Geothermal Picks up in the West but Hurdles Remain, WGA Panelists Say

PHOENIX, Ariz. — There is growing excitement about geothermal energy in the Western U.S., with billions of dollars invested in the industry, but panelists at a Western Governors’ Association workshop said supply chain issues and permitting complexity remain significant challenges.

Michael O’Connor, director of the Mountain West Geothermal Consortium, said during the Dec. 18 workshop that the U.S. leads the world in geothermal power with 4 GW of capacity and enjoys support from the Trump administration.

There has been about $2 billion in investment in the industry over the past few years. Fervo Energy announced Dec. 10 it has raised $462 million toward geothermal development, and other developers are expanding operations, according to O’Connor.

Despite this momentum, commercial lenders remain cautious because of project risks and the difficulty developers face in proving their models are accurate, making it challenging to scale the industry.

“There are some places where we can really see the West leading,” O’Connor said. “Getting to scale is going to require several different projects in several different environments. We need to get over that risk curve … in a lot of different places, and the West has all of that geological variability that you need to demonstrate it.”

Another key to ensuring geothermal success involves knowledge-sharing across state lines, O’Connor said.

“Each of these states should not have to learn how to permit this technology separately,” he said. “This is something that a lot of regional collaboration can be helpful for.”

Developers are testing several types of geothermal technology. The most mature approach is called a hydrothermal system and accounts for roughly 16 GW worldwide. The approach includes looking for naturally occurring conditions that allow hot fluids from underground to spin turbines, O’Connor said.

One of the most commercially viable approaches is called an enhanced geothermal system (EGS). The approach includes leveraging hydraulic fracking between wells in reservoirs to extract heat, O’Connor explained.

Fervo operates an EGS called Project Red in Nevada. One of the company’s main concerns is finding geologic conditions for its systems. Another is transmission availability, according to Marc Reyes, director of interconnection and transmission at Fervo.

“That is a key concern,” Reyes said. “As we all know, the grid is not built to have a lot of excess capacity. Ultimately, cost-causation drives the rates that we all see and pay in our electric bills and by and large, the grid is not built to accommodate very large projects. So that is one of the factors that comes into play … not just identifying perhaps incrementally available capacity on the transmission grid, but where the transmission grid might be suitable for expansion.”

Tim Kowalchik, research director at the Utah Office of Energy Development, said geothermal is “maybe the ideal co-location resource.”

“At its heart, you’re getting heat from the ground, maybe digging some holes, putting pipes in the ground and circulating a fluid,” Kowalchik said. “That really basic system is the same thing that can do district heating; it is the same thing that can give you process heat. That is not true of other generating technologies. There is a larger lift to being able to do sort of multi-use cascades.”

While there are a lot of “exciting” initiatives in the geothermal space, “none of that establishes you a supply chain,” Kowalchik said.

No single company or laboratory can reduce costs enough for utilities to choose geothermal as the least-cost option, he added.

“That takes building at scale, multiple regions to multiple ownership structures … to who is your offtake is going to be incredibly important,” Kowalchik said. “We need all of that to get fleshed out to make a healthy ecosystem for geothermal, and that takes building at scale. And I do not know if the industry has the scale capability for enhanced geothermal.”

DOE Orders Two Indiana Coal Plants to Stay Open Through Winter

U.S. Secretary of Energy Chris Wright issued more emergency orders under Section 202 (c) of the Federal Power Act to keep a pair of Indiana coal plants, F.B. Culley and R.M. Schahfer, running past their previously scheduled retirement at year’s end.

CenterPoint Energy owns the F.B. Culley generating station in Warrick County, Ind., which is made up of two coal-fired units — the 103.7-MW Unit 2 and the 265.2-MW Unit 3, said the order issued Dec. 23. Unit 2 was poised to retire in December 2025, and the order keeps it open until March 23, 2026.

Northern Indiana Public Service Co. (NIPSCO) owns the Schahfer plant, which is made up of two gas-fired units and two coal-fired units at 423.5 MW apiece, the latter of which were going to retire in December. The order keeps the plant open at least until March 23, 2026.

DOE has issued multiple successive orders to keep the Campbell plant in Michigan and the Eddystone plant in Pennsylvania running since this summer. (See State AGs, Enviros Argue Campbell Plant Orders Exceed DOE’s Authority.)

