NYISO Reveals Bids in NYC Offshore Transmission Solicitation

NYISO this month received four bids in response to its Public Policy Transmission Need solicitation to deliver up to 8 GW of offshore wind power to New York City. 

Each developer proposed multiple options, differing by size, number of offshore platforms and HVDC cables, or interconnection points. They are: 

    • energyRE Giga-Projects USA, with three options for its Clean Borough Power Link; 
    • Viridon New York, with three options for its Liberty Link; 
    • New York Transco, with 10 options for its Energy Link New York; and 
    • the New York Power Authority and LS Power, with 12 options for its Five Boro Energy Connect. 

Most project options propose to connect to Consolidated Edison’s Brooklyn Clean Energy Hub, expected to be completed in 2028. But many others propose to interconnect via DC-to-AC converter stations that have not yet been approved. 

NYISO issued its solicitation in response to an order by the New York Public Service Commission in June 2023. The PSC mandated that projects should accommodate at least 4,770 MW of offshore wind, with options to expand up to 8 GW. (See New York PSC Calls for More Transmission for Long Island OSW.) 

Viridon and energyRE proposed in-service dates of December 2032 for all of their proposals, while NY Transco proposed January 2033. NYPA and LS Power’s proposed dates vary by option, with the earliest being September 2032 and latest December 2033. 

New York’s Climate Leadership and Community Protection Act calls for 9 GW of offshore wind by 2035. The state’s — as well as the U.S.’ — first utility-scale project, the 130-MW South Fork Wind Farm, began operating in March. The 924-MW Sunrise Wind project received federal approval last week. (See Sunrise Wind Cleared to Begin Construction.) 

“The investment in transmission is needed so that we are prepared for the future state,” said Susan Craig, spokesperson for NYPA. “The expectation is that generation sources will be there to connect.” 

NYISO will conduct a viability and sufficiency analysis on all the proposals that is expected be conclude in the fourth quarter. The Board of Directors will select a proposal in the second quarter of 2025.  

Craig compared the Five Boro project to Propel New York Energy, which included the construction of new underground transmission lines and substations. Developed by NYPA and NY Transco, Propel was selected by NYISO’s solicitation in June 2023 to meet the PSC’s order for projects to connect up to 3 GW to Long Island. (See NYISO Selects Propel Project for Long Island Transmission.) 

“New transmission is essential for the reliable deployment of offshore wind, and energyRe is ready to modernize New York’s electric grid in support of the state’s clean energy goals,” company COO Ryan Brown said in a statement. 

“As New York develops more renewables, we will need the necessary transmission to carry that clean energy to homes. Energy Link NY is the best project for the job,” said Will Hazelip, vice chair of NY Transco’s board and president of National Grid Ventures. 

“LS Power’s joint proposals with NYPA will deliver state-of-the-art transmission solutions that provide New York City with more renewable generation to integrate into the electric grid and increased reliability to meet power demand, while also minimizing environmental impacts,” LS Power CEO Paul Segal said. 

Calif. Agencies Outline ‘High Road’ to Developing EV Workforce

California officials on June 25 outlined how their agencies plan to address the shortage of skilled workers needed to support the state’s transition to zero-emission vehicles (ZEVs). 

The state’s Workforce Development Board (CWDB), Employment Training Panel (ETP) and Air Resources Board (CARB) were among the several agencies that presented their approaches to workforce development during a Clean Transportation Program workshop hosted by the California Energy Commission. The program receives up to $100 million annually to fund ZEV infrastructure and development. (See Calif. Clean Transportation Program Needs Equity Emphasis.) 

Also participating was the Governor’s Office of Business and Economic Development (GO-Biz), which leads the state’s ZEV Market Development Strategy, designed to be a “north star” for meeting the state’s goals, according to Gia Vacin, deputy director of ZEV Market Development at GO-Biz. The strategy outlines four pillars supporting the development of a successful ZEV market: vehicles, infrastructure, users and workforce. 

Agency officials emphasized the need to develop “high-road” — or living-wage and skills-based — careers and opportunities for disadvantaged communities in the ZEV industry.  

“We can’t succeed in these other pillars without the support of a robust and thriving workforce that can help lift these others up,” Vacin said. “As we assess our current and future workforce needs, we are really thinking about this ecosystem and standing up and maintaining the entire market.”  

In 2020, the CEC and CWDB partnered in a joint memorandum of understanding to coordinate economic and workforce development planning related to the state’s clean transportation goals, with an emphasis on increasing job opportunities for disadvantaged populations. 

