation resources with an offline non-spin (OFFNS) schedule to allow non-zero values for the billing determinant only if the resource is offline when it telemetered OFFNS. This ensures an accurate settlement when an online resource erroneously telemeters OFFNS.
  • NPRR1136: adds clarifying language to the logic in place as fast frequency response is developed to ensure a QSE does not replace a regulation service with fast-responding regulation service.
  • NPRR1137: replaces the annual requirement to review the OBD list with a four-year review cycle.
  • NPRR1142: increases emergency response service’s (ERS) annual budget from $50 million to $75 million and gives ERCOT the ability to contract ERS for up to 24 hours in a standard contract term.
  • OBDRR040: removes the controllable load resource providing non-spin schedules and regulation service schedules from the capacity calculations to align with NPRR1131.
  • OBDRR042: increases the ERS annual budget and makes other administrative changes to the program.
  • PGRR101: clarifies that a DC tie’s owner will provide the appropriate dynamic model data to its tie operator, which will then provide the data to ERCOT.
  • RMGRR168: synchronizes ERCOT’s role and responsibilities with current market transactional solutions upon the removal of the “out-of-cycle” switch term and market process.
  • SCR822: creates a new daily integration report and dashboard for energy storage resources similar to the current wind and solar integration reports and dashboards.

FERC OKs GreenHat Settlements

The principals of GreenHat Energy will pay PJM almost $1.4 million to settle claims over the company’s spectacular default in the RTO’s financial transmission rights market, which cost members almost $180 million.

GreenHat founders John Bartholomew and Kevin Ziegenhorn will pay $375,000 and $400,000, respectively in disgorgement, with the estate of founder Andrew Kittell paying $600,000 under settlements approved by FERC in two orders Aug. 19 (IN18-9). Kittell died in January 2021.

Bartholomew and Ziegenhorn also agreed not to participate in FERC-jurisdictional markets for 10 years. “In the case of PJM markets, the agreed prohibition is permanent,” FERC said.

The GreenHat principals also consented to the entry of a judgment of $179.6 million against the company in a lawsuit pending in state court in Texas, but with the company insolvent, the judgment is moot.

“GreenHat and the [Kittell] estate state they are unable to pay the assessed amounts and have furnished confidential financial disclosures sufficient to substantiate their claim,” FERC said. “The agreed settlement amount is based on ability to pay in light of financial information provided by the estate and GreenHat to [FERC’s Office of] Enforcement.”

The disgorgements by Bartholomew  and Ziegenhorn also were based on their ability to pay, FERC said.

The three founded GreenHat in 2014 to trade FTRs in PJM, eventually acquiring a portfolio of 889 million MWh. When the company defaulted in June 2018, however, the company had less than $560,000 in collateral with PJM. (See Doubling Down — with Other People’s Money.)

“Over the next three years, GreenHat’s default required PJM to assess other members of PJM a total of $179,600,573,” FERC said.

Following an investigation, FERC assessed civil penalties of $179 million on the company and $25 million against the three principals, accusing them of violating the commission’s Anti-Manipulation Rule by purchasing FTRs with virtually no upfront cash, planning not to pay for losses at settlement and selling profitable FTRs to third parties. The commission said they also purchased FTRs based not on market considerations but to amass as many FTRs as possible with minimal collateral; they also made false statements to PJM about money purportedly owed by Shell Energy North America (NYSE:SHEL) to convince PJM not to proceed with a planned margin call. FERC said they also submitted inflated bids into an FTR auction in an attempt to inflate the clearing price of FTRs that Shell had purchased from GreenHat. (See FERC Levies $242M in Fines on GreenHat, Owners.)

Under the settlement, the principals did not admit or deny the alleged violations. GreenHat agreed to dismiss its lawsuit seeking more than $62 million from Shell in addition to the $13.1 million that Shell paid GreenHat in 2016 and 2017.

PJM and Shell also agreed to settle their billing dispute over Shell’s obligations to indemnify PJM over its FTR trades with GreenHat. PJM also agreed to drop a lawsuit it filed in California against the Kittell estate.

“This settles all pending litigation,” PJM spokesman Jeff Shields said Monday. “We appreciate FERC’s leadership on resolving these matters.”

Wash. High Court Shuts Down Cap-and-trade Challenge

Washington’s Supreme Court ruled Thursday that the state’s most prominent anti-tax activist cannot put a 2021 cap-and-trade law to a non-binding statewide public ballot. 

The justices ruled 7-1 that Tim Eyman filed his challenge to the state’s cap-and-trade program one year too late.  

Eyman has been a controversial anti-tax activist and fundraiser in Washington for the past 30 years. He is currently facing $5.4 million in fines and other penalties for numerous irregularities in his fundraising and campaign finances. Most of his anti-tax public ballot initiatives have failed or were disqualified because their language violated state laws. 

Eyman filed for bankruptcy in 2018 and a superior court judge ruled last year that he must liquidate his assets to pay the $5.4 million. 

Washington’s legislature passed a law creating the nation’s second cap-and-trade program in the spring of 2021. (See Wash. Becomes 2nd State to Adopt Cap-and-trade.) Eyman argued that the new program represents a tax, which state law requires to be put to a public non-binding advisory vote in the first election after the bill is passed. That would have translated to a November 2021 public ballot. 