“The Trump administration remains committed to swiftly deploying all available tools and authorities to safeguard the reliability, affordability and security of the nation’s energy system,” Wright said in a statement. “Keeping these coal plants online has the potential to save lives and is just common sense. Americans deserve reliable power regardless of whether the wind is blowing or the sun is shining during extreme winter conditions.”

Both orders cite declining reserve margins in MISO as the reason for keeping the power plants running past their intended retirement dates. The most recent Organization of MISO States and MISO survey of resource adequacy shows a risk of falling short of planned reserve margins later this decade. (See MISO, OMS Report Stronger Possibility for Spare Capacity in Annual RA Survey.)

The orders also note that MISO is trying to address the situation, especially with its Expedited Resource Adequacy Study (ERAS) proposal, which FERC approved this summer. (See FERC Approves MISO Interconnection Queue Fast Lane.)

“The ERAS process should help expedite the construction of needed new capacity,” DOE said in the order. “However, resources studied under the ERAS will have commercial operation dates that are at least three years away and are provided an additional three-year grace period to commence commercial operations.”

Earthjustice called the latest two 202 (c) orders a “power grab to override the decisions made in the interest of customers by power companies, grid operators and state utility regulators.”

“The plants at issue here were marked for retirement because coal is expensive and unreliable,” Earthjustice senior attorney Sameer Doshi said in a statement. “These aging power plants emit deadly air pollution, contaminate water with toxic metals, harm our climate and increasingly break down when we need them most — and the Trump administration is now asking ratepayers to pay more to keep burning coal. What’s more, the Federal Power Act should be applied based on its plain text. An event carefully planned for years is not an ‘emergency.’”

Citizens Action Coalition of Indiana Program Director Ben Inskeep said keeping the two coal plants running would add to affordability worries for the state’s ratepayers.

“The federal government’s order to force extremely expensive and unreliable coal units to stay open will result in higher bills for Hoosiers who are already reeling from record-high rate increases in 2025,” Inskeep said in a statement. “We can’t afford this costly and unfounded federal overreach.”

Natural Gas Generation in Demand, and Priced Accordingly

With support from the Trump administration and demand from data centers, 2025 and now 2026 are high times for the U.S. natural gas sector.

But the picture is not uniformly rosy: Large gas turbines are hard to come by and increasingly expensive, gas transmission pipelines are constrained in some regions, and rising LNG exports further weld the U.S. market to global price volatility.

Natural gas accounted for 43.4% of U.S. utility-scale generation in 2024, more than nuclear (18%) and renewables (17%) combined, according to the U.S. Energy Information Administration. Net generation from natural gas was 3.5% higher in 2024 than 2023, while renewables jumped 12.8% and nuclear held steady.

Renewable energy, particularly solar, is likely to carry this momentum well into President Donald Trump’s second term, despite his efforts to boost fossil fuels, but a large pipeline of natural gas projects awaits.

GE Vernova, which claims the title of world’s largest gas turbine manufacturer and supplier, said in early December it would end 2025 with a backlog of 80 GW of orders and manufacturing slot reservations — and need until the end of 2028 to fulfill it. The company has been raising its prices as well — CEO Scott Strazik said in October that a new combined-cycle gas plant now runs in the range of $2,500/kW of capacity.

Two large competitors, Siemens Energy and Mitsubishi Heavy Industries, report similarly strong order books.

“We continue to see high demand for gas turbines particularly in the U.S., where new electricity demand from the data center buildout and other factors are driving capital expenditures at our utility customers,” Mitsubishi CFO Hiroshi Nishio said in November.

Siemens Energy said in November it closed its 2025 fiscal year with a $162 billion backlog and with a 43% increase in transactions for its gas services division, which sold 194 gas turbines.

Natural gas-fired generation has had its ups and downs. It replaced coal as the dominant U.S. power generation fuel when advances in hydrofracking techniques made the nation the world’s leading natural gas producer.

Federal priorities quickly swung toward renewables under President Joe Biden, then swing back even more suddenly under President Donald Trump.

Natural gas-fired generation capacity will grow, Brattle Group principal Samuel Newell told RTO Insider. But that does not necessarily lock the U.S. into decades of use.

