Protesters Doubt PJM Analysis of Transource Alternative

By Christen Smith

Landowners united against a proposed transmission project straddling the Pennsylvania-Maryland border said on Monday they doubt an alternate plan using existing lines may cost an extra $94 million, as PJM suggests.

“I don’t see how that’s possible that by using existing infrastructure that it could be more expensive,” said Barron Shaw, spokesperson for Citizens to Stop Transource. “It’s hard to understand.”

Shaw’s group includes residents from Pennsylvania’s York and Franklin counties and Maryland’s Harford County, where Transource Energy plans to construct two 230-kV double-circuit lines totaling about 42 miles, known as the Independence Energy Connection (IEC) project. PJM selected the $372 million proposal — its largest market efficiency project to date — during the 2013/14 long-term planning window to address congestion in the AP South interface and has five times since reviewed its benefits to the grid, determining in each round that the IEC remains the most effective way to reduce load costs.

PJM
Once referred to as the AP South Congestion Improvement Project, Transource’s Independence Energy Connection project would consist of two lines. The western portion would run from the Ringgold substation in Maryland to the Rice substation in Pennsylvania. The eastern line would run from the Conastone station in Maryland to the Furnace Run station in Pennsylvania. | Transource

In testimony submitted to the Maryland Public Service Commission on May 8, PJM’s Tim Horger said the RTO’s most recent analysis, completed in February, determined the IEC would generate a $931 million reduction in congestion costs over the next 15 years, with a benefit-cost ratio of 2.17 — well above PJM’s 1.25 threshold required for inclusion in its Regional Transmission Expansion Plan.

Protesters argue, however, that the need for the eastern segment of the project could be met by the existing Furnace Run-Conastone and Furnace Run-Graceton 230-kV double-circuit transmission tower lines, which each have only one 230-kV circuit and could carry a second. Maryland’s Power Plant Research Program (PPRP) urged the PSC to suspend the project while PJM studied the market efficiency of this alternative and three others — a request that was granted in January. (See More Info Needed on Tx Line Options, MD PSC Says and Cancel Transource Line, Md. Panel Says.)

As requested, PJM analyzed PPRP’s four conceptual alternatives and determined all but its third option — adding lines to the Furnace Run-Conastone towers — created thermal violations too costly to even consider for its RTEP. Even still, to help the remaining plan survive its market efficiency process, PJM and Transource expanded the scope to add a third transformer at the Furnace Run station that would alleviate possible reliability violations. This modified plan was called 3A in PJM’s testimony.

Steve Herling, PJM’s vice president of transmission planning, said in testimony that the additional transformer caused the Peach Bottom-to-Furnace Run 500-kV lines to reach 98.5% of its thermal conductor limit following a single contingency. Conversely, the IEC takes significant power load off that line, Herling said, calling into question the viability of the proposed configuration in 3A.

PJM’s analysis showed 3A would cost between $54 million and $94 million more than IEC and produce $267 million less in congestion benefits to the region. Its benefit-cost ratio ranges from 1.39 to 1.52, still well above PJM’s 1.25 threshold but lagging far behind the IEC’s rating.

Herling said none of the conceptual alternatives proved “demonstrably superior” or even equal to the IEC plan. Jeff Shields, PJM spokesman, said Monday that staff stand by their testimony.

PSC hearings on the project begin in Maryland on June 3. Meanwhile, an administrative law judge in Pennsylvania will consider the IEC’s reliability benefits after the state Public Utility Commission overturned a prior dismissal of PJM testimony regarding the issue.

PPRP has described PJM’s attempt to justify the project on reliability grounds as a “bait and switch.” Although the project was not needed to address reliability violations when it was approved, the RTO said “that the project would inherently enhance system reliability by introducing additional transmission network paths.”

“Reliability means generator-deliverability reliability,” Shaw said. “It’s not about keeping people’s lights on.”

Eversource Balks at ISO-NE Plan on CIP Costs

By Rich Heidorn Jr.

ISO-NE on Thursday proposed a “hybrid” filing Section 205 of the Federal Power Act to allow some generators to recover the costs of NERC critical infrastructure protection (CIP) requirements, but Eversource Energy suggested alternatives, saying it doesn’t want the costs collected as part of its transmission rates.

The RTO’s Jonathan Lowell made the proposal at a meeting of the New England Power Pool’s Transmission Committee on Thursday. It would allow cost recovery for generators designated by the RTO as “critical” to the determination of interconnection reliability operating limits (IROLs), which have higher CIP standards than other generators.

Violations of IROLs can lead to instability, uncontrolled separation and outages cascading into neighboring regions. Generators are designated as IROL-critical because of their characteristics and locations relative to other control areas, the RTO said.

ISO-NE says it has about as many IROLs as all other ISOs and RTOs together. “Because New England is at the eastern end of the Eastern Interconnection, a contingency in New England can have significant reliability impacts on systems to the west,” explained ISO-NE spokeswoman Marcia Blomberg. “Many interconnection reliability operating limits have been identified in New England to avoid creating those impacts, and many facilities have been determined to be critical to the determination of those limits.”

ISO-NE
Eversource Energy told the NEPOOL Transmission Committee that the costs of generators’ compliance with NERC CIP requirements should not be recovered in transmission rates. | Eversource Energy

The RTO is proposing to make a Section 205 filing with FERC to add a new OATT Schedule 17 for the billing and collection of FERC-approved IROL-CIP costs, with the RTO serving as billing agent. It would be based on a formula rate template listing recurring and nonrecurring costs.

The initial filing will “facilitate a smooth and efficient FERC review of the Section 205 formula rate filing by having resolved most controversies in advance,” the RTO said in a presentation.

Critical generators and similarly situated transmission facilities would then make their own Section 205 filings itemizing their costs for FERC review and approval.

ISO-NE said the two-step filing is necessary because the RTO cannot be responsible for supporting the costs of individual facilities.

