It’s an “all-hands-on-deck” moment for CAISO to open its extended day-ahead market in less than two months, CAISO’s CEO Elliot Mainzer said at a Western Energy Market Board of Governors meeting.
The EDAM is on track to open May 1 with PacifiCorp as the first participant, but the ISO needs to work through a few issues it observed during PacifiCorp testing.
“We are on the threshold of EDAM implementation, [which] reflects several years of hard focus work,” Mainzer said at the March 3 meeting. “Our partners at PacificCorp are working so hard … they are going to be the first utility to join the new market just as they were the first utility to join the Western Energy Imbalance Market back in 2014.”
PacifiCorp recently finished CAISO’s market simulation and now is in parallel operations testing, which is divided into three parts, said Khaled Abdul-Rahman, CAISO vice president and chief information and technology officer. Each part does not take an equal amount of time: CAISO moves from one part to another depending on the results in a given part.
The final part of parallel operations testing should start in mid-March and focus not only on the day-ahead market, but also on rolling results into the real-time system, Abdul-Rahman said. This final phase will be a full, end-to-end test, starting from the day-ahead market and moving into the real-time market and then watching how the system and resources and market results perform, he said.
CAISO added an extra month to PacifiCorp’s parallel testing phase, pushing it to the end of April, days before EDAM opens. Typically, parallel operations testing takes about two months, but CAISO extended it to three months “to give us more time to work on any issues that are identified,” Abdul-Rahman said.
Despite this extension, CAISO is on track. “Things are looking really promising in terms of meeting our deadlines,” Abdul-Rahman said.
CAISO is using PacifiCorp’s onboarding and testing process to “beef up our training for [future] EDAM entities,” Abdul-Rahman said. “We are identifying issues and differences … between the real-time and day-ahead markets.”
One challenge has to do with the accuracy of charge codes in the EDAM system. Software updates are required to fix these code inaccuracies, and the updates are “being tested as we speak,” Abdul-Rahman added.
System scheduling issues arose because of differences between WEIM and EDAM. In particular, the real-time market uses the concept of a base schedule, which is not in EDAM. Instead, EDAM uses economic bids and self-scheduling, which will require more training,
WEM board member Robert Kondziolka asked if CAISO experienced challenges in working with PacifiCorp, since it has two balancing authorities.
“I don’t want to say it is complicated. … It looks like one entity that we are onboarding regardless of the number of balancing areas. The volume of the data is of course bigger,” Abdul-Rahman said.
CAISO is in the market simulation phase for EDAM’s second participant, Portland General Electric (PGE), which plans to join EDAM on Oct. 1. During this phase, CAISO will test all of its system interfaces to ensure the data flows.
“It’s a little early to report on PGE’s market simulation [results]. We just started the simulation literally yesterday,” Abdul-Rahman said.
