FERC Denies Louisiana PSC Clarification on Entergy ROEs

By Tom Kleckner

FERC last week denied the Louisiana Public Service Commission’s request for clarification on one matter related to a sprawling Entergy-related case before the federal commission.

The PSC was seeking to learn what specific proceeding would determine the return on equity that would apply to amended power purchase agreements that were the subject of an August 2016 order (ER16-1251). It requested the clarification following a January 2017 FERC order denying its request for a rehearing of the 2016 ruling. FERC had said the proceeding regarding the amended PPAs was not the right forum for determining the appropriate ROEs to be applied under a replacement tariff, finding the issues raised by Louisiana regulators to be outside its scope.

The PSC said “that if the appropriate ROE … is outside the scope of the instant proceeding, it does not appear the ROE will be addressed in any [FERC] proceeding.”

In its Jan. 18 ruling, FERC told the PSC it had explained in the 2016 order that issues concerning the application of ROE under Entergy’s unit power sales and PPAs are pending in the massive ER13-1508 docket. FERC also noted that it had already dismissed concerns by the PSC about applying a generic ROE to the amended PPAs.

FERC LPSC Entergy Power Purchase Agreements PPAs
MISO North and MISO South | MISO

FERC last week also approved an uncontested partial settlement related to adjustments in MISO Tariff transmission formula rate templates for Entergy’s operating companies (ER17-2579), directing the company to file a revised rate template in eTariff and terminating four related dockets (ER17-2579, ER16-1528, ER15-1453 and ER15-1436).

Entergy Services had objected to FERC trial staff’s October 2017 recommendation that it file a revised rate template for Entergy Gulf States Louisiana, but a settlement judge in November certified the partial settlement as uncontested.

The settlement memorializes adjustments to three items in the Entergy operating companies’ rate templates: excess accumulated deferred income taxes; certain permanent differences in income taxes; and the Entergy operating companies’ post-retirement benefit costs other than pensions for 2014 and 2015.

FERC Denies New England Tx Owners ROE Rehearing

By Michael Kuser

FERC on Thursday denied requests by New England transmission owners and the Edison Electric Institute for rehearing of its September 2016 ruling regarding complaints over the TOs’ base return on equity.

Since September 2011, numerous parties have filed complaints seeking reductions in the New England TOs’ base ROE.

The commission’s 2016 order established hearing and settlement judge procedures and a refund effective date for a complaint filed by an ad hoc group of municipal utilities, Eastern Massachusetts Consumers-Owned Systems, which contended that the New England TOs’ 10.57% base ROE (11.74% including incentives) should be reduced to 8.78% and 11.38%, respectively.

iso-ne roe return on equity
| ISO-NE

The commission’s Jan. 18 order rejected every argument made by the TOs, saying it “has repeatedly rejected the assertion that every ROE within the zone of reasonableness must be treated as an equally just and reasonable ROE in [a Federal Power Act] Section 206 proceeding” (EL16-64-001).

FERC in October rejected a bid by the TOs to increase their ROEs to the levels before they were lowered by a 2014 commission order vacated by an appellate court in April 2017. The commission said it would address the actual rate in a later remand order (ER15-414, EL11-66). (See FERC Rejects New England Tx Owners on ROE.)

The TOs also argued that constant litigation over the ROEs introduces risk and uncertainty in the ratemaking process.

They contended that the 15-month refund limitation in Section 206, as amended by the 1988 Regulatory Fairness Act, requires the commission to deny a complaint when a similar complaint is already pending.

“While Congress’ adoption of a 15-month refund limitation in the Regulatory Fairness Act gave public utilities some rate certainty in FPA Section 206 proceedings, the New England TOs misinterpret the level of certainty that Congress provided,” the commission said.

Following such logic “would prohibit any party from challenging a utility’s ROE as long as there is another complaint involving that utility’s ROE pending before [FERC], the commission said. “The language of FPA Section 206 does not support such a finding.”

The commission also rejected the TOs’ assertion that it had ignored “countervailing evidence regarding the cost of equity capital and the fact that the capital markets continue to remain unusual,” insisting it “had reviewed the pleadings and evidence submitted by all parties and found that the evidence raises issues of material fact that could not be resolved based upon the record before the commission. The hearing and settlement judge procedures established in the September 2016 order are the product of that review and are the appropriate vehicle to resolve the dispute.”