‘Inappropriate’

But Cal Bowie, representing Eversource, told the committee in a presentation that it is “inappropriate” for generators to recover expenses through regional network load transmission charges. “Transmission charges should primarily reflect the costs of building, operating, maintaining and ensuring the reliability of the transmission system,” Eversource said.

The company said the RTO should instead consider collecting the costs under its capacity load obligation (used to recover the “missing money” not recovered by generators in the energy market) or real-time non-coincident peak load obligations (Schedule 3 reliability administration service costs). Eversource also said the RTO should create a separate billing item for CIP costs to make them transparent.

According to the New England States Committee on Electricity, transmission costs are between 11 and 18% of total electric bills for residential customers in the region. Total transmission charges have risen from about $869 million in 2008 to $2.25 billion in 2018, NESCOE says.

Asked whether ISO-NE could accommodate Eversource’s proposal, Blomberg said the RTO believes its cost-allocation plan “is the most appropriate solution to ensure compensation” for the NERC compliance requirement.

“The ISO is continuing to listen and discuss this issue with stakeholders,” she added.

In a presentation to the Transmission Committee on March 27, ISO-NE had proposed a cost-of-service reimbursement method, saying a 2017 effort to create a formula rate failed because the RTO was unable to identify a methodology to determine an IROL-critical “proxy” generator or estimate reasonable costs for compliance with the NERC standard.

ISO-NE says the lack of “clear and precise CIP requirements” in standard CIP-002-5.1a Attachment 1 may lead generators to differing interpretations on what steps they need to take. The RTO said costs disclosed by the operators of seven IROL-critical generating stations showed both one-time capital costs and recurring O&M expenses. There was no obvious correlation between costs and generator size, type or vintage, ISO-NE said.

Blomberg said a formula rate is not the same as a proxy rate approach. “Under a formula rate approach, the facility submits its specific costs for approval. A proxy rate is an estimate of the costs of a generic, but similar, facility without consideration of the actual costs. IROL-CIP facilities all have different characteristics, which make proxy rate approach extremely challenging.”

ISO-NE said IROL-CIP costs should be allocated to regional network service and through or out service because accurate IROLs allow the RTO to maximize use of the transmission system.

Lowell told the committee at the March meeting that the ISO-NE would consider alternatives to the cost-of-service proposal if it had broad support within NEPOOL and had a cost estimation methodology the RTO could defend as just and reasonable.

NERC spokesman Martin Coyne declined to comment on the RTO’s characterization of the CIP requirements.

“[We] can’t comment on a presentation that’s not ours or for security purposes discuss details on critical facilities,” he said.

He added: “It is common for entities to seek information from NERC on how specific requirements in our stakeholder consensus-based standards apply to them.”

Business Procedure Change Approved

In other matters, the committee approved ISO-NE’s proposal to make administrative changes to Ancillary Service Schedule 2 of Section II of the Tariff and the VAR Business Procedure, along with revisions to accommodate electric storage reactive resources. The changes move requirements from the Business Procedure into the Tariff and incorporate electric storage facility language into the Schedule 2 capacity cost compensation program.

The RTO said the changes were related to FERC’s Feb. 25 approval of revisions to Section II that created multiple constructs for storage devices to participate in the RTO’s day-ahead and real-time energy markets (ER19-84). (See FERC Accepts ISO-NE Storage Tariff Revisions.)

PJM PC/TEAC Briefs: May 16, 2019

VALLEY FORGE, Pa. — PJM’s existing Market Efficiency Process Enhancement Task Force will tackle concerns raised by the Independent Market Monitor over its benefit-cost analyses for transmission projects.

PJM Director of Infrastructure Planning Sue Glatz told the Planning Committee on Thursday that staff agreed the issues raised in the Monitor’s problem statement last month would be best addressed in the task force’s third phase. (See “Revisit Benefit-cost Analysis, Monitor Says,” PJM PC/TEAC Briefs: April 11, 2019.) Glatz stood in for PC Chairman Ken Seiler.

The Monitor said last month that PJM’s current benefits calculation ignores increased congestion in all zones resulting from a transmission project. Specifically, the benefit-cost analysis does not account for the fact that transmission project costs are not subject to cost caps and may exceed estimated costs by a wide margin. When actual costs exceed estimated costs, the benefit-cost analysis is effectively meaningless, and low estimated costs may result in inappropriately favoring transmission projects over market generation projects or the option of no project at all, the Monitor said.

PJM
Side-by-side comparison of estimated project costs. The bars represent the possible spectrum of cost for each project, with the bottom of the bar representing the project sponsor’s cost estimate and the top point indicating an independent consultant’s estimates. | PJM

Generation Interconnection Requests Update

PJM proposed revisions to its generation interconnection requests process, as detailed in Manual 14G.

Lisa Krizenoskas, PJM senior engineer, said the first proposed change expands rules for demand response found in section 1.7. Staff propose directing on-site generators used to reduce load that participate as DR to Manuals 11 and 18 for further guidelines, while requiring the portion of any such generator that injects power past the point of interconnection to follow the existing interconnection process outlined in Manual 14G.

PJM also proposes a site control term of three years — two years for projects of 20 MW or less — commencing on the first day of the new services queue in which the customer submits its request. Extensions must be exercised by the developer at the time site control evidence is given to PJM.

New Fee Structure for Cost Containment Needed

PJM said its reconfigured cost-containment process will charge developers a lot more money, even for projects valued at less than $20 million.

Mark Sims, PJM’s manager of infrastructure coordination, said the old tiered approach, approved in 2014, doesn’t account for the increased cost of the new comparison framework that involves independent consultant review and legal and financial analyses.

“A lot of work is going to be done in parallel, which is going to increase costs,” Sims said. “A lot of projects up to $100 million will need extensive analysis. That’s just the bottom line. We aren’t sure the existing fee structure is going to work.”

