By Rory Sweeney
AUSTIN, Texas — More than three years after it was initially conceived, a short but expensive transmission line to address expected growth in the suburban areas of Denton County, Texas, finally received state regulatory approval last week.
The Public Utility Commission approved a somewhat unusual “settlement stipulation” that committed the City of Frisco to paying more than half of the bill for a hybrid above/below-ground route. The 2.9-mile 138-kV project, which received more than 3,000 comments in protest of various above-ground proposed alternatives, was approved with the stipulation that more than 90% of it be installed underground. Built and operated by the Brazos Electric Power Cooperative, the line will run west along Frisco’s Main Street from an existing Oncor line tap to a new Stonebrook substation.
Based on its projected $24.5 million cost, the commissioners were reticent to approve the more expensive burying options, but they relented because Frisco agreed to pay more than $12 million to get its specified, mostly underground option approved. The agreement will allow the line to be laid underground as part of a widening and water line installation project the city had already planned for the street.
Combined with the existing $6 million cost credit for the route the PUC had been prepared to approve, Brazos will be able to recoup $12 million through transmission cost of service recovery. Should Frisco fail to make its payments, the agreement allows Brazos to revert to the all-overhead route.
State Sen. Jane Nelson, who represents the area as the state’s highest-ranking Republican, wrote a letter to the PUC in support of the agreement, saying there were few other viable options because both the Texas Department of Transportation and the U.S. Army Corps of Engineers denied use of their land. Overhead lines would have eventually conflicted with infrastructure needs for street widening and water lines, she said.
She also applauded Frisco for contributing more than 50% of the total cost and more than 67% of the incremental cost to bury the lines. The commissioners joined Nelson is noting that Frisco’s commitment is “far exceeding” that of other municipalities in similar situations.
The additional costs still didn’t sit well with commissioners, despite arguments that it was a better plan for expected future growth. “I have concerns with uplifting any underground costs to ratepayers,” Commissioner Brandy Marty Marquez said.
“There’s a heavy burden to prove that the undergrounding needs to take place because it’s so much more expensive than placing the lines above ground,” Commission Chairman Donna L. Nelson said at last week’s meeting.
But they had also heard from many citizens near the route, who had organized themselves into a group called Bury the Lines. The city acknowledged that the above-ground routes were “universally opposed” by the community.
The agreement requires that Frisco have its widening and water line project awarded within 15 months of the PUC’s final order.

Enel Green Power North America has begun building the 150-MW Lindahl wind project in North Dakota. The project is designed to generate about 625 GWh annually to meet the electricity needs of more than 50,000 households.
Renewable Energy Systems is considering a 121-turbine, 150-MW wind energy project on the Michigan Upper Peninsula that would be roughly five times larger than the only wind farm on the peninsula, according to documents obtained by Midwest Energy News using a Freedom of Information Act request.
Opponents to a Duke Energy plan to build a $750 million natural gas-fired plant near Asheville are asking an appeals court to waive a requirement that they post a $10 million bond if they appeal regulators’ approval of the project.
DTE Energy has opened a facility in Bad Axe, Mich., that will serve as an operations center for its renewable energy operations.
A plan by Puget Sound Energy to buy back bonds at a discounted rate isn’t going over well with some of the bond’s owners, who say they deserve better terms. Puget Sound wants to retire $250 million in 6.974% bonds that aren’t due until 2067 as a way to lighten its balance sheet.











The current grid was based on utilities earning returns on investments in large, centralized power systems sized to meet peak electric demand that occurs only a few days each year, “an energy and financially inefficient system,” the commission said in announcing the order.
The National Academies of Sciences, Engineering and Medicine is calling for better fire prevention, more stringent anti-terrorist protections and better disaster preparedness at the nation’s sites for storing spent nuclear fuel.
A 22-year-old hose linking a storage tank to a pump leading to an emergency generator failed during an inspection earlier this year at Exelon’s aging Oyster Creek Nuclear Generating Station in New Jersey, leading the Nuclear Regulatory Commission to assess the plant with a “white” finding.
The Nuclear Regulatory Commission and the operator of the Palisades nuclear plant in Michigan have reached a settlement concerning a leak that allowed 80 gallons of radioactive water to escape into Lake Michigan in 2011. Instead of a fine, the commission said it is satisfied with Entergy’s decision to take corrective actions to ensure a leak does not happen again.
EPA issued a draft water use permit for Entergy’s Pilgrim nuclear generating station, updating a permit that was first issued in 1991. Although opponents of the plant have long argued that the water use permit expired in 1996, the agency said regulations allow the plant to use the original permit until a new one is issued.