FERC Denies Bear Swamp Waiver on Affiliate Info

FERC on Thursday denied Bear Swamp Power’s request for a waiver of the requirement to include certain affiliate information in its market-based rate filings (ER17-603).

Bear Swamp, which is controlled by Brookfield Renewable Energy Group, operates the 600-MW Bear Swamp Pumped Storage Development and the 10-MW Fife Brook Development on the Deerfield River in northwestern Massachusetts.

Bear Swamp Project Map | Brookfield

In December 2016, the company filed a notice of change in status, reporting that Nova Scotia-based Emera had acquired an indirect 50% ownership in the company. Bear Swamp requested a waiver of the requirement to include Emera generation and transmission assets in its change-in-status notice and future market-based rate filings.

The company argued that Emera’s affiliates should not be included in its horizontal market power analysis and other filings because its generation capacity is fully attributed to Brookfield, and Brookfield is not privy to Emera’s acquisition activities. Emera affiliates include Emera Maine and Tampa Electric.

Bear Swamp Reservoirs | Google Maps

“Bear Swamp has not presented any compelling reason for its request,” the commission said in its Jan. 18 order. “The facts that Brookfield and its affiliates are not privy to the acquisition activities of Emera and its affiliates, and that a Brookfield affiliate controls day-to-day operations of Bear Swamp’s generation facility, [do] not affect the affiliate relationship between Emera and Bear Swamp.”

The commission directed the company to submit an updated market power analysis including Emera affiliates within 30 days.

Under FERC’s market-based rate regulations, any company controlling 10% or more of another company is considered an affiliate.

— Michael Kuser

FERC Nixes SMECO Request to Pre-empt Md. Solar Rules

FERC last week denied a request by Southern Maryland Electric Cooperative (SMECO) to rehear a petition asking it to rule that Maryland Public Service Commission regulations on acquiring power from community solar facilities run afoul of the federal Public Utility Regulatory Policies Act (EL16-107).

FERC SMECO solar maryland
Centreville, Maryland Solar Array | Paradise Energy Solutions

SMECO and Choptank Electric Cooperative had asked FERC in 2016 to issue a declaratory order that the PSC’s rules covering from which facilities and at what price state utilities must buy solar is pre-empted by PURPA. FERC declined at the time, arguing that the action was premature because the program was voluntary and neither cooperative had indicated it planned to enter into the program.

The cooperatives in December 2016 then asked the commission to grant a rehearing of the request or otherwise clarify that the ruling was without prejudice so that they could bring their complaint again if the PSC failed to address their concerns. They also requested that the filing fee be waived the second time around. Last October, SMECO filed a motion to supplement the record to include a proposed solar tariff it had filed with the PSC, along with the PSC’s recommendations in response and subsequent letter denying the proposal.

FERC SMECO solar maryland
Hebron, Maryland Solar Array | Paradise Energy Solutions

SMECO argued this showed its intent to enter into the program and that it had exhausted all of its state law remedies, but FERC was not persuaded.

“SMECO’s motion does not allege any change to the facts relied upon by the commission in dismissing the petition, particularly, that the community solar systems program remains voluntary and that SMECO is not subject to the program’s regulations,” the commission wrote in denying the rehearing.

The order did clarify that the denial was without prejudice but did not waive the filing fee. Commissioner Robert Powelson didn’t participate in the order.

— Rory D. Sweeney

‘Creative’ Settlement Approved in VEPCO Revenue Spat

By Rory D. Sweeney

Despite complaints from PJM’s Independent Market Monitor, FERC last week approved a settlement in a yearslong fight over how much revenue Virginia Electric and Power Co. should receive for its reactive energy supply fleet.

FERC VEPCO reactive energy
Bowring | © RTO Insider

The commission’s ruling said “the IMM’s concerns are too attenuated to outweigh the bargained-for benefits of the settlement, which include rate certainty and reduced litigation costs” (EL16-89, EL17-40, ER06-554, ER17-512).

The settlement between VEPCO, North Carolina Electric Membership Corp., Old Dominion Electric Cooperative and Northern Virginia Electric Cooperative came after FERC initiated a review in July 2016 of VEPCO’s rates for reactive services under Section 206 of the Federal Power Act.

The settlement maintains VEPCO’s fleetwide annual revenue requirement of $27.5 million but maintains a list compiling the revenue requirements for each generating unit totaling nearly $40 million. When VEPCO files to retire a unit, it will remove the unit’s associated revenue from the compiled list. However, its fleetwide revenue requirement will remain the same, and the other parties agreed not to contest the filing until the compiled list totals less than $27.5 million.