Currently, PJM charges nothing for cost-containment review of projects $20 million or less. Projects up to $100 million cost $5,000 to review and larger projects incur a $30,000 fee.

Sims said the expense of paying independent consultants for each individual project proposal could reach $50,000. He said staff are working to finalize a new fee structure to present to stakeholders in the coming months.

RTEP Language on Track for June MRC Vote

PJM
Aaron Berner | © RTO Insider

Aaron Berner, PJM’s manager of transmission planning, said proposed revisions to the Regional Transmission Expansion Plan process remain on track for a vote at the June Markets and Reliability Committee meeting.

LS Power proposed an amendment in January to Manual 14B that was slated for stakeholder endorsement at the April 25 MRC meeting. The proposal specifies that a transmission owner’s supplemental project “will generally be removed from the RTEP” following a final order by a state siting agency rejecting the project. Supplemental projects are proposed by TOs and are not required for compliance with PJM’s reliability, operational performance or economic criteria. (See “RTEP Removal Language Vote Deferred Again,” PJM MRC/MC Briefs: April 25, 2019.)

Berner said PJM asked stakeholders to submit feedback by today so staff can present revised manual language at the May 29 meeting.

Geomagnetic Disturbance Data Needed

PJM wants TOs to submit new or updated data on facilities susceptible to geomagnetic disturbance events as part of its ongoing effort to establish procedures in sync with NERC requirements.

Affected facilities are those that include high-power transformers with a high-side, wye-grounded winding with terminal voltage greater than 200 kV.

PJM wants the TO-supplied data by July 18 so that further analysis can be completed in 2020.

Dominion Supplementals

Dominion Energy submitted requests for supplemental projects during Thursday’s Transmission Expansion Advisory Committee meeting.

A Dominion customer wants to add a third 84-MVA distribution transformer at the Enterprise Substation in Loudoun County, Va. The new transformer is being driven by continued data center load growth and alternate feed contract reservations, with a requested in-service date of July 15, 2020.

In the same county, Dominion wants to add a fourth 84-MVA distribution transformer at the Poland Road Substation. The need is driven by continued load growth in the area and contingency loading for the loss of one of the existing transformers, with a requested in-service date of Dec. 31, 2021.

In Prince William County, Dominion requested a new substation to support a data center campus with a total load in excess of 100 MW, with a requested in-service date of Dec. 15, 2021.

Dominion also presented nine proposed solutions for requested supplementals at a total cost of $104.25 million.

PJM
| © RTO Insider

American Electric Power Solution

American Electric Power presented a solution to one of its proposed supplemental projects for the Tanners Creek line in Indiana on Thursday.

AEP wants to spend $5.93 million installing two new 345-kV breakers to address faults on the connecting Dearborn line. A crew will move the existing M2 breaker into a new N string, allowing for the termination of the Dearborn line. A new 345-kV breaker will complete the T string.

Alternative solutions include reterminating the 345/138-kV transformer and 345-kV Dearborn line into existing breaker spots. Because of the way the station is laid out, this would require reconfiguring multiple 345-kV lines and would cost more, AEP said.

Protection Standards Revisions Endorsed

Stakeholders unanimously endorsed editorial changes to Manual 7: PJM Protection Standards.

The revisions reflect industry standard updates from the Institute of Electrical and Electronics Engineers and will apply to all new projects approved after Jan. 1, 2012.

– Christen Smith

SPP Western Reliability Briefs: Week of May 13, 2019

GOLDEN, Colo. — SPP staff last week shared a proposed “modification oversight process” with its Western reliability coordination customers, much to the glee of those involved.

Given the industry’s fondness for acronyms, there’s always room for one more: The process was tagged as “MOP.”

“Mop it up!” advised SPP Operations Vice President Bruce Rew as staffer Clint Savoy prepared to explain the process during a Friday conference call with the Western Reliability Executive Committee (WREC).

“That’s what we use to clean up stuff,” Savoy said.

SPP
The SPP Western Reliability Working Group gathers in Golden, Colo. | © RTO Insider

MOP actually borrows from SPP’s existing revision-request process to provide a means of managing document modifications (modification responses, or MRs) related to the RTO’s Western RC services. Savoy said it applies to documentation established by SPP or its working groups that might affect operations or have a compliance or financial impact on its Western RC services customers.

“MRs identify which governing document or specific section requires a review and approval, and by which groups,” Savoy explained.

The process establishes submission timelines, how to submit and respond to comments, and guidelines for public posting. MOP incorporates the impact analysis and recommendation reports familiar to SPP’s Eastern members.

SPP said in September it had signed contracts to provide RC services to balancing authorities representing about 12% of Western Interconnection load, effective Dec. 3. Peak Reliability, which has been the West’s RC since 2011, is winding down operations by the end of the year. (See CAISO RC Wins Most of the West.)

The Western Reliability Working Group (WRWG), which reports to the WREC, debated the MOP during a May 14-15 meeting in the Rocky Mountains’ foothills. As the primary — and currently only — SPP working group in the West, the WRWG will be responsible for taking one of five actions on any MR: approve, reject, table, withdraw or refer.

The WREC will be the final authority and can take the same five actions, the lone exception being remanding — rather than referring — an MR back to the working group.

The WRWG was unable to reach consensus on whether the executive committee should see every MR the working group approves or just those that aren’t unanimous. Members were also unable to agree on how the WREC would revise an approved MR.

SPP
WRWG Chair Denton McGregor | © RTO Insider

“My concern with the process is the time consideration,” said Black Hills Energy’s Denton McGregor, the WRWG chair. “But with 40 [stakeholder] groups in the East, SPP seems to be managing [the process].”

The WREC discussed the same issues during its conference call before voting to require that all items needing approval be sent to the committee. Its members also agreed they should provide guidance when remanding MRs back to the WRWG.

“We should tell them exactly what were the concerns that led to the turndown,” Rew said.