But neither Eyman nor anyone else called for a public ballot on the bill in 2021, when opponents of the program still had legal standing, the Supreme Court’s ruling said. 

Eyman earlier this year filed suit calling for a public ballot on the cap-and-trade law to be held in November. A Thurston County Superior Court judge provided a temporary restraining order preventing the state from printing its voters’ pamphlets for the upcoming election, pending resolution of the litigation. The state immediately appealed to the Supreme Court to get a quick resolution.

SREA Criticizes Lack of MISO South Planning in FERC Tx Proceeding

The Southern Renewable Energy Association (SREA) said last week that while MISO may have a robust transmission planning process, FERC should know that the RTO’s South region does not share in it.

The sentiment was made in comments to the commission under its transmission planning notice of proposed rulemaking. SREA accused Entergy, which comprises the majority of MISO South, of impeding and delaying transmission planning to benefit its bottom line. (See Battle Lines Drawn on FERC Tx Planning NOPR.)

“Overall, transmission planning in the south is lagging behind other regions,” SREA said. “We are not prepared for the energy transition already underway, and some utilities in the region are actively opposing reasonable transmission planning practices. This places [President] Biden’s Inflation Reduction Act at risk of not reaching its full potential.”

The association said MISO South is a patchwork of load pockets that include Amite South, Downstream of Gypsy, West of the Atchafalaya Basin (WOTAB), Texas East and Texas West. SREA said Texas uses the load pockets to its advantage, constructing new generation in them and using the load pockets to justify “underinvesting in transmission to the benefit of its generators.”

SREA said power outages were more prevalent in MISO South during the February 2021 winter storm. All eight of the transmission lines into New Orleans failed or collapsed during Hurricane Ida last year, leading to nearly a week of power outages. Estimates for Entergy grid repairs have topped $4.4 billion, about a third of all of MISO North’s proactive long-range transmission plan (LRTP) projects, the group said.

SREA said that while Entergy’s 2013 incorporation into MISO was meant to put an end to the utility’s anticompetitive business practices, the RTO “has not been entirely effective at increasing competition.” It said MISO South consultants bogged down planning that could have come from the grid operator’s 2017 regional overlay study.

“When MISO South slows down transmission planning at MISO, the entire region is negatively affected. Opposition to MISO’s transmission planning effectively delayed transmission by three years while MISO retooled to start the LRTP process,” SREA said.

SREA pointed out that MISO was forced to bifurcate cost allocation between the Midwest and South in its LRTP so it could move forward on new transmission lines in the Midwest without risking delay from the more hesitant southern stakeholders.

MISO approved the first of four LRTP portfolios in late July. It contains 18 projects costing more than $10 billion, all destined for MISO Midwest. (See MISO Board Approves $10B in Long-range Tx Projects.)

SREA also touched on the fact that the RTO has been unable to build any market efficiency projects in the South. Its lone competitive market efficiency build, the Hartburg-Sabine Junction project, is all but certain to be cancelled because Entergy added the 993-MW Montgomery County Power Station in southeast Texas and plans to construct the 1.2-GW natural gas and hydrogen-powered Orange County Advanced Power Station by 2026. The Hartburg-Sabine line was meant to alleviate the WOTAB load pocket. (See MISO on Verge of Cancelling Hartburg-Sabine Tx Project.)

The organization said there is a “demonstrated need to introduce transparency and competition in the region to mitigate the use of utility market power to thwart transmission solutions that would increase reliability and lower customer costs.”

“I think the big idea here is MISO stakeholders went through a really long and arduous process to get where we are on LRTP,” SREA Executive Director Simon Mahan said in an interview with RTO Insider.

Mahan said there’s no need for MISO to “reinvent the wheel” on its transmission planning but emphasized that the grid operator’s long-term planning needs to gain traction in MISO South.

Mahan said he felt a bit “jilted” that MISO Midwest is first in line for long-range transmission planning while MISO South utilities and regulators appear to favor a delay.

“I really hope that the regulators down here read our comments and really take them to heart,” he said.   

MISO so far envisions four LRTP portfolios. It doesn’t plan on addressing MISO South needs until the LRTP’s third iteration.

Mahan pushed back on the notion that the Midwestern portion of MISO needs more urgent transmission planning because it contains an aging coal fleet and a healthier appetite for renewable energy.

“The reality is we have a lot of old gas generation in MISO South that operates similarly to aging coal plants,” he said, noting the region is undergoing its own renewable energy transition.

For years, Mahan said he’s wanted the two regions to share a better transmission connection so they can better share resources. Not addressing the Midwest-South constraint is to the detriment of MISO itself, he said.

“We can plainly see with Winter Storm Uri that getting that connection fixed is a matter of life and death,” Mahan said.  

He said building new import capability in MISO South for the sake of reliability is a must. While little load pockets in the wetlands, forests and swamps of Louisiana made sense decades ago, it isn’t a reliable practice today, he said.

MISO South load pockets in Louisiana (Entergy) FI.jpgMISO South load pockets in Louisiana | Entergy

“We need to connect these regions because as hurricanes are pummeling our coast, it’s becoming clear that generators can’t take the direct hits,” Mahan said.