The Monitor argued that VEPCO, a Dominion Energy subsidiary, should have to itemize how much of the $27.5 million is attributable to individual units each year. The Monitor said the information would help with calculating several of the plants’ market positions, including their cost-based offers, but FERC dismissed the requests.

In a separate case, FERC also approved a settlement in the reactive rate requirements for Talen Energy’s West Deptford facility (EL16-100, ER14-1193).

MISO Readies Retirement Change

By Amanda Durish Cook

CARMEL, Ind. — MISO is close to completing a plan that would give generators three years to submit a decision to retire after signaling their intention, but some stakeholders think the changes could allow unit owners to “game the system” for allocating transmission costs.

MISO FERC generator retirements
Joe Reddoch | © RTO Insider

Joe Reddoch of MISO’s retirement planning group said the proposal — slated for a March filing with FERC — will close out a longtime recommendation from the Independent Market Monitor to allow generators to time their retirements according to Planning Resource Auction timelines.

Under the proposal, generation owners considering or planning a shutdown will still submit an Attachment Y notice to MISO, but the RTO will now treat all such notices as a request for suspension. Owners would no longer have to decide between a permanent retirement and a temporary shutdown with an estimated return-to-service date.

Instead, they would have three full planning years to prepare a return to service or decide to make the suspension permanent, providing additional time to decide whether to participate in the capacity auction. Suspended generators would lose interconnection service after three planning years if they don’t resume operations.

“By removing the return date [requirement], we can actually consider them in our planning processes,” Reddoch said during a Jan. 17 Planning Advisory Committee meeting.

Reddoch said MISO plans to continue its practice of passing pro rata transmission upgrade costs needed to maintain baseline reliability to unit owners who rescind their decision to retire.

Wind on the Wires’ Natalie McIntire pointed out that unit owners cause unnecessary costs for new interconnection customers by deciding to suspend and then come back online after an interconnection customer has shouldered the entire cost of interconnecting to make up for the lost generation.

“We have concerns about this,” McIntire said. “This treatment sort of creates an opportunity to game the system.”

“They could play games right now, but they don’t. They’re simply looking at the viability of their assets,” Reddoch said. “Right now, we create a false sense of security by modeling their return date when most of them never return.”

Reddoch said the proposal will not require changes to the planning process, as planning models already assume all retiring and formerly suspended units will be offline within 36 months. MISO last year deferred the proposal while it looked into possible modeling implications stemming from the change. (See MISO Defers Retirement Process Changes.)

MISO Director of Planning Jeff Webb said the plan improves the auction because owners uncertain about retiring a generator can still choose to participate in auctions, but the RTO’s Interconnection Planning Task Force could still explore the possibility that interconnection customers could be left holding the tab on an ultimately ineffectual network upgrade.

Other stakeholders said generation owners could potentially game the system by vacillating in and out of three-year suspensions. Reddoch pointed out that MISO’s Tariff limits total suspension times to three years in a five-year period.

FERC Rejects Challenge to PJM CP Rules on Coal Plants

By Rich Heidorn Jr.

FERC on Thursday rejected an Illinois Municipal Electric Agency challenge to PJM’s Capacity Performance rules for coal plants, saying it had dealt with IMEA’s concerns in its June 2015 order approving the program (ER15-623-010, et al.).

IMEA asked for rehearing on two aspects of the commission’s May 2016 follow-up CP order on compliance, arguing that the order will “unduly disadvantage coal-fired generation owners like IMEA who separately bid in their minimal level of output and megawatts,” according to FERC’s summary.

PJM Capacity Performance CP IMEA
IMEA owns 12% of LG&E and KU’s Trimble County 1, a 514-MW coal-fired unit between Louisville and Cincinnati. | LG&E-KU

Created in 1984, IMEA comprises 32 municipal electric systems and one cooperative in Illinois. It owns a 15% stake in two 800-MW supercritical units at the Prairie State Generating Co. in Southern Illinois, and 12% of Trimble County 1 (a 514-MW coal-fired unit) and Trimble County 2 (a 750-MW super-critical, pulverized coal-fired unit) located between Louisville and Cincinnati.