“I believe the WREC exists for a reason,” said WREC Chair Keith Carman, of Tri-State Generation and Transmission. “We don’t need a strong hand of approval, but simply having these items come to us provides value. It gives us the ability to be aware of things that are changing.”

The MOP has yet to be approved. SPP is still gathering comments from Western entities with plans to gain the WRWG’s approval in June. Savoy is scheduled to bring a final version for approval to the WREC in July.

RC Still Needs Data-sharing Agreement

Lack of a final data-sharing agreement appears to be the lone sticking point in SPP’s plans to extend RC services into the West.

SPP
SPP’s Yasser Bahbaz explains the West’s different data-sharing agreements. | © RTO Insider

Peak currently operates under a universal data-sharing agreement (UDSA) that gives operating entities access to key data necessary for reliable system operations and meets NERC standards. CAISO has used that agreement and revised it to create a Western Interconnection Data Sharing Agreement (WIDSA) that it will use moving forward, SPP staff said.

SPP conducts its business in the East under NERC’s operating reliability data (ORD) confidentiality agreement. It has worked with CAISO to add language to the WIDSA that allows non-signatories to see some of the data but hopes to have everything resolved before shadow operations start in October.

SPP’s Yasser Bahbaz said the WIDSA acknowledges the ORD. “We’re in a much better place than we were two months ago,” he said.

Elsewhere, SPP remains on track to meet the go-live date with progress on a several fronts:

  • The Congestion Management and Seams Task Force, one of three groups reporting to the WRWG, is developing a congestion management methodology that CAISO “can agree to as well,” Tri-State’s Michael Houglum said. “We’re getting close to this,” he said. “It’s already so much better than what we used to have [with Peak].”
  • SPP staff are testing its custom R-Comm messaging system with the Grid Messaging System (GMS) used by the Western Interconnection’s other RC providers (the Alberta Electric System Operator, BC Hydro, Gridforce and CAISO). SPP and CAISO have also created a communication protocol whereby neighboring balancing authorities and transmission owners that lie across the seam can send messages using GMS or R-Comm, depending on their RC. SPP is also setting up an application programming interface (API) that will further enable messaging with CAISO.
  • Staff said SPP will register as SPPW in the North American Energy Standards Board’s electric industry registry (EIR), effective Dec. 3. This will require SPP’s Western RC entities to designate the RTO as their RC before Dec. 21, when Peak plans to pull its EIR registration. Software developer OATI administers the web-based tool, which collects e-tags from registered entities that feed into the unscheduled flow mitigation plan.
  • SPP has completed site visits with all the Western entities, helping increase the RTO’s familiarity with the region. “It gives us an appreciation for how they do things in the West,” Bahbaz said. The RTO will welcome visitors to its Little Rock, Ark., headquarters in the fall.
  • An East-West system model is expected to go into production in July using a Western model based on a Peak model published earlier this year.
  • SPP has been holding monthly calls with training representatives in the Western footprint. Operator training begins in September. Staff are discussing with CAISO restoration training in 2020.

Three major deadlines loom: the Sept. 1 completion of on-site RC certification, the Oct. 1 commencement of shadow operations with adjacent RCs and the Dec. 3 go-live to begin providing RC services.

SPP’s Reliability Plan Confidential, but…

Bahbaz told the WRWG that SPP’s reliability plan includes both its Eastern and Western footprints and should “hopefully meet the need of anyone interested in SPP procedures.”

However, those interested in SPP procedures will have to travel to Little Rock to view the plan.

“The plan has steps specific to SPP’s system, and SPP believes those are confidential to SPP,” Bahbaz said. “We will show the procedures to anyone who comes to [our] control room.”

“We can follow directions just fine,” Houglum said. “It helps everybody’s knowledge if we understand why you’re asking us to do certain things in certain instances. Any background information we have allows us to execute those decisions better.”

Working Group Revises its Charter

The WRWG made several changes to its charter, adding clarity to term limits for the group’s leadership and its voting structure.

Members agreed to limit the chair and vice chair to two-year terms, with the initial term beginning in January 2019. Elections will be held at the end of the calendar year. Should one of the positions become vacant before the term expires, a special election will be conducted during the next regularly scheduled meeting.

The WRWG also revised the charter to include the use of a simple majority (greater than but not equal to 50%) of those present and voting to determine motion outcomes.

SPP
Black Hills’ Denton McGregor and SPP’s Clint Savoy share a light moment. | © RTO Insider

“SPP wants engagement,” McGregor said. “You need to be present and take part if you want your voice heard.”

Other charter revisions eliminated the need to reach a unanimous decision before requesting feedback from the WREC and added the ability to review and approve or reject revisions to applicable documents in accordance with the MOP, and to provide recommendations and escalate to the WREC items requiring financial consideration.

WRWG Members: Coordinating Communication Helpful

Working group members found the discussion beneficial, even if they did spend considerable time trying to determine whether abstentions count against a unanimous vote. “An abstention is not a vote,” said Colorado Springs Utilities’ Warren Rust, stating the group’s consensus position.

“This is all related to coordinating and communicating activities,” McGregor said. “There are a lot of moving parts and pieces to everything, not just with SPP, but here in the West. This keeps us informed.”

“Oh yes, this is helpful, just having come and hearing the discussion,” said Linda Jacobson-Quinn of Farmington Electric Utility System in New Mexico. “It’s the good old theory that if there were no communication at all, we wouldn’t be able to build the things we need in order to ensure reliability.”

Savoy, SPP’s senior interregional coordinator, said the RTO’s significant progress in offering RC services to the West is “a direct result of the engagement of stakeholder groups.”

“I think the representatives all agree that our collective success is dependent on solidifying relationships and promoting collaboration between entities,” he said. “That’s where SPP believes we provide significant value to our stakeholders.”