“The Workforce Board has spent the last several years really advocating to do better in the state of California and the Energy Commission has become a really good partner, especially given the [number] of investments that are being made through the department,” said Derek Kirk, assistant deputy secretary of climate at the state’s Labor and Workforce Development Agency. “The reality is, not a whole lot of that money is flowing directly through the workforce agencies or any of our workforce development partners, and so it’s incumbent on us to build relationships across the board to leverage our expertise and to start identifying those programs that can be leveraged to support the creation of this new workforce.”  

As part of the partnership, the CWDB assigned liaisons to the CEC to provide the latter with workforce expertise in labor development strategies and policy and technical assistance and to help identify resources and opportunities. Kirk highlighted the CWDB’s High Road Training Partnership Resilient Workforce Program, designed to increase access to high road jobs for underserved populations, which developed opportunities such as the Jewish Vocational Services 18-week Automative Pre-Apprenticeship Program in partnership with the City College of San Francisco.  

Robert Meyer, director of economic development at the ETP, which uses a pay-for-performance contract to reimburse costs for customized job skills training, said his agency will fund nearly $95 million in training for fiscal 2024/25. The CEC and ETP are currently formalizing an interagency agreement to increase the number of Electric Vehicle Infrastructure Training Program (EVITP) certified electricians needed to support widespread transportation electrification. Both agencies established a goal of allocating the ETP $3 million in CTP funds to offset training and EVITP certification costs.  

CEC staff also highlighted the Inclusive, Diverse, Equitable Accessible and Local (IDEAL) ZEV workforce pilots, one of which awarded $6.5 million to 14 projects for high school and college students, veterans and disadvantaged communities, as well as the ZEV Sustainable Equitable Employment Destination (ZEV SEED) project, which targets training workers in disadvantaged communities in Sacramento County. 

Equity Considerations

While investing in workforce training programs is important, the state should do more to consider equity gaps and the barriers some communities face in accessing these programs, said Eileen Tutt, executive director of the Electric Transportation Community Development Corp.  

“We offer all these opportunities equally to various communities, and we are not recognizing the different needs in especially low-income, disadvantaged communities,” Tutt said. 

Tutt identified the “gaps” some residents face in participating in training programs, such as a lack of a driver’s license, and reliable transportation, and encouraged state officials to use a portion of the funding to pay participants for taking time off from jobs or obtaining mobility.    

“There’s just costs associated with this training that are not manageable for some communities,” she said.  

Representatives from the International Brotherhood of Electrical Workers (IBEW) were frustrated the union wasn’t included in the workshop and said investing in ZEV infrastructure trainings and apprenticeships is a “waste” because the union already provides enough to support the industry.  

“I am astounded that IBEW wasn’t included as an industry partner or expert or highlighted in today’s workshop,” said Gretchen Newsom, the union’s international representative for government affairs. “We’ve been training our members on EVITP many, many years ahead of the EV revolution. Why not layer this EV operations and maintenance training and knowledge onto the existing high road career as electrician?”  

Echoing Newsom’s comments was Alex Lantsberg, research and advocacy director at San Francisco Electrical Construction Industry, the Labor-Management Cooperation Committee of IBEW Local 6 and the San Francisco Electrical Contractors Association.  

“Rather than just simply a lack of IBEW … what it appears to me is that the state is trying to approach this training question in a very decentralized, uncoordinated way, throwing a bunch of money at a bunch of different programs and hoping they work,” Lantsberg said.  

“IBEW contractors have extensive institutional memory and institutional capacity to train thousands of workers,” he said. “We’ve demonstrated in a variety of different contexts that there are plenty of EVITP certified electricians to be performing this work. What’s absolutely needed and what hasn’t been discussed is an affirmative pathway developed by the state to put those apprentices and to put those skilled and trained contractors on these jobs.”

LNG Won’t Replace Coal in Generating China’s Power, Report Says

While natural gas has taken a huge bite out of coal’s share of the electric generation market in the U.S., LNG will not have the same impact globally, according to a new report from the Institute for Energy Economics and Financial Analysis (IEEFA). 

That is because China, the world’s largest coal consumer, will not be replacing that domestic resource with imported natural gas, IEEFA said in its report, “LNG is not displacing coal in China’s power mix.” 

“Policymakers in both LNG exporting and importing countries should approach claims about the necessity of LNG as a ‘bridge fuel’ with a high degree of skepticism,” report co-author Sam Reynolds said in a statement. “The case of China clearly shows that LNG has played a minimal role in displacing coal in the country’s largest coal-consuming sectors.” 