Samuel Newell | Brattle Group

“I think the next several years, the demand growth is such that the combination of using the existing gas-fired fleet more and new capacity, we’re going to be burning a lot more gas in the next several years,” he said. “But in the long run, if we go in a direction that does take climate change seriously, you’d have to increase non-emitting generation a lot, some combination of renewables and nuclear. [But] the gas-fired is still helpful to have there for reliability reasons.”

The larger problem is that load forecasts are increasing at a rate that outstrips the supply chain’s ability to produce new gas-fired generation, said Newell, who leads more than 50 electricity-focused consultants at Brattle.

“I think we’re in a position where it would really help to have everything,” he said, which is why he expects wind, solar and storage development to continue despite the policy shifts against wind and solar.

The political shifts are not the only influence on energy-sector strategies, but they can be hard to overlook.

Strazik said in December 2024 that GE Vernova had secured 9 GW of turbine manufacturing reservations just in the month after Election Day.

NextEra Energy in February 2023 boasted it was the word’s largest generator of renewable energy from the wind and sun. In January 2025, it emphasized that it had the nation’s largest natural gas fleet and recently had struck a framework agreement with GE Vernova to pair new gas generation with renewables and storage.

NextEra’s December 2025 investor presentation contains more than 200 references to “gas” and boasts of being the quintessential all-forms-of-energy company: Gas-fired generation, nuclear, electric transmission, gas pipelines, storage and renewables, in that order. The December 2023 investor presentation contains only 26 references to “gas,” and 16 of those were buried in the fine-print disclaimers at the end.

National Grid’s Northport Power Plant is shown in October 2024. It is one of the aging gas-fired power plants that help keep the lights on in New York. | © RTO Insider 

So what becomes of all this gas generation demand if the major manufacturers cannot quickly meet it?

In some cases, smaller-scale generation is a solution.

Caterpillar, Cummins, Generac, Rolls Royce, Wartsila and others all are reporting booming demand for their products as standby or prime power for data centers.

GE Vernova does not operate in this space — its offerings start at around 35 MW.

The company says its 35-MW LM2500 aeroderivative gas turbine will consume about 60% more fuel and emit 60% more carbon dioxide per megawatt hour generated than its 7HA.03 heavy duty combined-cycle gas turbine configured in a 2×1 block, while its 90-MW 7E simple-cycle gas turbine’s consumption and emissions are roughly 90% higher.

But a new 7HA.03 is taking about 24 months to reach commercial operation, compared with about six months for the 7E and about six weeks for the LM2500.

Strazik said in December 2025 that GE Vernova is not losing deals to competitors pitching small generation.

However, he said, there are projects that initially will rely on someone else’s reciprocating engine or other small generation as a bridge solution to eventual installation of his company’s heavy-duty turbines.

“But I don’t really cry in my beer over that because it’s enabling the heavy-duty to get done later,” Strazik said.

Markets+ Stakeholders Approve Baseline Protocols

SPP Markets+ stakeholders have unanimously approved the first version of the day-ahead market’s protocols, providing a framework for market design, operations and settlements as its future participants build its systems and processes.

The grid operator said the protocols will provide additional guidance on how market rules are applied by translating policy requirements into operational procedures as stakeholders construct and implement Markets+ in its second phase.

“A big milestone for this group to be able to get that approved,” Arizona Public Service’s Kent Walter said during a Dec. 18 virtual meeting of the Markets+ Participant Executive Committee (MPEC). The committee’s vice chair, Walter led the meeting in Chair Laura Trolese’s absence.

MPEC and its working groups and task forces are well into the $150 million implementation effort to add a bundle of services that will centralize day-ahead and real-time unit commitment and dispatch. Markets+ offers Western entities an alternative to CAISO’s Extended Day-Ahead Market as the two grid operators develop regional markets where none existed before.

“What we’re contemplating here is a huge improvement over the status quo, but I’m hopeful that someday, we’ll get to the more optimal use of the transmission system,” Western Power Trading Forum Executive Director Scott Miller said. “I appreciate what SPP is doing. We believe that this is going to go relatively smoothly. … But for a lot of people, this is one of those areas where it’s like, ‘We’re going to watch to see how this operates.’”

Two working groups brought the draft protocols forward. The Markets+ Resource Advocacy Task Force incorporated four outstanding parking lot items into the protocols, including adjustments to the appropriate must-offer calculation for storage resources that are self-committed to charge.