Mahan said Entergy has a troubling pattern of supplanting transmission lines with new generation.

“This is a clear pattern that we’ve seen with Entergy proposing generation when lines are recommended. People need to know that this is going on so we can come up with solutions for it,” he said. “We’ve seen it enough: Entergy plopping generation at the end of a new, large-scale transmission project, and the project dies. I’m very concerned that this strategy is working, but the generators rarely turn on.”

Mahan said the St. Charles Power Station gas plant, built in place of a 2016 MISO-recommended 230-kV line spanning two substations in the New Orleans area, was derated to about half its capability during the winter storm. He also said Entergy’s new Montgomery Power Station failed to come online during the same extreme weather event.

“Time and time again, Entergy keeps building power plants in these load pockets, and during these extreme events for whatever reason, they can’t turn on. … This isn’t old generation. They’re brand-spanking new power plants,” Mahan said. “The reality is that the lights keep going out in MISO South, and transmission keeps not getting built. Those are pretty damning examples of what’s going on in MISO South.”  

Mahan said he hopes that FERC’s ultimate rulemaking will “codify the good work we’ve done here at MISO to ensure that no region is going to be left behind in the future.”

Entergy had not returned a request for comment at press time about its philosophy on transmission planning.   

ERCOT Board Gives Southern Cross Project a Boost

AUSTIN, Texas — ERCOT’s Board of Directors last week added their endorsement of the Southern Cross Transmission (SCT) merchant project’s last three regulatory directives, imposed to determine whether it can safely interconnect with the Texas grid.

The project, a long-haul HVDC transmission line that would connect the Texas Interconnection with systems in the SERC Reliability region, has been under regulatory review for seven years. It will be capable of carrying 2 GW of power between Texas and SERC over a 400-mile, double-circuit 345-kV line.

More important to the Texas Public Utility Commission and the state’s leadership, SCT has FERC approval and a waiver from its jurisdiction, keeping ERCOT free of federal overview and maintaining its status as an island unto itself.

The project’s developer, Pattern Energy, called the board’s Aug. 16 action an “important milestone” and thanked ERCOT staff for completing the studies ordered by the PUC.

“Today’s action … represent[s] the completion of all studies ordered by the [PUC] to confirm the Project can be reliably interconnected with the ERCOT grid,” said Glen Hodges, Pattern’s vice president of business development. “Once completed, Southern Cross Transmission will provide substantial reliability benefits to all Texans who rely on the ERCOT grid, providing access to alternate sources of reliable and affordable power during emergencies such as Winter Storm Uri and the recent extreme heat-related demands on the grid.”

“For the last five years or so, we’ve been resolving the directives and getting this project ship shape,” ERCOT assistant counsel Nathan Bigbee said. “These last three [directives] get closure and regulatory certainty to move forward with this project.”

The directives are:

  • 1: creates a new market participant type, “Direct Current Tie Operator.” A nodal protocol revision request (NPRR857) approved in 2018 created the DCTO role, but SCT has told the grid operator it does not plan to join an appropriate market segment at this time. That led staff to conclude no bylaw revisions are needed yet.
  • 11: finds that costs identified by the PUC have been appropriately addressed by resolving each of the commission’s 14 directives and through a memorandum of understanding between ERCOT and SCT. Under the agreement, Pattern will fund the projects needed to accommodate the tie; it has already been compensating ERCOT monthly for related costs.
  • 12: determines that costs associated with DC tie exports have been sufficiently addressed by the other directives’ resolution and that no further revision to any cost-allocation mechanism is necessary.

Bigbee told directors that SCT will affect voltage on the eastern side of ERCOT’s system. He said an NPRR will need to be drafted to ensure the project provides voltage support in the region.

The PUC asked ERCOT to address 14 directives and determine whether DC ties should be economically dispatched or subject to a congestion-management plan. Only Directive 2, which requires the grid operator to enter a coordination agreement with the balancing authority on the project’s eastern end, has not been completed. The project’s developers have said that directive is not necessary to the commission’s review and can be closed later.

Garland Power & Light owns the project’s western endpoint and holds a certificate of convenience and necessity granted by the PUC in 2017. The project developers have not yet announced an eastern endpoint.

PUC Commissioner Jimmy Glotfelty has taken the agency’s lead on SCT and filed a memo in January that said it’s time that the commission and ERCOT “close a chapter” on the project and allow it to “stand or fail on its own economic merits.” He believes the review can be finished by the end of October (46304). (See Texas Regulators Boost Southern Cross Project.)

The Technical Advisory Committee earlier endorsed the directives in June. (See “SCT Project Moves Closer to Reality,” ERCOT Technical Advisory Committee Briefs: June 27, 2022.)

SCT supporters got a minor scare when Board Chair Paul Foster mistakenly tried to bring the meeting to an early end just before the project was due to be discussed.

“So that concludes our agenda, and we are now adjourned. Thank you all,” Foster began before he was quickly interrupted.

“No, no. Sorry … we have a few more voting items,” ERCOT General Counsel Chad Seely said, keeping the meeting on track.