China is the world’s largest energy consumer, with coal accounting for 55% of its primary energy demand, while natural gas, hydropower and renewables each provided 8% of primary energy consumption in 2022.  

Over the past decade, natural gas’ share of generation has stayed around 3%, while renewables have grown to 16% and contributed more to coal’s falling share of generation from 70 to 61%. 

“Although China is the world’s largest LNG importer, the country’s coal demand has increased more than LNG imports every year since 2017,” the report said. “Claims about the role of LNG in displacing coal usage appear to be based on hypothetical arguments that coal generation would be even higher without gas-fired power.” 

While coal’s share of total generation has fallen over the last decade, its generation output has grown by 1,700 TWh, which suggests coal is not being displaced in absolute terms, while wind and solar have contributed to its decline in share of overall generation. 

Recently, China even passed policies to “strictly control” coal-to-gas switching and promote domestic production of coal and natural gas. 

“As a result, coal capacity additions have far outpaced additions of gas-fired power plants, and both are dwarfed by wind and solar installations,” the report said. “National energy sector development plans have called for coal plants to provide flexible operations to integrate variable renewables sources.” 

LNG also costs three times as much as coal in China, so even if prices for imported gas drop as new supply comes online in the near future, those declines will likely not be enough to close the gap. China has replaced coal heating with gas heaters in urban areas, but the paper suggested that would be hard to replicate in the countryside. 

China is the fourth-largest producer of natural gas, which has been growing in recent years, but it is the largest coal producer, last year hitting record production of 4.7 billion tons, 14% above 2021 levels. 

China is also the largest importer of coal, with imports accounting for about 10% of supply needs.  

“The country’s coal, natural gas and LNG demand have all increased since 2016,” the report said. “China consumes nearly seven times more coal than natural gas, though consumption of both fuels increased by roughly the same amount (8 exajoules) between 2012 and 2022.” 

Electricity generation has grown 6.3% a year since 2013, with coal, natural gas, wind, solar and nuclear increasing every year over that time frame.  

“Looking ahead, generation from coal and renewables will continue to exceed gas-fired generation, and capacity investments suggest that LNG and gas will continue to play a limited role in coal displacement,” the paper said. “In recent years, gas plant capacity additions have paled in comparison to coal and renewables additions.” 

China had 1,051 GW of installed wind and solar at the end of 2023 and could hit 1,300 GW this year, beating its target of installing 1,200 GW of wind and solar by 2030. That trend has the International Energy Agency predicting the country could get 50% of its generation from renewables by 2028, while IEA’s projections for gas power are flat through 2030. 

DOE Dives into US Offshore Wind’s Growing Pains

U.S. Department of Energy officials say they’re optimistic the costs of offshore wind energy development will begin to ease by the end of the decade. 

They struck an optimistic tone during a June 25 webinar, acknowledging the growing pains the industry has had as it establishes itself in the United States but saying the problems of the past 20 months can be overcome. 

Jigar Shah, director of the DOE Loan Programs Office, said while the complicating factors were not unique to U.S. offshore wind development, U.S. offshore wind was particularly vulnerable to them. 

“With all that said, global cost headwinds have begun to stabilize and new offtake solicitations from states are de-risking development moving forward,” Shah said. “Government and industry are drawing on lessons learned with ongoing efforts to refine project and supplier procurement, foster regional collaboration for supply chain and transmission planning and make investments to support necessary enabling infrastructure.” 

Jocelyn Brown-Saracino, DOE’s offshore wind lead, said wind energy area leases held by developers total more than 50 GW of potential generation capacity. Offshore wind is a headline priority for the Biden administration, which plans to auction more leases this year. 

“That said, the last year was a tumultuous one for offshore wind. The industry was hit by a perfect storm of global macroeconomic challenges,” she said. “The sector is adapting, however, and improved risk mitigation is being built into industry planning.” 

The webinar was centered on the DOE’s “Pathways to Commercial Liftoff” report for offshore wind, released in April during the 2024 International Partnering Forum. (See Interior Announces Updated OSW Regs, Auction Schedule at IPF24.) 

Lead authors Brett Anders and Jonah Uri summarized three key takeaways from that report: 

    • Offshore wind will play a critical role in coastal decarbonization and would be hard to replace with other sources of emissions-free power. 
    • Roughly 6 GW of projects are under construction but there needs to be 10 GW to 15 GW this decade to ensure development of a domestic supply chain and reduce some of the long-term risks of building supporting infrastructure. 
    • State policy drives the offshore wind market more than it drives other technologies; federal policy mechanisms such as the Inflation Reduction Act offer support but have not been enough on their own to overcome the challenges created by macroeconomic conditions. 