The task force will spend 2026 working on two more parking lot items and addressing any new developments that emerge from the Western Power Pool’s Western Resource Adequacy Program. (See WRAP Wins Commitments from 16 Entities.)

The Markets+ Design Working Group (MDWG) added market transfer, balancing authority area constraints and violation relaxation limits to the protocols. They would optimize market flows between BAs, using an e-tag framework for source and sink that defines the system limits in optimizing each interval.

The work represents an “early alignment” between the MDWG and SPP staff ahead of the broader design buildout, said Xcel Energy’s Nick Detmer.

Jim Gonzalez, SPP’s senior director of seams and Western services, said the interface portion of the protocols gets into “some of the deep nuts and bolts of the technical implementation” of the approved tariff.

“Version 1 of the protocols generally covers all the business practices of the approved tariff language from [January 2025] … where we really need that starting point to fully appreciate as we move in through this implementation effort,” he said. “A lot of the structure is correct. It’s in place. It’s really not going to change what we’re talking about as all the extra work is really fine-tuning.”

The protocols now go to the Interim Markets+ Independent Panel, composed of three SPP board members, for its consideration Jan. 6.

PacifiCorp Contests Amazon Data Center Service Complaint

PacifiCorp filed a partial motion to dismiss a complaint Amazon Data Services submitted to Oregon regulators alleging the utility had breached agreements to provide electric service to four data centers in its service territory.

Portland-based PacifiCorp filed the motion with the Oregon Public Utility Commission on Dec. 19, along with a nearly 40-page answer to the complaint contending the utility has “at all times … negotiated in good faith with ADS and diligently worked to discharge its obligations under the parties’ agreements.”

Amazon’s complaint (UM 2410), filed Oct. 30, said the company has been working since 2021 to develop four data center campuses in PacifiCorp’s territory in Eastern Oregon. (See Amazon Files Complaint Against PacifiCorp for Lack of Data Center Power.)

Amazon contended that, for the first campus, called Specialized, PacifiCorp has been “supplying significantly less power than promised,” while the second campus, Litespeed, has received no power.

For two other campuses, called Pivot and Gray, PacifiCorp has “refused to even complete its own standard contracting process,” Amazon alleged.

The company said it had exhausted “all reasonable efforts” to work with PacifiCorp to comply with the agreements and asked the PUC to either require the utility to provide the contracted volumes of power or shift the data centers into the territory of another utility willing to supply electricity — effectively shifting utility boundaries.

PacifiCorp’s partial motion for dismissal focuses on that latter request, arguing that, contrary to Amazon’s argument, there is no basis under Oregon law for the PUC to reallocate a service territory or electric customers “without the agreement of the affected utilities.”

“There is no legal basis for the commission to remove portions of PacifiCorp’s exclusive service territory so that the territory can be served by a different utility. Such a process is prohibited by the Territory Allocation Laws, which set forth the exclusive process for allocating and reallocating service territory and do not recognize the process ADS requests,” the utility argued.

‘Intervening Events’

PacifiCorp’s broader answer drills down into the specifics of Amazon’s complaint.

The utility said that under the terms of the master electric service and facilities improvements agreement (MESA) it entered with Amazon to serve Specialized, it paid nearly $100 million for transmission system upgrades and obtained transmission service from the Bonneville Power Administration, Umatilla Electric Cooperative and PacifiCorp Transmission.

PacifiCorp said it began serving the Specialized campus on a date that was redacted from the public version of the document and since that time has “provided all power required by ADS’ current operations” at the facility.

“Contrary to ADS’ allegations in the complaint, ADS has consistently requested PacifiCorp to deliver far less power than the amounts it is entitled to under the Specialized MESA. But if ADS were to increase its load to the full amount to which ADS is contractually entitled, PacifiCorp would be prepared to serve the full amount,” the utility wrote.

Regarding Litespeed, PacifiCorp wrote that, after “extended negotiations” with the property owner, it has acquired necessary easements for the “significant upgrades” required to power the facility and has begun their construction.

The utility said it has been supplying “bridging power” to the Litespeed site since a date also redacted from the document. It noted that Litespeed’s projected in-service date — also redacted — is later than the target completion date set out in the facility’s MESA, signed in 2023, but attributed the delay to “factors outside PacifiCorp’s control.”