Grid United Files CCN in West Texas

A second HVDC merchant project is taking shape on the western side of ERCOT’s system, where Grid United, led by a familiar face, has applied with the PUC for a CCN (53758).

Grid United’s Pecos West project consists of two proposed 1,500-MW HVDC converter stations in ERCOT’s West Texas region (near Bakersfield) and El Paso in WECC territory. The project would bridge two Texas markets with 250 to 300 miles of an HVDC intertie line.

Skelly-Michael-2019-05-29-RTO-Insider-FI.jpgMichael Skelly, Grid United | © RTO Insider LLC

The company was founded last year by Michael Skelly, who serves as its CEO. Grid United says it seeks to tie regional grids together to improve resilience, increase the reliability of cheap renewable energy and reduce health hazards from fossil fuel energy production.

Skelly was also behind Clean Line Energy Partners, another long-haul developer that was working on five projects at one time, capable of carrying 16.5 GW of energy. Faced with political, regulatory and landowner opposition, Clean Line eventually was forced to sell most of its projects and was out of business by 2019. (See Out of the Game, Skelly Still High on Wind Energy.)

“Texas is blessed with an evolving and abundant power supply. … However, this abundance presents unique challenges, including volatile commodity prices and reliability concerns due to market structures that were not designed for the evolving energy mix the Texas grid is faced with today,” Skelly said in testimony filed with the PUC.

“These challenges, which are especially acute in West Texas where renewable generation has proliferated, will only increase over the decades to come unless steps are taken proactively to address them,” he said.

Grid United’s Texas subsidiary is only seeking approval of the interconnection and will file for full CCN rights once the interconnection is approved. The company says it will obtain all necessary FERC approvals to maintain ERCOT’s jurisdictional status quo.

Former FERC and Texas PUC Chair Pat Wood says the federal commission has policies that would protect the Texas Interconnection from federal interference if it were to strengthen its existing connections to the two national grids.

“We have the ability to build gates to the outside and not become vassals of another king,” Wood said during a panel discussion earlier this year. “We [would still be] in charge of our own grid — and that was built into the federal law.”

Court Blocks LS Power’s Attempts for More Competitive MISO Tx Projects

Transmission developer LS Power was unsuccessful twice with the D.C. Circuit Court of Appeals last week in separate attempts to force MISO to open more projects to competition.

LS Power had sought appeals on two FERC complaints, one where it challenged FERC’s repeated refusal to compel MISO to lower its voltage threshold of competitive economic projects from 230 kV to 100 kV; and another where it contested MISO’s practice of not cost sharing baseline reliability projects (BRPs) beyond the transmission pricing zone in which they’re located.

In a pair of rulings issued Aug. 19, the D.C. Circuit Court declined to order FERC to revisit its rulings. It said the commission reasonably accepted 230 kV as the market efficiency project threshold (20-1465) and similarly acted sensibly when it kept the cost sharing of BRPs limited to the transmission pricing zone in which they’re physically located (20-1421).

LS Power argued to the D.C. Circuit Court that its business will suffer if MISO is allowed to keep the voltage threshold and local cost sharing of regionally beneficial BRPs in place. The company said those criteria deny it the opportunity to participate in more competitive solicitations for transmission projects.

MISO in 2020 overhauled its cost allocation procedures, lowering the voltage threshold for market efficiency projects that are regionally cost shared from 345 kV to 230 kV, adding two new benefit metrics and eliminating a 20% footprint-wide postage stamp allocation. (See MISO Cost Allocation Plan Wins OK on 3rd Round.)

FERC rejected LS Power’s rehearing requests and complaint that a further reduction to the kilovolt threshold to 100 kV was necessary, concluding that the 230 kV threshold would spur more economic projects and sufficiently expand the number of them eligible for competition. (See La. and Miss. Join MISO, TOs in Opposing Cost Sharing at 100 kV.)

FERC likewise refused LS Power’s joint 2020 complaint with the the Coalition of MISO Transmission Customers and the Industrial Energy Consumers of America, which alleged that MISO’s nearly 10-year old location-based cost allocation methodology for BRPs doesn’t comport with the commission’s principle that beneficiaries of transmission projects should pay for them.

In MISO, BRP costs are allocated only to local transmission pricing zones where project facilities are physically located; costs are recovered by the transmission owners developing the projects. They are not open to competitive bidding.

The court said LS Power’s examples of BRPs with benefits spillover “was limited to a relatively small number” and “did not necessitate a categorical finding that location-based cost allocation is unjust and unreasonable.” It said LS Power’s “crown jewel of new evidence” was a report containing a line-outage analysis that showed of 29 baseline reliability projects approved by MISO between 2013 and 2018, 12 showed they could deliver more than “de minimis” benefits beyond their transmission pricing zone.

The court added that FERC “need not consider cost allocation rules on a project-by-project basis, which would unravel the framework of ex ante tariffs established by Order 1000.”

In its voltage threshold ruling, the D.C. Circuit Court also rejected LS Power’s ask that MISO be prohibited from employing an “immediate need reliability exception,” where the RTO can bypass a competitive solicitation process for certain urgently needed reliability projects. The court borrowed a line from FERC’s Order 1000, noting that “if the time needed to solicit and conduct competitive bidding would delay the project and thereby threaten system reliability, then competitive bidding would not be required.”