— Tom Kleckner

FERC Ends Examinations of TO Tax Calculations

By Amanda Durish Cook

FERC on Thursday terminated its investigations into the tax calculations included in transmission rates after several MISO transmission owners made compliance filings to remove a two-step averaging methodology that could inflate rates by underestimating tax credits.

The commission accepted compliance filings in part for MISO TOs ALLETE, Montana-Dakota Utilities, Northern Indiana Public Service Co., Otter Tail Power and Southern Indiana Gas & Electric (EL18-138), as well as American Transmission Co. (EL18-157) and International Transmission Co. (EL18-159). It also fully approved filings submitted by CAISO TOs GridLiance West (EL18-158) and Southern California Edison (EL18-164).

All the TOs proposed to end the use of a double averaging formula to calculate accumulated deferred income taxes (ADIT).

FERC last year ordered compliance filings and opened a Section 206 proceeding investigating TOs’ use of the practice. (See FERC Acts on Transcos Revised Tax Calculations.)

Some MISO TOs were using a two-step averaging methodology in their projected test year calculations of ADIT balances, but FERC said the practice makes deferred income tax credits appear lower than they should be, possibly raising rates because averaging the prorated ADIT value for the year with the beginning-of-year ADIT balance “produces a result that is disproportionately skewed towards the beginning-of-year balance.” (See FERC Broadens Challenge to TOs Tax Calculations.)

FERC got a bit more than it bargained for when the MISO TOs submitted compliance filings that also revised their annual ADIT true-up calculations.

The commission rejected the MISO TOs’ proposed revisions to apply the IRS’ proration methodology to their annual true-up calculations, saying the effort was beyond the scope of compliance.

“The filing parties’ proposal to prorate certain MISO TOs’ annual true-up calculations is not necessary to comply with the remedy … and is thus outside the scope of this compliance proceeding,” FERC said.

It directed the TOs to make further compliance filings that include the revised ADIT calculations, this time leaving out “any other modifications or revisions.”

The commission said if the TOs still want to revise their transmission formula rates to apply the proration methodology in their true-up calculations, they could make separate filings for FERC review.

METC Filing Rejected

In a proceeding separate from the other MISO TOs, Michigan Electric Transmission Co. (METC) failed to earn FERC’s stamp of approval over its attempt to address the ADIT issue (EL19-16). In that order, the commission said that while METC’s proposed removal of two-step averaging complied with FERC’s directive, the company’s request to include the IRS’ proration methodology in its true-up calculations for all of 2019 amounted to retroactive ratemaking because the company had submitted its filing on Jan. 22.

“Although we are rejecting METC’s filing, we note that it may refile its proposal to apply the IRS’ proration methodology to its true-up calculations, provided that its proposed revisions apply prospectively, in a separate [Federal Power Act Section] 205 filing. The commission will evaluate the proposal at that time,” FERC said.

Robert Mullin contributed to this article.

PJM Revisits Gas Pipeline Contingency Plan

By Christen Smith

VALLEY FORGE, Pa. — PJM asked for stakeholder feedback last week about how to reshape its gas pipeline contingency plan, three months after FERC turned it down for lacking specificity and clarity.

“We talked with FERC staff to get a read on what they want to see in a new proposal,” Thomas DeVita, PJM senior counsel, told the Market Implementation Committee on Wednesday. “We got an insight to their thinking. … The key point is the commission wants to see a meeting of the minds between generators and pipelines.”

On Feb. 19, FERC rejected the stakeholder-approved mechanism that would have implemented a process for market sellers seeking cost recovery for certain gas contingencies associated with the RTO’s instruction to temporarily switch to an alternative fuel or alternative fuel source because of pipeline breaks or the loss of compressor stations (ER19-664). The proposal included nine cost categories of switching costs, including park-and-loan service charges and overrun charges.

PJM
PJM’s Market Implementation Committee meeting on May 15 | © RTO Insider

The commission said PJM’s definition of penalty was “unreasonably narrow and unsupported” because pipeline tariffs delineate between penalties and fuel-switching costs in different ways, meaning what appears to be an appropriate cost for one pipeline could be considered a penalty for another. FERC also faulted PJM for not including events that might trigger fuel-switching directives in its Tariff and for lacking procedures for dealing with such contingencies through the Capacity Performance market design. (See FERC Rejects PJM’s Gas Contingency Pipeline Proposal.)

DeVita said commission staff discouraged PJM from submitting an itemized list of switching costs, as it did in the first filing, and instead focus on procedures surrounding “explicit authorization” to switch between pipelines and any new limitations on the amount of gas burned after the switch occurs. Rich Brown, manager of PJM’s system operator training, said FERC’s focus on authorization and fuel burned reflects the commission’s insistence on ensuring reliability is maintained during any switch.

David “Scarp” Scarpignato of Calpine said that approach would not protect his company’s interests.

“I’m not comfortable that we just leave it open and send it to FERC with no guidance on what’s a coverable cost and what’s not,” he said. “Just getting over the hurdle of notice is not enough to give us confidence that our costs will be recovered.”

PJM
Thomas DeVita | © RTO Insider

In a January filing with FERC, Duke Energy and East Kentucky Power Cooperative said they generally supported the idea of compensating generators for switching fuels, but they worried that PJM’s enumerated categories didn’t capture all the possible costs. Without an exhaustive list, they said, generators lacked financial incentive to make the switch or the ability to recoup expenses after-the-fact.

Marji Philips, Direct Energy’s director of RTO and federal services, told the MIC that if generators know PJM will order the switch — instead of generators making the call themselves — the cost of fuel switching is transferred to customers instead. The filing isn’t clear as to whether generators who can’t perform will incur CP penalties, either, she said.

“This is so fundamentally flawed,” Philips said. “It is not pipelines that do the switching. It’s whoever owns the capacity on the pipeline. We need to rethink this and reframe how we think about this.”