“ADS has contributed to the delay by failing to timely complete required steps in the project construction and energization schedule, and the current projected in-service date is driven by the construction schedule for necessary upgrades that Portland General Electric is completing at one of its substations,” PacifiCorp added.

PacifiCorp said that meeting the full contracted future demand at Specialized and providing desired redundancy would require additional system upgrades, including building a new substation and 230-kV line — the cost estimates for which were redacted. The utility said it likely would incur similar costs to serve Pivot.

PacifiCorp argued that Amazon had failed to pay all “actual costs” required to serve Specialized and Litespeed, pointing to the company’s refusal to pay “gross-up” charges that reflect the amount of income tax the utility incurred from ADS’ financial contributions to construction.

“Cost responsibility for these upgrades is not discussed in the Specialized MESA because the upgrades were necessitated by intervening events and therefore were identified after the MESA was executed. However, ADS has been aware of the need for these upgrades since 2023, and PacifiCorp understood that ADS was willing to pay for these upgrades,” the utility said.

Among those intervening events was this year’s passage of Oregon House Bill 3546, which requires that utility contracts with data centers avoid shifting network upgrade costs to other retail electricity customers.

PacifiCorp said it and ADS recognized this past summer that negotiations over a contract to cover all four sites “had become protracted” but that ADS rejected the utility’s “last, best and final” offer that would be consistent with rules under HB 3546.

“While PacifiCorp remains ready and willing to serve all four data center campuses, it cannot agree to terms for electric service to ADS that contravene Oregon law or policy or otherwise shift costs or risks to PacifiCorp’s other customers,” the utility said.

Reached for comment on PacifiCorp’s answer, Amazon spokesperson Lisa Levandowski said the company has paid more than $100 million for PacifiCorp over the past four years “to build and upgrade its electrical infrastructure” to “ensure it can deliver the power we’ve agreed on for our data centers … without passing additional infrastructure costs to its other customers.”

“Despite these investments and our compliance with all commission-approved policies, PacifiCorp has delivered only a fraction of its contractual obligations, forcing us to file with the Oregon Public Utility Commission,” Levandowski said in an email.

MISO, Minn. Say Federal Funds for JTIQ in Play

Federal funding for MISO and SPP’s Joint Targeted Interconnection Queue (JTIQ) portfolio is still intact nearly three months after the U.S. Department of Energy said it was revoking its grant for the transmission projects.

“The federal grant for the JTIQ portfolio has not changed since the award was issued, and projects are proceeding as planned,” the Minnesota Department of Commerce said in a statement to RTO Insider.

The $464.5 million in federal funding for the $1.7 billion portfolio was among the 321 grants DOE said it was canceling in early October. (See DOE Terminates $7.56B in Energy Grants for Projects in Blue States.) The state Commerce Department led the application for federal funding with assistance from the Great Plains Institute.

When asked about the JTIQ funding status, MISO issued an identical statement to the Minnesota agency. Neither organization offered any details on the possible reconsideration of the projects by DOE, nor whether they were notified that the funding no longer was in jeopardy.

MISO said it is “not in a position to speak on the DOE’s processes.” CEO John Bear mentioned that JTIQ’s federal funding was restored at the RTO’s Board of Directors meeting Dec. 11.

DOE did not respond to RTO Insider’s request for comment on the JTIQ portfolio’s funding status.

MISO and Minnesota’s implication that the funds are not in doubt doesn’t quite square with congressional record.

Earlier in 2025, the chopping block appeared to be the most likely outcome for the $464.5 million from the department’s Grid Resilience and Innovation Partnerships (GRIP) program awarded to the JTIQ portfolio in 2023. While the department did not specifically name the portfolio in its announcement, it was on a list of projects slated for cancellation that was posted by Democrats on the House Appropriations Committee.

MISO, Minnesota and the Great Plains Institute have said they have never been formally notified that GRIP funding for the JTIQ projects is rescinded. However, regulators publicly appeared nervous about the status of the funding.

“I wish all the people who spent many thousands of hours on those projects strength in these trying times,” Wisconsin Public Service Commissioner Marcus Hawkins said at the Organization of MISO States’ annual meeting in October.