CAISO Updates EDAM Straw Proposal

CAISO issued a revised straw proposal last week for its planned day-ahead expansion of the Western Energy Imbalance Market, currently a real-time market that covers large portions of 10 states and one Canadian province.

The updated proposal, released Aug. 16, adds provisions on transmission commitment, resource sufficiency and firm energy contracts following a series of technical workshops and stakeholder meetings to iron out differences on the more difficult issues.

“This revised straw proposal for the extended day-ahead market (EDAM) reflects significant stakeholder input and design changes from the initial April 28, 2022, straw proposal,” the ISO said. (See CAISO Issues EDAM Straw Proposal for the West.)

Among the major changes are refinements to the EDAM’s proposed transmission commitment framework.

The initial straw proposal stated that unsold, firm available transfer capability (ATC) should be offered by EDAM participants to support transfers between balancing authority areas (BAAs) in the West.

An EDAM entity would be expected to “make available all remaining unsold firm ATC at an intertie with an adjoining EDAM BAA” by 10 a.m. in the day-ahead market and to stop open-access transmission tariff sales of firm ATC at the intertie between 10 a.m. and 1 p.m. while the day-ahead market was running, it said.

EIM-Map-Updated-2022-07-04-(CAISO)-Alt-FI.jpgThe EDAM could extend across much of the territory now included in the WEIM’s real-time market. | CAISO

 

Stakeholders and the ISO, however, did not settle on some specifics of the plan.

The revised straw proposal says that “unsold transmission by the transmission provider will be made available to the market hurdle-free. Transmission customers can voluntarily release transmission rights for EDAM optimization, and the ISO will allocate transfer revenue associated with those rights directly to the transmission customer.”

“The design also includes a proposed mechanism for transmission providers to recover potential foregone transmission revenues resulting from their participation in EDAM. This seeks to keep transmission providers as whole as possible from a transmission revenue recovery perspective.”

Resource Sufficiency

The proposal for a resource sufficiency evaluation (RSE) in the EDAM was left partially incomplete in April. The RSE test is intended to keep participants from leaning on the market for internal capacity needs, but consequences for failing the test — one of the most controversial issues in the EDAM stakeholder process so far — were not delineated in the first straw proposal.

Stakeholders had discussed financial penalties and transfer limits but did not reach agreement.

“Although there was no consensus regarding a particular approach, stakeholders generally preferred some form of financial consequence for failure, rather than a complete freezing of transfers in the day-ahead time frame, which could be detrimental to reliability,” the straw proposal said.

After multiple technical workshops, the revised straw proposal “focuses on an administrative surcharge[s] under all conditions to incentivize meeting the RSE. It also introduces mechanisms to address ISO [load-serving entities’] concerns regarding their discretion to manage supply above what the ISO needs to meet its RSE to better manage grid reliability challenges if conditions change between day-ahead and real-time.”

Firm Energy Contracts

The revised proposal also introduced a “tagging mechanism,” a means of electronically monitoring and recording an energy transaction, for firm energy contracts.

In a firm energy contract, the “supplier takes on the obligation to deliver the generation and make the necessary transmission arrangements” to get the supply to the purchasing or sink BAA, but “neither the source of the generation (or source BAA), nor the transmission path is known by the time of the day-ahead market (10 a.m.) when bids into the market are due.” That information “becomes known later,” it said.

“In a day-ahead market context, the lack of source specificity and transmission path pose a challenge in modeling the expected flows across the system,” it said. “Nevertheless, the ISO recognizes these arrangements are an important source of supply in the West today.”

Uncertainties about source and transmission require a tagging mechanism to “provide greater confidence in these arrangements,” it said. “Intertie bids at the ISO border that are under contract to an ISO LSE or otherwise have a contract under the ISO tariff will be eligible for the ISO RSE and will also be subject to the tagging requirements.”

Additional Features

Other provisions in the revised straw proposal include:

  • a convergence bidding proposal that maintains a one-year transition period to convergence bidding for EDAM entities. “After that first year, the EDAM entity will have the option to adopt convergence bidding in their area or elect for another year of transition,” it says. “After the second transition year, an EDAM entity would be expected to transition to convergence bidding, absent any findings that doing so poses adverse outcomes.”
  • an equal sharing of transfer revenues “across all interfaces between EDAM BAAs, subject to commercial arrangements that may require exceptions. In addition, in instances where congestion arises from an internal intertie constraint enforced within a BAA, the ISO will allocate the congestion revenue fully to the BAA where the constraint is modeled.”
  • a greenhouse gas accounting and reporting protocol in which the EDAM will start with a “resource specific approach to GHG accounting because this is a known, implementable approach that California ISO builds upon and enhances the current WEIM framework. Throughout this initiative, however, we will continue to vet and evaluate the alternate approaches.”
  • an EDAM administrative fee arrangement under which a “systems operations charge will be applied to metered flows in megawatt-hours of supply and demand. This is a similar assessment to the grid management charge system operations charge.”