Globally, offshore wind is a mature technology that has grown tenfold in the past decade and is projected to grow fivefold in the next decade, they said. 

The United States is late to the table, however, home to less than 0.5% of the world’s operational capacity and struggling to add more. 

More than half of the projects contracted off the Northeast coast have been canceled or have canceled their offtake contracts in the past year, victims of soaring costs and supply chain or infrastructure constraints that made it impractical to proceed to construction under the financial terms negotiated. 

The projects being contracted now are much more expensive. The levelized cost of electricity (LCOE) has risen from $85/MWh for fixed-bottom offshore wind projects that reached final investment decision (FID) in 2021 to a projected $140/MWh for projects reaching FID in 2023-2026.  

That is mainly due to the rising cost of capital, cost of construction and cost of operation. Offshore wind is highly sensitive to the cost of capital, said Anders, a member of the market analysis team at the DOE’s Office of Technology Transitions. A 2% increase in the cost of debt alone would lead to a roughly 20% increase in LCOE. 

The report estimates that FIDs reached in 2030 will be back down to $84/MWh through a combination of decreasing interest rates, commodity prices and inflation, and because of tax credits and policy support. 

“Given the inherent uncertainties in the market, particularly with respect to macroeconomic challenges, these estimates should not be interpreted as a cost forecast but rather a framework for understanding the cost of offshore wind today and into the future,” said Uri, a transaction specialist at the Loan Programs Office. 

The economics seen in the era after the Great Recession and before COVID or the war in Ukraine offer some basis for optimism, the report notes: As worldwide installed offshore wind capacity surged from 3 GW in 2011 to 33 GW in 2021, the LCOE of new wind farms gradually decreased 60% through factors including supply chain efficiencies, de-risked construction, technology innovations, institutional knowledge and turbine upsizing. 

Some of the complicating factors in the United States today, such as lack of domestic manufacturing capacity, ports and specialized installation vessels, are particularly sticky, Uri said: They must be put in place at a cost of hundreds of millions of dollars each before the projects that will pay for them can be built. 

“So, the early movers are a primary engine to fund the long-term ecosystem buildout for offshore wind here in the U.S., whether that’s ports, vessels, supply chain, etc.,” he said. “It’s a key area of risk that we focus on and part of the reason why building out the initial wave of projects and getting over this hump, of this chicken and egg, is a key force to help lock in the future of the industry.” 

The tone of the webinar and the report on which it is based is optimism in the face of setbacks. 

A central feature of the DOE “Liftoff” series of reports on new energy technologies is the projection of the liftoff — the point at which an industry sector begins actively contributing to decarbonization goals and has a sustained pipeline of projects regularly reaching completion.  

“We found that offshore wind liftoff can be achieved in less than 10 years driven by deployment of projects in the 2020s, several of which are under construction today,” Anders said. “Liftoff for offshore wind will require steady deployment enabled by continued refinements to project sequencing and funding.” 

NJ Senate Energy Committee Backs PJM Interconnection ‘Skip’ for Solar

New Jersey’s Senate Environment and Energy Committee on June 20 passed a bill (S3308) supporters said would allow grid-scale solar projects of up to 20 MW to bypass PJM’s interconnection queue and connect to the grid through their local utility. 

The committee voted 5-0 to advance the bill, which would require electric utilities to “accept, process and approve” solar projects of 2 MW to 20 MW to the transmission and distribution system, unless the application is incomplete or the utility believes the interconnection would be “unsafe or a risk to the stability of the utility’s electric distribution or transmission system.” In those cases, the utility would have to provide the developer with recommendations on how to modify the proposal to make it complete or “reconfigure, downsize or otherwise modify” it to remove the risk. 

The bill would require the utility to “timely process any complete interconnection applications received.” The owner or developer of an approved project would be required to pay all the interconnection costs that are “identified by the electric public utility” and would be compensated for the electricity supplied by the utility, according to the bill. 

Committee Chair Bob Smith (D) said the bill, “in a nutshell, in some ways allows interconnectors to skip the PJM process.” He added, however, that he is “not 100% sure of that.” 

Fred DeSanti, executive director of the New Jersey Solar Energy Coalition, said the bill would provide an alternative to the extensive delays experienced by projects in seeking interconnection through PJM’s process. 