Brattle Group Praises JTIQ, Calls for More Interregional Transmission

Brattle Group Principal Johannes Pfeifenberger issued an appeal for more interregional transmission planning during the Midwestern Governors Association’s webinar on transmission benefits Dec. 15.

He praised the JTIQ portfolio in particular. By spending a couple of billion dollars, MISO and SPP “can create interconnection headroom more cheaply than in individual interconnection queues.”

“Doing something more proactive on both sides of the seams can really save some money,” he said.

Pfeifenberger said upgrade costs for generation developers under the JTIQ should be about half as expensive as the upgrades identified in MISO and SPP’s separate interconnection queues.

He also expressed hope that the 765-kV projects under MISO’s $22 billion long-range transmission portfolio eventually could be “interconnected into a macro grid.”

Overall, much remains to be done on the interregional front, Pfeifenberger said. He said RTOs’ interregional planning processes come last and that grid operators often will focus on local needs at the expense of more beneficial interregional links.

Pfeifenberger said spending on transmission has increased tenfold over the past 30 years, from $3 billion per year in the mid-1990s to $30 billion annually today. However, he said most of the investment is spent to refurbish local infrastructure.

“MISO is the exception,” Pfeifenberger said. But overall, he criticized transmission planning as “too siloed and reliability-focused.”

Pfeifenberger said the simulations RTOs use to plan transmission tend to underestimate the savings projects can deliver.

He said simulations use normal weather conditions that don’t test heat waves or cold snaps. He also said they don’t account for fuel price spikes or unusual generation or transmission outages.

Pfeifenberger said on Dec. 15, Henry Hub in the MISO footprint was trading at $5/MMBtu, up from the average $3/MMBtu, while gas in Boston was valued at $25/MMBtu. But if RTOs always experienced normal weather, outages and fuel prices, “we wouldn’t need half the grid we have.”

“Sometimes you have to spend money to save money,” he said.

MISO and SPP are considering a FERC filing to amend their joint operating agreement to be able to consider more types of benefits to justify future interregional transmission projects.

Governors’ Workshop Focuses on Energy Demand, Collaboration

PHOENIX, Ariz. — Arizona Gov. Katie Hobbs and panelists discussed efforts to meet rising energy demand at a Western Governors’ Association workshop, with some noting opportunities and challenges navigating state-level permitting and regulation.

Hobbs delivered the keynote at the association’s two-day workshop — Energy Superabundance: Unlocking Prosperity in the West — Dec. 17. The governor said while innovation in chip manufacturing and artificial intelligence is “booming” in the U.S., more energy is needed to support those efforts.

Hobbs touted recent Arizona initiatives, including a $15.6 million investment for grid resiliency projects and an executive order to streamline energy development. She urged Western states to collaborate, saying, “The fact is that America’s energy future runs through Arizona and other Western states.

“We stand on the frontier of energy innovation and generation, and our collective power has the ability to support and promote American advancement for generations.”

In a separate panel on the relationship between energy and economic development, Jake Dubbs, lead adviser for external affairs and tribal relations at SPP, discussed increasing electricity demand and the need for regional cooperation to bring new generation online more quickly.

SPP projects “an increase of almost 35%” in electricity demand by 2030, according to Dubbs.

“The West requires so much attention, and it requires a lot of different groups coming together,” Dubbs said. “And I think that’s one thing that we are really working hard towards at SPP, making sure that all the different groups, unique perspectives, are coming together to talk.”

He said SPP’s RTO expansion and development of the day-ahead market, Markets+, are part of efforts to increase partnerships in the West and take advantage of the region’s resources. (See SPP Markets+ Cruising Through Early Development.)

Navigating state agencies remains a challenge for developers, said Ashley Bunch, manager of government relations and stakeholder engagement at BluEarth Renewables.

Some places, like Arizona, are easier to navigate because agencies are aligned and “understand what our goal is,” Bunch said. “And they really are all kind of working together.

“We sometimes see in other states that a game and fish department may not be as on board as, say, another state land entity, and it makes things … more difficult. … If the state agencies can come together and … put forth the guidelines very clearly … that would be very helpful to us. And I do think Arizona does a very good job of that.”

Long interconnection queues also pose obstacles to new generation, said Chris Pasterz, economic development director in Navajo County.

Developers and large energy users look for favorable governments “that have pathways for development,” Pasterz said. Expanding the use of private land is one part of the solution, he noted.