The Independent Market Monitor and the PJM Industrial Customer Coalition further alleged that the RTO’s gas-electric coordination remains an information-sharing process, therefore PJM can’t give operational instructions to pipelines. Moving customers with firm contracts off some pipelines — while others with lower levels of service remain unaffected — may discourage the former group of market sellers from taking proper steps to obtain reliable back-up fuel sources, they said.

The D.C. Office of the People’s Counsel crafted the Operating Agreement and Tariff changes detailed in the rejected filing after earning a majority of stakeholder support at the December meeting of the Markets and Reliability Committee.

The supermajority vote was a victory for load interests who opposed a Calpine-authored plan endorsed at the MIC in November. That proposal would have developed a formula for cost recovery to be filed with FERC that did not include pipeline penalties.

Although ongoing services generally include cost recovery formulas, DeVita said FERC may interpret the “rare” event of generators seeking fuel-switching reimbursement as incomparable.

“We are very concerned about cost to load,” said Adrien Ford of Old Dominion Electric Cooperative. “We are also very concerned about generators mitigating their own risk. We are in no man’s land now.”

FERC Ends Notices of Alleged Violations

By Michael Brooks

WASHINGTON — FERC on Thursday officially rescinded its controversial policy of allowing its Office of Enforcement to publicly disclose its investigations of possible misconduct and their subjects’ identities, ending a practice in place since 2011 (PL10-2-003).

The commission in 2009 authorized Enforcement to issue a Notice of Alleged Violations (NAV) after the subject of an investigation had the opportunity to respond to the office’s preliminary findings. Enforcement issued its first five NAVs on Jan. 25, 2011, four of which dealt with alleged market manipulation in ISO-NE’s Day-Ahead Load Response Program.

NAVs, however, were not like indictments: They were issued before Enforcement staff had finished their investigations and reached their conclusions in the case. Prior to 2011, the commission only disclosed the existence of an investigation and its subjects’ identities when it approved the issuance of an Order to Show Cause (OSC). NAVs also did not need to be approved by the commission itself; instead, they were issued after approval from the director of enforcement.

FERC

FERC holds its open meeting May 16. | © RTO Insider

FERC said it had “acknowledged the potential risk of reputational harm that might result from the issuance of a NAV but sought to strike a balance between protecting the confidentiality of investigations and promoting the public interest of heightened transparency.”

But the commission found that issuing NAVs generated little information for Enforcement’s investigations. And since the policy’s adoption, the commission found that other sources, such as data provided by RTOs under Order 760, have been more useful.

“Accordingly, the commission finds that the potential adverse consequences that NAVs pose for investigative subjects are no longer justified in light of the limited transparency NAVs have generated and the more effective, alternative means of adding transparency that the commission has developed since the NAV order.” These means include providing guidance through orders on settlement agreements, OSCs and orders assessing civil penalties.

At FERC’s open meeting Thursday, Commissioner Richard Glick said the policy had been unofficially ended for some time. Indeed, the last time Enforcement issued a NAV was in April 2018, the only one that year. (See FERC Investigation Shows PSEG Violated PJM Bidding Rules.) Prior to that, the office on average issued seven to eight per year.

While Glick acknowledged that NAVs had provided limited value, and joined in the unanimous vote to end the practice, he said that “the Office of Enforcement must act aggressively when there is evidence of market manipulation or other malfeasance that could adversely impact our jurisdictional markets, and I intend to review any future proposals affecting Enforcement’s role with that in mind.”

Asked by reporters after the meeting whether the commission was considering any other changes to Enforcement policies, Chairman Neil Chatterjee declined to comment.

FERC Approves Expansion to Freeport LNG Export Terminal

By Michael Brooks

WASHINGTON — FERC voted 3-1 on Thursday to approve the construction of a fourth liquefaction unit at the Freeport LNG export terminal in Brazoria County, Texas (CP17-470).

The unit, called a “train” in the LNG industry, will allow for the export of an additional 5.1 million metric tons per annum (mtpa), equivalent to about 0.74 Bcfd. Currently, the facility has a capacity of 15.49 mtpa (2.14 Bcfd), according to FERC.

The approval of the so-called Train 4 Project marks FERC’s fourth approval of an LNG project this year, following last month’s approval of the Driftwood and Port Arthur projects, and February’s approval of the Venture Global Calcasieu Pass project. And as has become common, the order elicited celebration from Chairman Neil Chatterjee, a reluctant concurrence from Commissioner Cheryl LaFleur and a dissent from Commissioner Richard Glick over the commission’s reticence to assess the project’s impacts on global climate change.

“I’m proud of the efforts by the commission and its staff to process today’s and our previous LNG orders,” Chatterjee said in a statement. “Exporting LNG from the United States can help increase the availability of inexpensive, clean-burning fuel to our global allies who are looking for an efficient, affordable and environmentally friendly source of generation.”

FERC
Freeport LNG export terminal | Freeport LNG Development

FERC disclosed in its order that its environmental assessment (EA) of Train 4 estimated that operation of the project may result in emissions of up to 491,500 metric tons per year of carbon dioxide equivalent, increasing national emissions by about 0.01%. “Currently, there are no national targets to use as benchmarks for comparison,” the commission said.

This was enough to secure LaFleur’s vote, though she warned that the order, as with previous LNG approvals, are vulnerable to judicial scrutiny. She also noted that an additional risk existed for Train 4 because the commission issued an EA instead of an environmental impact statement (EIS). Under the National Environmental Policy Act, federal agencies issue an EIS when they find that an action will have a significant impact on the environment.

“This tension between the finding of no significant impact, and the commission’s failure to assess significance of climate change impacts, heightens the risk that a court could vacate and remand this project, simply on the basis of which environmental document was prepared,” LaFleur said in her concurrence.

At Thursday’s meeting, Glick noted that Chatterjee has said that the Natural Gas Act doesn’t give the commission authority to analyze the impact of natural gas infrastructure on climate change. He then turned and appealed directly to Chatterjee, suggesting that they “work together to send some draft legislation to Congress to fix the problem and clarify that FERC does have such authority.”