Nonperformance Charge Exemption

IMEA said FERC should have approved PJM’s compliance filing — a response to the June 2015 order — proposing to exempt generators from nonperformance charges “if the relevant resource is not scheduled by PJM, or is online but scheduled down, subject to a determination by PJM that such an action is appropriate” under its economic dispatch.

The agency said the May 2016 order was thus inconsistent with commission precedent recognizing the longer ramp-time needs of coal units.

But FERC ruled that “IMEA effectively seeks rehearing of the initial June 2015 order, not the May 2016 order.”

“Having failed to seek rehearing of the June 2015 order on this issue, IMEA may not raise these issues on rehearing of the May 2016 order addressing PJM’s compliance filing,” the commission said.

Operating Parameter Constraints

PJM IMEA Capacity Performance CP
IMEA Members | IMEA

The commission also rejected IMEA’s argument that PJM’s compliance proposal on operating parameter constraints failed to provide sufficient specificity or transparency.

IMEA said “it is critical that PJM be required to explicitly document the specific operating limitations it will impose on a given resource and the reasons justifying those limitations,” FERC explained.

In response, the commission reiterated its May 2016 order, finding that PJM’s provision of timelines and details specifying how the RTO will implement its process for reviewing unit-specific parameter limited schedules is sufficient.

The commission cited “provisions of PJM’s Tariff allowing for an annual review of unit-specific parameter limitations and a case-by-case procedure through which a resource can justify operating outside of its unit-specific parameters for purposes of receiving make-whole payments. The May 2016 order further interpreted PJM’s obligation to notify a seller in writing regarding PJM’s determination as a commitment to provide sufficient detail regarding its determination.”

Chairman Kevin McIntyre and Commissioner Robert Powelson did not participate in the ruling.

FERC Sides with Incumbent TOs; OKs Limits on Competition

By Rory D. Sweeney

In a win for PJM’s incumbent transmission owners, FERC ruled Thursday that transmission projects driven by TOs’ individual planning criteria are exempt from competitive bidding.

It also ruled against a competitive transmission developer’s request to allow bidding on some immediate-need projects (ER16-2401, EL16-96).

FERC transmission owner planning criteria
| © RTO Insider

The order approved Tariff and Operating Agreement revisions PJM proposed in response to FERC’s July 2016 show cause order initiating a Section 206 proceeding over inconsistencies in the OA. (See FERC Rejects PJM Cost Allocation on Dominion Project.)

PJM made revisions suggested by the commission to clarify that projects driven solely by a TO’s Form 715 local planning criteria are not subject to PJM’s competitive process because all the costs are allocated to the zone of the TO. PJM’s competitive process is limited to regionally allocated projects.

In the revisions, PJM also said it will identify local planning criteria transmission needs at the monthly Transmission Expansion Advisory Committee meetings so stakeholders can review and comment on them. The RTO will present its solutions to the issues, identifying applicable criteria, the project’s zone, alternatives it considered and an explanation of the decision to assign the project to the incumbent TO.

LSP Challenge

LSP Transmission, an LS Power subsidiary, challenged both the 206 proceeding and PJM’s filing in response. It said the RTO’s proposed revisions stifle competition and overlap with issues outstanding in other dockets, including a request for rehearing on an order that Form 715 projects aren’t eligible for regional cost allocation (ER15-1387). It also cited a show cause order in August 2016 questioning whether PJM TOs’ procedures for planning supplemental projects provided stakeholders opportunity for “early and meaningful input and participation,” as required by Order 890 (EL16-71).

Neither has been decided. In December 2016, the commission did reiterate an earlier ruling that Form 715 projects are not eligible for regional cost allocation. (See FERC Rejects Challenges on Local Tx Cost Allocations.)

Defining ‘Immediate Need’

LSP also argued that FERC “got it backwards” in directing PJM to clarify the three-year threshold for immediate-need reliability projects. LSP said immediate-need projects should only be exempt from competition if the in-service date of a solution is within three years, rather than also exempting those with a need date within that period.

PJM responded that it “makes no sense” to delay a project that cannot be built within three years to conduct bidding.

FERC agreed, saying, “The fact that it may take longer than three years to build a solution to an immediate reliability need is not a persuasive justification for potentially further delaying the solution.”

RTEP Approvals

In a related order, FERC on Thursday confirmed its approval of PJM’s cost allocations for projects added to its Regional Transmission Expansion Plan in March 2017 (ER17-1236). Commission staff had approved the allocation tentatively in June 2017 while the commission was without a quorum.