“That’s one thing that we’ve done in Navajo County to promote the private landowners’ utilization of their lands, their resources,” Pasterz said.

The agreements between private landowners and developers must ensure that local communities reap the benefits from new projects, he added.

Policymakers “can really help with that speed of development by finding your areas where there is a pathway for private land development,” Pasterz argued. “But also supporting those private elected officials who are negotiating those deals locally to make sure that those benefits are retained into the future for their community.”

State Briefs

CALIFORNIA

CEC Denies Shasta County Wind Farm

The Energy Commission denied the approval of the Fountain Wind project, ending a yearslong battle by Shasta County to stop the project from moving forward. In October 2021, the Shasta County Board of Supervisors voted down the project, denying ConnectGen’s appeal of the planning commission’s decision not to approve the wind farm. But the California Legislature in 2022 approved AB 205, which allowed the commission to consider approving the project even though Shasta County rejected it.

More: Redding Record Searchlight

PUC Votes to Keep Utility Profits High

The Public Utilities Commission voted 4-1 to keep utility profit margins near 10% despite calls to cut them to 6%. The four commissioners who voted to keep the return on equity at about 10% said they believed they had found a balance between the 11% or higher rate that Southern California Edison, Pacific Gas and Electric, San Diego Gas & Electric and SoCalGas had requested and the affordability concerns of customers. The vote will slightly decrease the profit margins beginning next year. Edison’s rate will fall to 10.03% from 10.3%. California has the nation’s second-highest electric rates after Hawaii.

More: Los Angeles Times

MASSACHUSETTS

DPU Opens Probe into Volatile Energy Bills

Nine weeks after Gov. Maura Healey requested a review, the Department of Public Utilities opened an investigation of all delivery charges on electric and gas bills. The DPU said its probe “will examine the causes of bill volatility and promote a greater understanding of rates for customers to take greater control over their energy bills.” It also will explore whether to establish limits on how much charges can increase from month to month and whether certain charges should be eliminated, consolidated or “redesigned as a fixed charge.”

More: WBTS

MICHIGAN

Lawmakers Introduce Bill to Repeal Data Center Tax Incentives

A bipartisan bill introduced in the Legislature would repeal the state’s data center tax incentive laws. The existing data center laws provide sales and use tax exemptions for tech companies. The tax revenue otherwise would go to the state’s school aid or general fund. Under an earlier version of the incentive, eligible data centers built between 2020 and 2024 avoided paying about $13 million in taxes. The proposed repeal comes as public outrage over data centers is reaching new heights. The data centers are also poised to derail the state’s clean energy transition.

More: Inside Climate News

NEBRASKA

OPPD Again Delays Plan to Stop Burning Coal at North Omaha Plant

The Omaha Public Power District Board of Directors voted to delay decommissioning the North Omaha Station’s coal-fired units. OPPD for more than a decade had planned to end coal use at its North Omaha power plant. After multiple setbacks, the utility aimed to transition the two coal-fired units to natural gas by the end of 2026, but new requirements from SPP and an increase in energy needs delayed the decision. The board delayed a previous plan that would have phased out coal in 2023. A 2022 vote pushed the conversion until at least 2026, in large part because of a regional backlog in replacement power. OPPD said if the timeline progresses as expected, the conversion could take place in 2028.

More: Nebraska Public Media

OHIO

Settlement Offer Would Give $275M to FirstEnergy Customers to End HB 6 Probes

Utility companies affiliated with FirstEnergy have agreed to provide $275 million in restitution to customers under a proposed settlement that would resolve years of investigations tied to the passage of House Bill 6 and related regulatory violations.

The proposed stipulation, filed with the Public Utilities Commission, covers Ohio Edison Co., The Cleveland Electric Illuminating Co. and The Toledo Edison Co. and would end four major commission investigations along with several related complaints if approved. On Nov. 19, the PUC and companies resolved three of the four investigations and had tentatively settled for $250 million in total for misconduct related to the HB 6 bribery scandal. But the latest stipulation adds another $25 million to the settlement and specifies all the money will go to customers.