Meetings to discuss the revised straw proposal are scheduled for Aug. 29 (virtual only) and Sept. 7-8 (virtual and in person.) The EDAM stakeholder initiative webpage contains additional information on the upcoming meetings and anticipated EDAM development milestones.

PJM MRC/MC Preview: Aug. 24, 2022

Below is a summary of the issues scheduled to be brought to a vote at the PJM Markets and Reliability and Members committees on Wednesday. Each item is listed by agenda number, description and projected time of discussion, followed by a summary of the issue and links to prior coverage in RTO Insider.

Markets and Reliability Committee

Consent Agenda (9:05-9:10)

B. Members will be asked to endorse revisions to Manual 6: Financial Transmission Rights as part of a periodic review and changes to conform with tariff revisions intended to increase transparency into and the efficiency of the RTO’s auction revenue rights and financial transmission rights markets. The changes were approved by FERC in March (ER22-797). (See FERC Accepts PJM ARR/FTR Market Changes.)

Endorsements (9:10-10:15)

1. Variable Environmental Costs and Credits (9:10-9:35)

The MRC will be asked to approve a proposed update to rules governing variable environmental charges and credits and their inclusion in cost-based energy offers. Generation units receiving production tax credits or renewable energy credits must reflect them in their fuel-cost policies when submitting non-zero cost-based offers into the energy market. The changes will include revisions to Manual 15: Cost Development Guidelines and Operating Agreement Schedule 2. (See “Variable Environmental Costs and Credits,” PJM MIC Briefs: May 11, 2022.)

Issue Tracking: Variable Environmental Costs and Credits

2. 2022 Quadrennial Review (9:35-10:15)

The MRC will cast advisory votes on four alternative sets of capacity auction parameters as part of its 2022 Quadrennial Review. Members will be asked to select one of the packages from PJM, the Independent Market Monitor, Calpine and Cogentrix for a recommendation to the Board of Managers consideration. (See “2022 Quadrennial Review,” PJM MRC/MC Briefs: July 27, 2022.)

Issue Tracking: 2022 Quadrennial Review

Special Members Committee — Quadrennial Review

Endorsements (1:25-2:15)

1. 2022 Quadrennial Review (1:25-2:15)

The MC also will take advisory votes on the proposed Quadrennial Review packages. (See MRC item 2.)

FERC Approves SPP Request for Uncertainty Product

FERC last week accepted SPP’s proposed tariff revisions to add an uncertainty reserve product to its Integrated Marketplace (ER22-914).

SPP said the product will address the need for flexible capacity when realized generation, load and net scheduled interchange deviate from its forecasts. The rising penetration of renewable resources in the RTO’s resource mix has increased the variability that it must manage in its market and reliability operations, it argued.

The RTO will procure uncertainty reserves by reserving a portion of a dispatchable resource’s upward ramping capability to address increasing net obligations in future dispatch intervals.

Resources that can follow real-time dispatch instruction and increase and maintain its output, once the specified output is met, for at least one hour can provide the product. That applies to both online and offline resources.

The grid operator’s resources will make themselves available through self-certification but can opt out with qualification and dispatch status. SPP will derive the value of resources clearing online uncertainty reserve using a loss-of-opportunity metric, similar to how it treats its existing ramp capability-up product. Offline resources offering uncertainty reserves will have an offer cap of $1,000/MW and a $0/MW floor; a demand curve will price the product when its availability on the system is scarce.

The RTO will impose a nonperformance penalty on resources when cleared real-time uncertainty reserves does not operate in a responsive manner.

SPP’s Market Monitoring Unit intervened in support of the RTO, saying the changes would significant improvements over manual commitments and will provide a market solution for midterm ramp capacity. That will result in increased flexibility to meet ramping needs, increased price accuracy for online resources and increased price transparency of ramping capacity’s value, the MMU said.

In its Aug. 16 order approving the proposal, FERC agreed with SPP’s request for a placeholder effective date so that it can develop the necessary software changes to implement the revisions. The grid operator expects the changes to be ready later this year and committed to specify the effective date at least 30 days in advance.

The tariff revisions were filed with FERC after the SPP Board of Directors and stakeholders approved the proposal in July 2021 after several years of development. The uncertainty reserve product was one of 21 recommendations made in 2019 by the Holistic Integrated Tariff Team. (See “Uncertainty Product Endorsed,” SPP Markets and Operations Policy Committee Briefs: July 12-13, 2021.)

Battle Lines Drawn on FERC Tx Planning NOPR

FERC’s proposed overhaul of its transmission planning and cost allocation rules received mostly supportive comments from industry stakeholders, but some criticized its requirements as overly prescriptive and said 20-year planning horizons could lead to speculative and unnecessary projects.

Stakeholders also disagreed sharply over whether the commission should reinstitute a federal right of first refusal (ROFR) for incumbent transmission owners.

More than 180 comments had been filed by utilities, public interest groups, industrial consumers, RTOs and ISOs and state officials by Wednesday’s 5 p.m. ET deadline (RM21-17). Reply comments are due Sept. 19.