FERC denied a protest and request for rehearing from Dominion Energy, which had argued it shouldn’t be allocated all costs for two 500-kV facilities in its zone to address its Form 715 criteria. Dominion is appealing the order that allocated all Form 715 project costs to zones in which the criteria apply (ER15-1387).

Commissioner Cheryl LaFleur issued a separate concurrence, pointing out that she had dissented on the order Dominion is appealing.

“As explained in that dissent, I believe the commission should have retained regional cost allocation for transmission projects that are double-circuit 345 kV and 500 kV and above,” she wrote.

FERC Backs NERC Supply Chain Standards

By Michael Brooks

WASHINGTON — FERC on Thursday proposed to adopt several reliability standards intended to mitigate cybersecurity risks posed by the global supply chain of grid operation tools.

Multiple entities around the world may participate in the development of software or technology used by utilities to manage their reliability duties, exposing them to potential corruption.

FERC NERC cybersecurity supply chain

In a Notice of Proposed Rulemaking (RM17-13) FERC indicated its intention to approve a NERC critical infrastructure protection standard (CIP-013-1) that would require utilities to consider several cybersecurity issues when procuring these products for their medium- and high-impact systems. These issues include:

  • disclosure of known vulnerabilities in the products;
  • security event notifications;
  • coordination of vendor remote access;
  • notification when vendor employee remote or onsite access is terminated;
  • coordinated response to vendor-related cybersecurity incidents; and
  • verification of integrity and authenticity of all software and patches.

NERC noted that the standard does not “require that every contract with a vendor include provisions for each of the listed items.” Rather, utilities would need to “ensure that these security items are an integrated part of procurement activities, such as a request for proposal or in the contract negotiation process.”

The actual terms and conditions of utilities’ contracts with vendors are outside the scope of the standard, as are the activities of the vendors themselves. “A responsible entity should not be held responsible under the proposed reliability standard for actions (or inactions) of the vendor,” NERC said.

Reliability officials would evaluate and reapprove utilities’ procurement processes every 15 months under the standard.

FERC also proposed to adopt two additions to existing NERC standards, both to support the requirements in CIP-013-1. One (CIP-005-6) would require utilities to develop a method for identifying active remote access sessions by vendors. The other (CIP-10-3) would require utilities to verify the source of all software and patches before installing them.

Broader Scope, Tighter Deadline

NERC developed the standards in response to a FERC directive in July 2016, marking only the third time the commission has taken such initiative. (See FERC Orders NERC to Develop ‘Flexible’ Supply Chain Standard.) The organization submitted the proposed standards last September.

FERC found that NERC had generally satisfied the four objectives it had laid out in its order: software integrity and authenticity; vendor remote access; information system planning; and vendor risk management and procurement controls. The commission had also directed that the standard be flexible, leaving it to utilities to determine the best way to comply.

However, the commission directed NERC to include Electronic Access Control and Monitoring Systems (EACMS) — firewalls, authentication servers, security event monitoring systems and intrusion detection systems, for example — as part of the scope of the standard.

It also instructed NERC to evaluate the risks posed by Physical Access Control Systems (PACS) — such as motion sensors, badge readers and electronic locks — and Protected Cyber Assets (PCAs) — networked printers, file transfer servers and local area network switches — as part of a supply chain cybersecurity study the organization’s Board of Trustees ordered last August.

FERC also proposed to tighten the implementation deadline for the standards, shortening NERC’s proposed 18 months after commission approval to 12.

Commissioners: Good First Step

Commissioner Cheryl LaFleur, who had dissented from FERC’s earlier order, issued a lengthy concurrence to explain her vote. She had called the July 2016 directive too broad and lacking in guidance. She had also said the timeline for developing the standards was too short given the lack of stakeholder input.

At the commission’s open meeting Thursday, LaFleur said she still had some of those concerns, calling the standards “quite general.” But, she said, “I agree that they are an improvement over the status quo.

“I do not believe that remanding these standards or the larger supply chain issue to the NERC standards process would be a prudent step at this point,” she said. “Rather, I believe the better course of action at this time is to move forward with these standards and … improve them over time as needed.”

Her colleagues had similar sentiments.

“While the standard is not a panacea, it is an important step forward to tackle a tough problem,” Commissioner Neil Chatterjee said. “It will be particularly important to revisit the standard after several years of experience to see what is working and what aspects could be improved. But again, today’s order is a good step in the right direction.”