More: Cleveland.com

TEXAS

AG Sues Xcel Over Role in Smokehouse Creek Fire

The Office of the Attorney General has sued Xcel Energy for its role in the 2024 Smokehouse Creek Fire, which was the largest wildfire in state history. Attorney General Ken Paxton accused Xcel of making “false representations about its safety commitments” and of ignoring warnings about infrastructure problems. He claimed that those actions “created a substantial wildfire risk.” Texas A&M Forest Service investigators found that power lines started that fire and the Windy Deuce fire. The fires burned nearly 2,000 square miles in Texas and Oklahoma. Xcel has agreed to $361 million in 212 settlements, with 42 claims still pending.

More: KXAN

Federal Briefs

Senate Approves TVA Nominees

The U.S. Senate confirmed four Trump nominees to the Tennessee Valley Board of Directors. Senators voted 53-47 to confirm Mitch Graves, Jeff Hagood, Randall Jones and Arthur Graham. The nominations came after Trump removed Biden appointees to the board after taking office, leaving it without enough members for a quorum to hold votes. Lee Beaman, another Trump appointee, was removed from the nomination process and would have to receive a new nomination to be considered.

More: Tennessee Lookout

DOE Inspector General to Probe Canceled Climate Grants

The Energy Department’s inspector general’s office says it will probe a Trump administration move to cancel nearly $8 billion in climate and energy funding that primarily impacted blue states.

“The Office of Inspector General recently announced an audit which will review the Department of Energy’s processes when cancelling financial assistance and whether those cancellations were in accordance with established criteria,” Nelson wrote in a letter. Taking up the probe does not necessarily mean the cancellation was improper.

Earlier in 2025, the DOE canceled awards to 223 projects worth about $7.6 billion. Some of the largest cancellations affected funding for hydrogen hubs in California and the Pacific Northwest.

More: The Hill

NRC Extends TVA Nuclear Plant

The Nuclear Regulatory Commission has approved another 20-year extension for the Tennessee Valley Authority’s Browns Ferry Nuclear Plant in Alabama. The extension will allow the three reactors to operate until their 80th birthdays in the mid-2050s. Their licenses were set to expire in 2033, 2034 and 2036. The plant can produce nearly 4 GW.

More: Chattanooga Times Free Press

BLM Advances Libra Solar Project

The Bureau of Land Management approved changes to the Libra Solar Project in Nevada, marking the first time the agency has advanced a solar project since July. The $2.3 billion project is among the largest in the U.S., adding 700 MW of solar and 700 MW of battery storage. Groundbreaking is scheduled for early 2026, with commercial operations planned by the end of 2027.

More: pv magazine

Mexico Greenlights 20 Renewable Projects

Private companies will invest $4.75 billion to build 20 renewable energy projects across 11 Mexican states, Energy Minister Luz Elena González said. González said the projects, 15 of which are solar and five wind, will add 3,320 MW of generation capacity and 1,488 MW of storage capacity.

More: Mexico News Daily

Company Briefs

Ford to Discontinue EV Truck, Lay off Battery Plant Workers

Ford has ceased production of the all-electric F-150 Lightning and instead will focus on hybrid vehicles and a future line of smaller, cheaper EVs.

Ford said the shift away from larger EVs is due to “lower-than-expected demand, high costs and regulatory changes.” The company plans to expand hybrid options to nearly every vehicle in its lineup, with larger vehicles gaining plug-in hybrids that power the wheels with electric motors but carry a gas engine to generate energy for the battery.

Ford also will lay off about 1,500 workers in Kentucky as it converts its BlueOval SK battery plant from making EV batteries to making batteries for a new energy storage business. 

More: Car and Driver; NPR; Kentucky Lantern 

Judge Denies US Wind Request to Halt Trump Admin Attacks

U.S. District Judge Stephanie A. Gallagher declined to issue an injunction that would have protected US Wind from what it says are Trump administration attempts to kill its planned wind farm off Ocean City, Md.

Gallagher noted in her decision that US Wind technically could move forward with constructing its wind farm. Even though President Donald Trump’s administration has announced its intention to re-evaluate the crucial Construction and Operations Plan approval issued during former President Joe Biden’s administration, it has not actually revoked the permit, Gallagher wrote.

In a previous decision, Gallagher preliminarily rejected a request from the Trump administration to remand the permit back to the Department of the Interior for reconsideration. Gallagher ruled the government needed to present more information for her to make a ruling but allowed the department to carry on with any “internal review” of the permit.

More: Maryland Matters