“We’ve got projects that are viable, that are just sitting there waiting,” he said. “And so all this bill does is, it says, ‘Hey, if the public utility has jurisdiction over the line, and if we meet all the requirements of the public utility … why shouldn’t they be able to approve it?’ We don’t necessarily need PJM at that point.” 

Joseph Gurrentz, director of external affairs for the New Jersey Utilities Association (NJUA), said one question still to be resolved is whether the bill defines the “electric transmission and distribution system to apply only to the electrical systems within New Jersey,” and therefore under the jurisdiction of the Board of Public Utilities. If not, he said, the projects could “inadvertently butt up against the jurisdiction over regional transmission infrastructure” of FERC. 

Asked for comment about the bill, PJM spokesman Daniel Lockwood said the RTO “has requirements to interconnect into the transmission system that have been approved by [FERC].” 

“Whether a prospective resource is required to follow that process depends on the size of the resource and where it wants to interconnect,” he said. “All of our states have their own interconnection processes, as some resources interconnect into the grid that is overseen at the state level.” 

Like all grid operators across the U.S., PJM has an interconnection queue clogged with proposed renewable resource projects. FERC approved a PJM proposal to overhaul its interconnection queue process in late 2022; the commission then issued Order 2023 last July, which required grid operators to revise their processes to include a “first-ready, first-served” cluster methodology, among other changes.  

PJM in May told FERC the RTO’s new commission-approved process already complies with Order 2023, as it “parallels many reforms PJM has already implemented” (ER24-2045). It argued it was eligible for “independent entity variations” under the rule. (See PJM Reaches Milestone on Clearing Interconnection Queue Backlog.) 

But on June 20, several clean energy and environmental organizations filed joint protests against PJM’s compliance filing. 

“PJM stretches the meaning of the ‘independent entity variation’ beyond any reasonable interpretation or application,” argued one group that included the American Clean Power Association. “Should the commission accept the compliance filing, PJM would completely avoid compliance with significant portions of” Order 2023. 

“The queue is so badly backlogged that PJM is not reviewing any new applications — and will not do so until 2026 at the earliest,” said another group that included the Natural Resources Defense Club. “At the same time, PJM is sounding the alarm about a reliability crisis because new generation cannot come online quickly enough to replace retiring power plants.” 

But “PJM resists reform to its interconnection process. PJM proposes very few changes to comply with Order No. 2023, and the few changes it proposes do not meet the order’s rigorous standards.” 

The RTO has not stopped accepting applications, Lockwood said, but new interconnection requests “will be studied starting in 2026 as we move the previously existing projects through the process.” 

Other State Efforts

The New Jersey bill follows other efforts by the state to improve and speed up the interconnection process for renewables as it strives to meet its aggressive clean energy goals. 

The state is seeking to install 12.2 GW of solar energy by 2030; it had about 4.85 GW of installed solar capacity at the end of April, according to the latest figures publicized by the BPU. 

The BPU on April 30 approved a package of rules designed to streamline the utility interconnection application process. Part of it included enabling applicants to get an early indication of the project feasibility and costs. (See New Jersey Opens 4th Offshore Wind Solicitation.) 

At the senate committee hearing June 20, NJUA’s Gurrentz said the organization was “not taking a position on the bill today,” but it is concerned that [it] could detract from some of the progress that’s gone on at the BPU and ship the application backlog that existed at PJM to a similar problem at home at our utility companies.” Another concern is the requirement to handle “very large” solar projects, up to 20 MW. 

“Undertaking these studies to determine the impact of such large interconnections on power quality, reliability and the stability of the electrical grid will take time, and it may divert time and resources that could be spent elsewhere,” he said. 

Gurrentz was the only person to testify in person on the bill, but it drew written expressions of support from Environment New Jersey, the New Jersey Division of Rate Counsel, the Mid-Atlantic Solar Energy Industries Association and the New Jersey Sustainable Business Council. 

Texas PUC Adds OPUC’s Hjaltman as 5th Commissioner

Texas’ Public Utility Commission is back to its full five-commissioner complement with the appointment of Courtney Hjaltman, CEO of the Office of Public Utility Counsel (OPUC) since 2022. 

Texas Gov. Greg Abbott named Hjaltman to the PUC on June 24 for a term that expires Sept. 1, 2025. She fills the seat left vacant by Will McAdams, who stepped down from the PUC in December to focus on his family and health. 