Commissioner Richard Glick also called the standards “an important first step,” but “I think more needs to be done.”

Comments on the proposal to adopt the standards are due 60 days after its publication in the Federal Register.

EOP Reliability Standards

FERC on Thursday also approved several updates to emergency preparedness and operations reliability standards proposed by NERC last March (RM17-12).

The revisions streamline existing standards and remove redundant language. The commission said they will ensure accurate reporting of events to NERC’s event analysis group; delineate the roles and responsibilities of entities involved in system restoration processes; and identify the elements required in plans for continuing operations when primary control functionality is lost.

FERC did not make any changes to the EOP standards since it proposed to adopt them last September, nor did stakeholders propose any. (See FERC OKs Rules on Balancing, Interconnection, Remedial Actions.) They will go into effect 60 days after their publication in the Federal Register.

FERC Denies FirstLight Hydro Capacity Change

By Michael Kuser

FERC on Thursday denied FirstLight Hydro Generating’s request to change reservoir levels this winter at a Massachusetts hydroelectric plant, citing inadequate time to assess the impact on the endangered shortnose sturgeon (P-2485-076).

FERC
Shortnose Sturgeon

FirstLight requested the temporary amendment to increase operational flexibility at its 1,167-MW Northfield Mountain Project in anticipation of potential reliability challenges in New England this winter. ISO-NE supported the request but did not say the extra capacity would be critical to reliability.

FERC sympathized with FirstLight’s intentions, but ultimately sided with the shortnose.

“While we are very sensitive to the need to take all feasible steps to ensure the reliability of the electric grid, and accordingly have approved previous amendment requests by FirstLight, the presence of an endangered species in the project reservoir that may be affected by the amendment is a significant new circumstance,” the commission said. “We could not lawfully approve the current amendment before completing consultation with the [National Marine Fisheries Service], a process that would require the gathering of information, followed by NMFS review and action.”

In comments filed with FERC last October, NMFS indicated the sturgeon had been found in Northfield Mountain’s lower reservoir, which was historically above the recognized upstream extent of the species’ range.

The commission ordered that “any future proposal of a similar nature should be filed a sufficient time before the winter season such that any necessary efforts with respect to [Endangered Species Act] consultation can be completed in a timely manner.”

Under federal regulations, NMFS has 135 days to complete a consultation. The commission said that “it did not appear possible” that the consultation process could be completed before March 31, the end of the period for which FirstLight requested the temporary amendment.

Technical Limits

FirstLight proposed reducing Northfield Mountain’s minimum reservoir elevation from 938 mean sea level (msl) feet to 920, and bumping up the maximum from 1,000.5 msl feet to 1,004.5, increasing the potential operating range from 62.5 feet to 84.5 and available storage from 12,318 acre-feet to 15,327. The company also sought unrestricted use of the extra capacity.

According to FirstLight, the additional 3,009 acre-feet of storage would increase the facility’s maximum daily generation by 2,050 MWh, or an additional 1.8 hours of generation at full load. Within current limits, it is capable of generating 8,729 MWh/day during peak load conditions.

But FERC signaled that it would seek limits on the flexibility offered by the adjustments. In its decision, the commission ordered that “any future proposal should be restricted to use during ISO-NE discretionary actions taken during emergency operations … unless FirstLight can provide sufficient evidence why a broader amendment is appropriate.”

The commission has previously granted six temporary amendments for the facility. The first three allowed FirstLight to modify operations only when ISO- NE declared an energy emergency, triggered by a forecast showing electric demand could exceed capacity reserves. The fourth and fifth did not restrict FirstLight’s use of the additional storage, but the sixth, most recent amendment also restricted the use of the additional storage to declared emergencies.

FERC Northfield Mountain FirstLight Hydro
Connecticut River at Turners Falls

Northfield Mountain includes an upper reservoir, an underground powerhouse containing four reversible pump-turbine generators and an intake/outlet structure in the Turners Falls reservoir. The 22-mile-long reservoir on the Connecticut River serves both Northfield Mountain and the Turners Falls Hydroelectric Project, for which FirstLight also holds the license.

FERC Northfield Mountain FirstLight Hydro
Northfield Mountain Environmental Impact Study | FirstLight Hydro

Northfield Mountain, Turners Falls and three other hydroelectric facilities directly upstream are all currently undergoing relicensing. As part of that process, the licensees are required to conduct studies for the five facilities to analyze interrelationships in project operations and environmental effects.