Asked by reporters about Glick’s remarks after the meeting, Chatterjee dismissed the idea, saying “there is a 0% chance that such legislation could get through the United States Senate. We have so many things to focus on, that to me is not a worthwhile thing to spend time on.”

Commissioner Bernard McNamee said the approval was “another great achievement.” He emphasized “that we have considered all the environmental effects, including greenhouse gases. I know there’s a disagreement about … how those should be measured. … But a disagreement about that does not mean they were not considered.”

Refund Hearing Ordered in Pseudo-Tie Complaint

By Amanda Durish Cook

Refunds appear imminent in a three-year dispute over MISO and PJM’s past practice of double-charging pseudo-tied generation for congestion fees after FERC last week ordered settlement proceedings to determine how much the RTOs must remit to address the redundant costs incurred from 2016 onward (EL16-108).

The issue stretches back three years to when Tilton Energy lodged a complaint against the RTOs for assessing overlapping congestion charges on pseudo-tied resources. American Municipal Power, Northern Illinois Municipal Power Agency, Dynegy and Illinois Power Marketing soon filed similar complaints. FERC consolidated the proceedings.

The RTOs introduced a temporary rebate program in 2017, then began including pseudo-ties in the day-ahead scheduling process in 2018 to end redundant congestion costs. (See MISO, PJM Pursue Pseudo-Tie Double-Charge Relief.) In March, MISO got FERC approval for a second piece of the solution, where participants with pseudo-tied resources can use the day-ahead market to hedge against real-time congestion.

MISO
| © RTO Insider

In its order, FERC noted that it has already accepted two filings apiece from MISO and PJM to address overlapping charges and has since discovered that those proposals have eliminated the congestion overlap. But those corrections come too late for the transmission customers already assessed those charges, FERC said.

“We find that the potential for overlapping or duplicative charges for congestion existed prior to the effective dates of the revisions,” the commission said.

As such, FERC established settlement procedures to determine the appropriate refunds owed to owners of pseudo-tied generation. The commission said if the involved parties don’t settle, a settlement judge will decide the case by May 18, 2020. FERC set a refund effective date of Aug. 25, 2016.

FERC: MISO Congestion and Admin Charges Appropriate

However, the refunds will not include the costs of MISO’s non-duplicative congestion and administrative charges that Tilton also challenged.

Tilton claimed MISO violated its Tariff by erroneously using financial schedules to assess charges on pseudo-tied generation, arguing the schedules are meant to represent contracts between two market participants and that the RTO is not a counterparty to the pseudo-tie transactions.

The company said MISO circumvented a Tariff provision and implemented Business Practices Manual language when it used its financial schedules to record transmission transactions for pseudo-tied generation “despite the nonexistence of a bilateral transaction that is a prerequisite for the use of a financial schedule.”

Tilton also argued that MISO’s assessment of real-time congestion costs against generation pseudo-tied from MISO to PJM is improper because the charges cannot be hedged and are “inconsistent with market fundamentals.” The company asked FERC to put a stop to MISO’s assessment of congestion and administrative charges.

In response, MISO argued that Tilton failed to show the RTO was acting counter to its Tariff and said the complaint should be thrown out. It also said Tilton failed to initiate dispute resolution procedures prior to filing the complaint, a break with commission precedent.

“Although Tilton has purchased long-term firm transmission service from MISO to PJM, paying for transmission service does not exempt Tilton from paying for congestion and losses,” the RTO explained.

The commission sided with MISO, ruling that Tilton must pay to use the RTO’s system.

“We conclude that MISO’s assessment of congestion costs and administrative charges on Tilton does not violate the MISO Tariff. Specifically … we find that the MISO Tariff authorizes MISO to assess congestion costs and administrative charges on pseudo-tie transactions. We also find that it was not a violation of the MISO Tariff for MISO to use financial schedules as a vehicle for imposing congestion and administration charges on Tilton,” FERC said.

The commission pointed out Tilton is a MISO transmission customer taking transmission service “to facilitate its pseudo-tie transactions” and is thus required to pay applicable charges.

Pseudo-tie transactions that use the the RTO’s system nevertheless contribute to its real-time congestion, FERC added.

NEECE Panelists Discuss Public Policy Drivers

By Michael Kuser

GROTON, Conn. — As Northeast states continue to expand their clean energy goals, the region faces the prospect that multiple overlapping public policies will create an oversupply of renewable resources at certain periods.

NEECE conference - discussing the impact of renewables targets and public policy on power markets

CPES and NECA hosted the 2019 New England Energy Conference and Exposition in Groton, Conn., on May 14-15. | © RTO Insider

“We’re very soon, even with the contracts we have in place, going to be in a position where our supply of contracted resources is going to exceed demand in some hours,” Katie Dykes, commissioner of the Connecticut Department of Energy and Environmental Protection (DEEP), said Wednesday at the 2019 New England Energy Conference and Exposition, hosted by the Connecticut Power and Energy Society and the Northeast Energy and Commerce Association.

NEECE renewables

Katie Dykes | © RTO Insider

Dykes noted that the Connecticut House of Representatives had a day earlier approved legislation (H.B. 7156) that would authorize DEEP to procure up to 2,000 MW of offshore wind resources over the next decade, “with a real focus on looking at a solicitation to be issued as soon as possible after the ink is dry on the governor’s signature.”

“It’s really an exciting time, [and] the question society has to be focusing on in the integrated resource planning process in Connecticut is how are we meeting resource adequacy with the public policy resources,” Dykes said. “We have to think about when we’re buying zero-carbon resources that are just displacing other contracted resources in certain hours, those benefits aren’t going to materialize in terms of meeting the carbon goals … and be reflecting that in our procurements.”