Abbott said Hjaltman’s service to the state and her legal expertise makes her the “ideal choice” to serve on the commission. “Courtney will ensure that Texans in every corner of our state have access to quality utility services for years to come,” he said in a statement. 

As OPUC’s CEO, Hjaltman advocated for Texas’ residential and small commercial customers. During the ERCOT Board of Directors’ meetings June 17-18, she voted against a protocol change revising an ERCOT ancillary service over concerns it would raise consumers’ rates. That likely means she will have to recuse herself when the PUC considers the protocol change. 

Hjaltman was Abbott’s deputy legislative director when she was appointed to OPUC and has more than 17 years of state service, much of it in the legislature. She holds bachelor’s degrees in science and arts from The University of Texas and is a graduate of the governor’s Executive Development Program at UT’s Lyndon B. Johnson School of Public Affairs. 

State lawmakers increased the size of the PUC from three commissioners to five after the disastrous and deadly 2021 winter storm. The three incumbents at the time lost their jobs in the storm’s aftermath.  

Report: Industrial Electrification Should Focus on ‘Easy to Abate’ Sectors

The U.S. could ramp up the electrification of heavy industry by 50%, reduce the sector’s fossil fuel use by 25% and cut its greenhouse gas emissions by 100 million metric tons per year by 2030, according to a new report from Schneider Electric’s Sustainability Research Institute.

But hitting those ambitious targets will require a shift of focus, the report says. Instead of prioritizing long-term solutions for the hardest-to-abate industries, such as petrochemicals, oil and coal, a different approach could zero in on the lower-hanging fruit of individual processes that can be electrified with existing technologies and without major changes to production.

“Emissions are not all equal,” the report says. “Those that can be reduced more rapidly hold much greater value than those that could be reduced in the future (even if massive).”

Pushing toward President Joe Biden’s goal of reducing the nation’s GHG emissions by 50 to 52% from 2005 levels by 2030, the U.S. has focused on electrification of transportation and buildings via incentives in the Inflation Reduction Act. But industrial electrification varies from sector to sector, the report says.

Electric arc furnaces are now widely used in steel production, but options for electrifying the high-temperature process heat needed for chemicals and oil and gas refining are still in the demonstration phase, according to the Department of Energy’s recent Pathways to Commercial Liftoff: Industrial Decarbonization report.

Industry accounts for about 23% of U.S. greenhouse gas emissions, according to EPA. The Schneider report notes that five sectors ― chemicals, petroleum and coal products, primary metals, nonmetallic minerals and paper ― make up close to 75% of that total.

Traditional approaches to industrial decarbonization require that certain hard-to-abate industries continue to rely on natural gas or other fossil fuels to produce the high heat they need, until alternative technologies such as green hydrogen, carbon capture and sequestration, and small modular reactors can be commercialized at scale.

The report cites 2020 research from the California Energy Commission suggesting that building electrification could drive a switch away from natural gas and a decrease in the customer base, driving up natural gas prices for both buildings and industry. Natural gas prices for industry could double by 2030, the CEC report predicts.

“This is particularly relevant in the context of rapid relocalization of a number of industries in the country,” the Schneider report says. “Will these new facilities be built for a net-zero world, relying on alternative and sustainable energy resources, or will they be connected to the existing natural gas grid and perpetuate reliance on fossil fuels?”

To move toward electrification, the report breaks down industrial energy use and emissions into subprocesses ― direct and indirect, process and nonprocess ― and identifies which could be electrified quickly in the coming decade. For example, most nonprocess energy use ― that is, energy not used for manufacturing but for building operations such as lighting and space heating and cooling ― could be rapidly electrified with existing technologies.

A second phase of industrial electrification would include the technologies currently being demonstrated but not yet deployed at commercial scale, especially for targeted processes in sectors such as food and beverage, textiles and electrical equipment, the report says.

Of the 21 industrial sectors analyzed in the report, the combination of the first and second phases could push eight to 80% electrification and 16 to at least 60% within a decade.

The report notes that half the reductions in fossil fuel use and GHG emissions will come from “easy to abate” industrial sectors, rather than hard-to-abate processes.

The report acknowledges the reduction in fossil fuel use will increase electricity demand ― by about 300 TWh per year ― but assumes that this new demand would be met with the wind, solar and storage sitting in interconnection queues across the country, providing additional efficiencies and emission reductions.

Getting the Finances Right

Beyond 2030, a third phase of industrial electrification would require innovative technologies still in development, such as electric “cracking” furnaces used in the production of petrochemicals and other electric furnaces, the report says.