Marginal Value of Tx (Lawrence Berkeley National Laboratory) Content.jpgCongestion across regions is often higher than congestion within regions, suggesting interregional transmission could produce economic gains, Lawrence Berkeley National Laboratory found. | Lawrence Berkeley National Laboratory

The Notice of Proposed Rulemaking, approved by the commission April 21 on a 4-1 vote, would direct transmission providers to identify infrastructure needs on a long-term, forward-looking basis and propose a list of benefits on which they would base their selections of proposed projects.

The NOPR said the new rules would help planning entities prepare for the growth of renewables, new sources of demand such as electric vehicles and extreme weather events, expected to increase as climate change worsens. (See FERC Issues 1st Proposal out of Transmission Proceeding.)

As always, numerous commenters urged the commission to allow regional flexibility and not to impede innovations already being pursued.

The ISO/RTO Council (IRC), representing the six FERC-regulated grid operators, said “many” of its members already engage in “long-term planning … or have ongoing initiatives” to develop such procedures. MISO, CAISO, NYISO and SPP employ a 20-year horizon in at least some of their planning processes, while PJM uses 15 years and ISO-NE uses 10 years, the IRC said.

The IRC said the commission was “overly prescriptive” on some issues.

“The proposed rule is very focused on process but needs to provide more clarity on how these processes produce actionable results,” the IRC said. “Without discretion to adapt the scenarios, factors and benefits to regional circumstances, the final rule could end up leading to more conflict, rather than useful transmission planning for needed infrastructure. Instead of prescribing detailed procedures, the IRC believes that the final rule should state high-level, long-term planning principles that transmission planners must consider, and then authorize them to craft their own processes that are tailored to their regional needs.”

ISO-NE cautioned the commission against setting uniform implementation requirements for long-term scenario analyses or “hardwiring these details into the region’s tariff.”

“In ISO’s experience with transmission planning based on scenario analysis, these actions will limit the efficacy of the studies,” it said.

SPP added: “If the commission specifies requirements that are expansive in scope and prescriptive in detail, this could become duplicative with SPP’s current processes and initiatives and place unnecessary burden on the future state of SPP planning.”

20-Year Planning Horizon

Commenters — including Minnesota’s Public Utilities Commission and Department of Commerce, the SPP Market Monitoring Unit and the U.S. Department of Energy — endorsed FERC’s call for a minimum 20-year time horizon for transmission planning, with reassessments and revisions to the scenarios at least every three years.

“Traditional transmission solutions that benefit an entire region can take more than a decade to site, permit, and construct and require planning that is more than a decade into the future. Creating long-term scenarios that are at least 20 years into the future will capture power sector changes that occur during transmission development,” DOE said. “However, for the evaluation period, the department encourages the commission to consider requiring an evaluation of transmission costs and benefits over a minimum of 30 years after in-service dates rather than the 20 years proposed in the NOPR.”

But others, including the Nebraska Power Review Board, said any 20-year horizon should be used only for guidance and not to identify transmission upgrades.

“While there is no crystal ball when it comes to transmission planning for the future, PJM continues to believe a 15-year planning horizon allows for sufficient time to identify, plan, and obtain siting and permitting approval and to construct regional transmission facilities while reducing input assumption risks associated with a 20-year horizon,” the RTO said.

Calpine Hay Road Energy Center 2022-06-29 (RTO Insider LLC) Content.jpgCalpine Hay Road Energy Center, Wilmington, Del. | © RTO Insider LLC

 

Industrial Energy Consumers of America, the American Forest & Paper Association, the PJM Industrial Customer Coalition and the Coalition of MISO Transmission Customers said “a 20-year planning horizon for new transmission has not been shown to be just and reasonable.”

NRG Energy (NYSE:NRG) said a 20-year planning horizon should be “only for purely informational purposes and not as a basis to mandatorily allocate investment costs.” It said a 10-year maximum planning horizon was more appropriate when applying involuntary cost allocation.

“While it is true that transmission development takes time and thus can be served by a longer view forward, it is also true that identifying a transmission project solution up to 20 years in the future could prove to be problematically speculative,” said the Electric Power Supply Association (EPSA). “A longer view could also lock in a specific approach to the detriment of any other solution that could be developed on a more timely basis or close the door to options for a transmission project that does not reach the final phase of development, which is all the more likely decades out. This could also prove to be short-sighted based on the pace of technological change.”

WIRES, which represents transmission providers and developers, said FERC should allow variances from the 20-year requirement “in order to account for regional differences or circumstances that would render such a timeline inappropriate.”

Non-profit GridLab said the NOPR “conflates the planning horizon with the time horizon over which benefits and costs are calculated in benefit-cost analysis (BCA).”

“FERC should clarify the distinction between the two … while maintaining requirements for a 20-year planning horizon and a 20-year period for BCA. The main benefit of a longer planning horizon will likely be capturing changes in transmission value (benefits) over a longer time horizon, which assumes that the value of regional transmission will look very different in the 2030s than it does today. There is indeed evidence that this will be the case, though some of the forces driving change in regional transmission value will increase value (e.g., growth in wind and solar generation, increased risk of extreme events), while others will decrease it (lower cost energy storage, growth in distributed energy resources). The balance can only be determined through rigorous planning and risk assessment.”