NEECE conference - discussing the impact of renewables targets and public policy on power markets

Michelle Morin | © RTO Insider

Many stakeholders are not that familiar with the technical aspects of offshore wind, so it’s important to have someone who can bridge that knowledge gap, said Michelle Morin, chief of the environment branch in the U.S. Bureau of Ocean Energy Management’s Office of Renewable Energy Programs.

“For example — the [OSW transmission] cable landfall. I get a lot of concerns that [it] will industrialize an area, so showing people what that will look like goes a long way,” Morin said.

The region’s switch from fossil fuels to wind, solar and storage is being driven by customer demand for cleaner energy, falling costs of new technologies and public policy, said Marc Montalvo, president of Daymark Energy Advisors.

“And the policy interests have many dimensions, like protecting the environment, building strong neighborhoods and communities, making sure the economy is robust,” Montalvo said. “It’s really interesting that we’re talking now about harmonizing markets and public policy, when the wholesale markets that we have in the region, and the way they’re organized, are themselves a response to public policy.”

Out of Market

Markets are very product-specific, and until recently the social science of economics was treated almost like a hard science, which created pejorative assumptions about what constitutes out-of-market actions or mechanisms, said Theodore Paradise, counsel and senior vice president for transmission developer Anbaric.

“Certain orders of market constructs have been protected because people thought that’s what they should do,” Paradise said. “But I think, again, not in 2030 but now, that we’re at the end of that paradigm. At this point, buyers are being told they can’t purchase what they want.

“And this is the proof that the bigger buyers and sellers that are outside this smaller market are really a market, because what do buyers do in a market when they’re being told you can’t buy that?” he said. “They go buy it elsewhere, and that’s what has happened.”

Paradise said the region has arrived at the point where buyers are making direct contracts for resources.

“It’s being conducted in a space that’s not out-of-market; it’s just a different market,” he said.

In addition to competitive contracts for resources, there will continue to be system dispatch, but buyers and sellers are having an impact there, too, he said.

“In the not-too-distant future, we’ll see a New England that has satellite control centers around the region that will become something more like distribution system operators … dispatching based on price, with a grid operator at the transmission level … to make that all work at the higher voltages,” Paradise said.

From a utility perspective, Avangrid’s vision would be to serve as the distribution system platform provider, or the smart integrator, said Rita King, senior director of smart grids innovation for Avangrid Networks.

“The smart integrator role really supports public policy and the region’s targets for climate change and deployment of clean energy,” King said.

David Ismay, a senior attorney with the Conservation Law Foundation, envisioned “an increasingly clean energy market” in 2030 run by Connecticut, Massachusetts and Rhode Island “with a seven-year price lock sufficient to mobilize capital for a range of zero-marginal-cost generators.”

Pentti Aalto of PJA Energy Systems Design asked, “Who is the customer? Is the state or the commonwealth the customer, and I’m just the bill payer? What happens if I find a cheaper way to get power and you’ve already contracted for me?”

Public policy resource choices are made by elected officials, so people can vote them out of office if they disapprove, Paradise said.

Greener Cities

Day Pitney attorney Alex Judd highlighted the increasing incidence of billion-dollar storms in the U.S. — in the Northeast in particular — and noted that the Boston Planning and Development Agency last year released the Imagine Boston 2030 initiative focused on climate change, the first citywide plan in 50 years. (See “Climate Change is Here,” Overheard at NECA Environmental Conference 2018.)

“However we get to carbon neutrality, efficiency is going to be very important, because whatever renewables you’re substituting for fossil [fuels], you lower the total needed,” said Rick Malmstrom, senior energy manager for the Dana-Farber Cancer Institute in Boston.

Malmstrom pointed to another influential initiative coming out of Boston: the 2013 Building Energy Reporting and Disclosure Ordinance (BERDO), which mandated that any building more than 50,000 square feet must report all its energy usage.

“They do have the ability to fine, but they do not want to do that,” he said. “They want to help all building stock get to that kind of reduction [15% energy consumption cut over five years], so now they’re exploring pathways to compliance, such as requiring energy audits be performed, etc.”

Aimee Chambers, director of planning for the city of Hartford, said the city represents “a great example of being able to integrate energy into its large-scale decision-making” through a zoning overhaul and related planning processes.

“The city was most surprised to learn that people … really care about affecting the environment,” she said. “We’ve incorporated a lot into the [building] code with relation to energy. Our code offers density bonuses if buildings use renewable energy or co-generation.”

Hartford also allows building-mounted solar and wind “everywhere, and for those who produce big energy, we allow large-scale wind along our highways, and we also would welcome solar parking canopy development,” Chambers said, adding that the city requires electric vehicle charging stations for lots with space for 35 cars or more.

Louise Yeung, energy portfolio manager for the New York City Economic Development Corp. (EDC), highlighted the value of leveraging a large real estate portfolio, which in her case is 62 million square feet.

“Part of our goal is to generate income for the city to fund other programs and functions, but we also want to make sure we are doing this with clear policy objectives in mind,” Yeung said. “Sometimes those are jobs. In my portfolio’s case, we are looking at emissions reductions and looking at how energy investments can support broader climate targets.”

Most of the EDC’s income comes from leasing, so hosting on-site renewables or generation is a way to diversify the revenue stream and realize the full potential of the assets, she said.

Nithya Sowrirajan, director of global product solutions for Google, showed how her company is using geospatial data and technology to help cities track their carbon emissions and improve their planning abilities.

“San Jose, Calif., was able to look at solar potential for their city as seen today in Google’s Environment Insights Explorer and see that their roofs had [potential] capacity of 4 GW, and thus confidently set a target to be the first 1-GW solar city,” Sowrirajan said. “We started with a small set of cities to pilot our platform, which of course is easier to do in our backyard in California. But as a proud New Yorker, I’m excited to be here alongside fellow panelists from New York City and Hartford to speak about smart cities and to see how we can drive partnerships farther on the East Coast.”