Such innovations could drive industrial electrification to 64% across sectors, with 14 sectors hitting 80%, the report says.

“This major opportunity challenges the current hard-to-abate-centric approach to industrial decarbonization, which suggests little is achievable until new innovations deploy at scale.”

The obstacles ahead include a lack of information about the potential benefits of industrial electrification, getting the finances right and “grid reinforcements, which take several years to materialize.” The report provides general, mostly familiar recommendations.

To raise public and industry awareness, the report proposes the launch of dedicated state offices or clearinghouses to advance industrial electrification.

Getting the finances right will require making the cost of electrification competitive or at least comparable with natural gas, through tax incentives but also new approaches to electricity rate-setting, including time-of-use rates, to promote system flexibility.

Grid modernization and expansion will take time and will “come at the expense of natural gas grids and their associated revenues,” the report says. “This also requires a specific policy focus to ensure a smooth transition.”

State Briefs

CONNECTICUT 

Moody’s Downgrades Eversource’s CL&P to Negative Outlook

Moody’s Ratings last week downgraded Eversource Energy’s Connecticut Light and Power subsidiary to a negative outlook based largely on “an inconsistent and unpredictable regulatory environment.” 

The downgrade reinforces longstanding complaints by Eversource and United Illuminating, also recently downgraded, that their ability to raise capital is suffering from what they call “arbitrary” regulatory decisions that undercut their ability to earn on the hundreds of millions of dollars that they invest annually in clean energy projects and other grid improvements. 

“CL&P’s electric distribution business operates under the purview of the [Public Utilities Regulatory Authority], a regulatory framework that has become increasingly difficult due to higher political scrutiny and inconsistent regulatory decisions and rate case outcomes,” Moody’s said. 

More: Hartford Courant 

LOUISIANA 

Craig Greene Won’t Seek Re-election to PSC

Public Service Commissioner Craig Greene last week announced he will not seek re-election once his term concludes at the end of the year. 

“When you know, you know,” Greene, first elected in 2017, said in a news release. “For almost a decade, I’ve worked hard to keep a watchful eye on our utility providers, holding them accountable to keep prices affordable for the many families in our community struggling to get by.” 

Greene, who works full time as an orthopedic surgeon in Baton Rouge, said he will spend the extra time enjoying activities with his family and caring for his patients. 

More: Louisiana Illuminator 

MISSISSIPPI 

Hinds County Approves Apex Solar Farm

The Hinds County Board of Supervisors last week voted 3-2 to approve the 396-MW Soul City Solar farm. 

The 6,000-acre project, developed by Apex Clean Energy, will be the largest in the state when completed. 

Construction is planned to start this year and be completed by 2027. 

More: The Clarion-Ledger 

NEBRASKA 

Oldest Operating Wind Turbines in State to be Removed

Lincoln Electric System will remove two 290-foot-tall turbines, installed in 1998 and 1999, in July, as they have reached the end of their productivity. 

They were the oldest continuously operating wind turbines in the state, producing 1.3 MW combined. Both could have lasted a little longer, LES said, but it estimates it will save $100,000 by taking them down now. 

Scott Benson, manager of resource and transmission planning at LES, said the turbines helped the utility learn enough about wind power to enter its first small contracts for wind farms. “We learned a lot from them.” 

More: Nebraska Examiner 

NEW YORK

National Grid Says More Staff Needed to Comply with Climate Law

National Grid last week asked the Public Service Commission to raise annual electric delivery rates by $525 million a year across its upstate territory. If approved, the rate hike would raise the average monthly electric bill by $18.92 (15%). 

National Grid said one of the reasons for its request is the state’s 2019 Climate Leadership and Community Protection Act, as it is putting new pressures on the company to hire more employees to comply with the law. 

“The company is seeking to add incremental [full-time employees] to support its customer programs,” National Grid said in its filing with the PSC. “From a broad perspective [this] is necessitated primarily by the need to achieve the [law’s] energy efficiency and emissions-reduction goals.” 

More: Times Union 

NYSEG Fined $11.4M for Poor Customer Service Performance

New York State Electric and Gas was fined $11.4 million by the Public Service Commission for failing to meet all four of its customer service performance metrics. 

NYSEG’s sister company, Rochester Gas & Electric, also failed to meet all four metrics, resulting in a $7.1 million penalty. 

“Ensuring that the utilities operation in New York state maintain good customer service is a top priority for the commission,” said Chair Rory Christian. 