Grid-enhancing Technologies

FERC’s support for grid-enhancing technologies received wide support, but the Los Angeles Department of Water and Power (LADWP) said the commission’s singling out of technologies such as dynamic line ratings (DLRs) and advanced power flow control devices (APFC) “seems inappropriate.”

“Transmission providers should have the range of available technologies for evaluation of solutions to meet economic, reliability and security needs in their respective regions,” LADWP said. “A rule that specifically calls out certain technologies as solutions is in danger of being biased, prescriptive and incomplete.”

ISO-NE said FERC should not mandate use of DLRs in lieu of transmission. “This technology cannot substitute for transmission facilities needed to solve system needs,” it said.

Potomac Economics, which performs market monitoring for MISO, NYISO, ISO-NE and ERCOT, said the commission should also require transmission providers to consider transmission switching and network optimization in addition to DLR and APFC. “Like GETs, network optimization can allow a transmission operator to circumvent a limiting transmission facility and substantially mitigate the associated congestion. In this case, investing millions in upgrading such a facility could prove wasteful and inefficient,” it said.

The Working for Advanced Transmission Technologies (WATT) Coalition, a trade group supporting GETs deployment, asked the commission to be more prescriptive, saying it should “specifically require evaluation of APFC for thermal overloads that fall within 50% of the line rating” and for network upgrades for new loads.

Right of First Refusal

There was also no consensus on the commission’s proposal to allow incumbent transmission owners a federal ROFR on regional projects on the condition that they partner with an unaffiliated company with a “meaningful level of participation and investment” in the project. (See ANALYSIS: FERC Giving up on Transmission Competition?)

Among those opposing the proposal were Electricity Consumers Resource Council, which represents large industrial consumers, and EPSA.

“Rather than less independence and accountability, there must be more independence and accountability in regional transmission planning processes to ensure that all options are offered and assessed to meet expected cost and time parameters pursuant to the planning process,” EPSA said.

“Because competition serves to discipline costs, allowing the incumbent transmission utility to exercise a ROFR, even if done in partnership with another entity, could expose load to higher costs,” said the Pennsylvania Public Utility Commission. “To the extent that FERC determines that the elimination of the ROFR by Order No. 1000 resulted in transmission providers focusing on local projects rather than regional projects, the solution is not to appease incumbent transmission owners’ reluctance to engage in competition from nonincumbent transmission developers, by restoring the ROFR. … Such a mechanism clearly grants preferential treatment to the incumbent transmission providers and discriminates against competitive transmission developers, in violation of the principle of an ‘open’ transmission planning process, as articulated in Order No. 890.”

FERC-Open-Meeting-2022-06-16-(RTO-Insider-LLC) Content.jpgFERC approved the transmission planning NOPR in April. | © RTO Insider LLC

 

NRG said FERC should withdraw the proposal “and instead eliminate formula ratemaking and other aspects to its regulatory scheme that have caused transmission developers to avoid regional projects.”

Transmission owners and the Edison Electric Institute expressed support for a renewed ROFR.

“Although in some instances, the lack of a ROFR may have arguably increased the number of innovative and/or cost-effective transmission options for consideration, it has also caused delays and limited opportunities for dialogue between transmission developers, market participants and RTOs/ISOs, in addition to not delivering regional transmission projects under the time frames necessary to meet increasingly aggressive climate targets,” WIRES said.

NEPOOL said it does not have a formal position on the conditional ROFR but noted it has previously advocated for competitive processes for transmission development. “To the extent the final rule provides for a conditional ROFR, the commission should maximize the opportunities and requirements for competitive processes to be used within that construct,” NEPOOL said. “This objective could be achieved potentially through guidelines for the criteria to be used in establishing joint ownership and development of regional transmission facilities.”

The Minnesota agencies noted that the state’s legislature has backed a state ROFR and said FERC’s joint ownership model “would create additional complexity but is not likely to provide the anticipated innovation and cost-control benefits.” (See Courts Uphold Minn. ROFR, MISO Cost Allocation.)

“Continuing to clearly align the responsibility to construct, own and maintain the high-voltage transmission system in our state with the related decision-making authority that has been given to the responsible utilities remains the best ownership model, at least for now,” they said.

States’ Roles

State regulators and others urged FERC to let states take a central role in planning.

ISO-NE noted that the New England States Committee on Electricity’s role in determining the range of scenarios to be plugged into the grid operators’ studies. Therefore, ISO-NE said, “the states should be responsible for determining whether to move forward with transmission and the associated cost allocation method, with the ISO playing a supporting, technical role.”

FERC should “explicitly authorize or allow for … greater state involvement in all aspects of policy-based transmission planning — not just the criteria for selecting and methodology for allocating costs of long-term transmission facilities,” ISO-NE said.

“FERC should reframe long-term regional transmission planning as an informational process with no attendant project selection or construction obligations unless the affected state regulators first support such actions consistent with their regulation of the public utilities subject to their respective jurisdictions,” said the Alabama Public Service Commission.

The National Association of State Energy Officials praised FERC’s creation of the Joint Federal-State Task Force on Electric Transmission as a “welcome advancement of federal-state coordination.”

But it said “FERC’s engagement on these issues needs to include additional state agencies, such as state energy offices.”