More: WETM 

Old Gas Line Left Open Caused Blast that Destroyed Syracuse Home

An explosion that collapsed a Syracuse house and injured 13 people last week was caused by an open natural gas line, fire officials said. 

Fire investigators inspecting the basement noticed a gas line intended to feed a clothes dryer was not connected to an appliance. The gas line had an open valve and was free-flowing natural gas at the time of the explosion. 

The landlord said there hadn’t been a dryer hooked up to the gas line for years. The line was not capped and only had a shutoff valve that was found in the open position. The line should have been capped, officials said. 

More: Syracuse.com 

OHIO 

Texts Show DeWine Initiated Dark Money Payment, Sparks New Bill

Newly revealed texts show that despite claiming no knowledge of the extent of FirstEnergy’s dark money support for his gubernatorial races, Gov. Mike DeWine personally solicited money from CEO Charles Jones. 

About a month before the 2018 election that launched DeWine into the governor’s office, he sent a text to Jones — indicted earlier this year on bribery charges — looking for cash. Jones forwarded the text to Senior Vice President Mike Dowling, who also was indicted this year on bribery charges. A $500,000 “dark money” contribution was later made. DeWine has not been accused of any criminal wrongdoing. 

The news has prompted Republican lawmakers to draft legislation requiring greater campaign finance disclosure from dark money groups. 

More: Cleveland.com; Ohio Capital Journal 

RHODE ISLAND

McKee Signs Legislation to Regulate Solar Companies

Gov. Dan McKee last week signed legislation designed to regulate solar companies and protect consumers from deceptive sales practices. 

The act will require solar retailers to register both their business and a roster of their representatives soliciting sales. Retailers must also conduct criminal background checks on principal officers and sales representatives, as well as follow municipal restrictions on door-to-door sales and federal telemarketing rules. 

The law will take effect March 1, 2025. 

More: WPRI 

VERMONT 

Legislature Overrides Scott, Passes Renewables Bill

The state legislature last week overturned Gov. Phil Scott’s (R) veto and enacted a law that requires utilities to source all of their electricity from renewable resources by 2035. 

Scott had said the bill would be too costly for ratepayers. Under the legislation, the biggest utilities will need to meet the goal by 2030. 

Senate President Pro Tempore Philip Baruth (D) called the governor’s veto an attempt to continue rejecting “critical progress on climate action” at a time when residents are still facing “the impacts of recent climate disasters.” 

More: The Associated Press 

Federal Briefs

EPA, DOE Announce $850M to Reduce Methane from Oil, Gas Sector

EPA and the Department of Energy last week announced that applications are open for $850 million in funding for projects that will help monitor, measure, quantify and reduce methane emissions from the oil and natural gas sector. 

Oil and gas facilities are the nation’s largest industrial source of methane, a climate “super pollutant” that is responsible for about one-third of the warming from greenhouse gases occurring today. 

The funds are from the Inflation Reduction Act. Applicants are required to submit community benefits plans to demonstrate meaningful engagement with and tangible benefits to the communities in which the proposed projects will be located. 

More: EPA 

DOE Picks New Company for Hanford Site Work

The Department of Energy has picked a California company for a contract worth up to $8.3 million to administer worker’s compensation claims at the Hanford nuclear site in Eastern Washington. 

Innovative Claim Solutions will replace Penser North America, of Lacey, Wash., which has held contracts to do that work since 2009. The new contract has a one-year base period, followed by options for one-year extensions up to a total of five years. 

The Penser contract, valued at $4.6 million when it was awarded, expires Sept. 30. A 60-day transition to Innovative will begin on Aug. 1. 

More: Tri-City Herald 

Company Briefs

ClearVue PV Selects San Jose for HQ

Solar developer ClearVue PV last week announced it has selected San Jose, Calif., for its U.S. headquarters. 

Australia-based ClearVue has developed specialized glass technologies that can keep a window fully transparent and generate electricity. The window allows light to pass through the glass before redirecting the incoming sun rays onto cells that can generate electricity for a building. 

The company expects to expand to 20 workers in San Jose. 

More: Redlands Daily Facts 

Ineos, NextEra Break Ground on Texas Solar Project

Chemicals company Ineos Olefins & Polymers USA, along with NextEra Energy Resources, announced they have begun construction of a 310-MW solar project in Bosque County, Texas. 

A NextEra subsidiary will build, own and operate the INEOS Hickerson Solar farm. The companies hope to reach commercial operation by December 2025. 

More: Renewables Now