ERCOT’s Board of Directors has approved staff’s proposed 765-kV Eastern Backbone project and its $9.4 billion capital cost price tag, making it the most expensive project in the grid operator’s history.
The 1,100-mile project, a subset of the 2024 765-kV Strategic Transmission Expansion Plan (STEP), will address Texas’ significant load growth and reliability needs, ERCOT said. Much of that demand is driven by more than 233 GW of interconnection requests by data centers, cryptocurrency miners and other large loads, and the electrification of the state’s oil and gas industry.
“We see the need for this infrastructure to be able to reliably serve the future demand on the system,” Kristi Hobbs, vice president of system planning and weatherization, told the board during its Dec. 8-9 meeting.
Incumbent transmission providers American Electric Power — an industry leader in building and operating 765-kV lines since the 1960s — CenterPoint Energy, CPS Energy and Oncor will build the project’s seven segments of extra-high-voltage transmission lines, four 765-kV substations, 11 765/345-kV transformers, and 69 765- or 345-kV circuit breakers.
The result will be a rectangular network from Northeast Texas down to the Coastal Bend in the South and connecting to 765-kV circuits into the petroleum-rich Permian Basin.
Hobbs said recent transmission plans have indicated a need to incorporate 765-kV facilities in meeting staggering demand increases.
“We realized we cannot keep planning the system the way we always had,” she said.
The new approach won’t come cheaply. ERCOT’s 2024 345-kV Regional Transmission Plan and the 765-kV STEP both expect about $5 billion per year of investment over a six-year planning horizon. Staff say a 765-kV network will enable power to flow more efficiently through long-distance transmission to urban load centers.
Hobbs and Thomas Gleeson, chair of the Texas Public Utility Commission, both assured questioning board members that their respective staffs have a firm grip on escalating costs. ERCOT used a 20% adder for mileage estimates to account for right-of-way issues, Hobbs said.
Gleeson told the board he joined the PUC as staff during the Competitive Renewable Energy Zone process, which was completed in 2014 at a cost of $6.9 billion, $2 billion over projections. However, the project resulted in 3,600 miles of 345-kV CREZ lines that freed up over 23 GW of wind capacity in West Texas.
“I’m very aware of the public’s desire to know cost overruns if schedule slips,” he said. “I think it’s important, given the magnitude of this and the cost, that we are transparent about any cost overruns and slips and schedules. We will do everything we can at the commission to make sure that that information is public so that everyone from the governor to the legislature to the public at large knows what’s going on with this project.”
The board approved two other transmission projects with a combined cost of $852.8 million, pushing the total estimated value of endorsed infrastructure to $10.3 billion:
-
- Oncor and AEP’s proposed 104-mile, single-circuit 765-kV project in West Texas that closes the western end of ERCOT’s EHV backbone. The Drill Hole-Solstice project has a projected capital price tag of $742.2 million.
- Oncor upgrades to a 345/138-kV switch and 9 miles of 138-kV line, and 13 new miles of 345-kV lines in far West Texas. The project has an estimated capital cost of $110.6 million and completion date in December 2026.
The projects were previously endorsed by the Technical Advisory Committee, with only two opposing votes and two abstentions. (See ERCOT Stakeholders Endorse $9.4B 765-kV Build.)
All three projects will require construction permits from the PUC.
Vegas Sets Lofty Goal
CEO Pablo Vegas told the board that ERCOT has updated its vision, mission and core values that see the grid operator as the “most reliable and innovative grid in the world.”
“Not just in Texas, not just in the United States, but in the world,” he said. “We are one [of the best], if not the leading, grids globally when it comes to operational and technical complexities. To be successful, we need to be a clear leader on a stage that represents the entirety of this planet.”
The vision builds on the ERCOT 4.0 construct that Vegas unveiled earlier in 2025. At the time, he said ERCOT 4.0 was a “strategic lens to look at the priorities and the initiatives that we’re going to be investing in to make sure that we continue to deliver on our mission, which is getting more complex and more dynamic every year.” (See ERCOT Board of Directors Briefs: June 23-24, 2025.)
“It represents a transition in our market that is characterized by high and very rapid growth of intermittent and short-duration supply resources,” Vegas told the board Dec. 9. “It’s characterized by a rapidly changing customer base that includes price-responsive loads like cryptominers, rapidly growing large-scale data centers and continued penetration of distributed energy resources. … It represents an opportunity to create a more resilient and cost-effective grid.
“To achieve this vision, we will ensure a reliable grid with competitive and cost-effective electricity markets,” he added.
The board backed up Vegas by approving the refreshed vision, mission and core value statements.
Board Designates Priority Requests
The directors designated a pair of revision requests related to key ERCOT projects in 2026 — dispatchable reliability reserve service and ride-through requirements for inverter-based resources — as board priority requests, giving them urgent status.
NPRR1309 and its associated Nodal Operating Guide revision (NOGRR283) address stakeholder feedback that DRRS procurements be co-optimized with obtaining energy and other ancillary services. The protocol change is the third iteration of DRRS’ design, which began development in 2023 as a subset on non-spinning reserve service. The PUC has set DRRS as a key commission priority.
In designating DRRS as a board priority, the directors also ordered TAC to bring the measures, structured to meet statutory requirements, to the June board meeting for consideration.
ERCOT has withdrawn NPRR1235, which would have developed DRRS as a standalone ancillary service.
The IBR measures granted priority status were NPRR1308 and its associated change to the Nodal Operating Guide, NOGRR282.
NPRR 1308 defines a large electronic load (LEL) as exceeding 75 MW, in which 50% or more of the site’s demand is computational load from a data center or cryptomining facility. NOGRR282 establishes frequency and voltage ride-through requirements for LELs.
Staff said the inability of LELs to ride through disturbances on the grid poses a growing reliability risk for ERCOT. They have identified 26 LEL ride-through events since the beginning of 2023. ERCOT says it is determining whether additional ride-through requirements are needed for other large loads.
Draft CDR Report Released
Hobbs told directors that a draft of the semiannual Capacity, Demand and Reserves (CDR) report has been published for stakeholder comment before its Dec. 19 release.
ERCOT says the draft’s release will help improve the final product’s quality and also strengthen the transparency of the data and associated processing steps. Staff have added additional scenarios that look at the effects of assumptions based off new rules for large-load curtailment and projects approved for Texas Energy Fund loans.
“Getting input from the stakeholders throughout the process has been beneficial,” Hobbs said.
The CDR gives a five-year look ahead at generation that has met certain requirements for connecting to the grid in the future. It also includes forecast demand received from utilities.
The report currently predicts a summer peak load hour of 138 GW and a net peak load hour of 126 GW in 2030. (Net peak load subtracts renewable energy generation.) It also forecasts 60 GW of additional generation by the summer of 2030, with solar and storage accounting for 86% (52.3 GW) of that total.
Real-time Price Correction
The board approved another real-time market price correction with more than $812,000 in impact, representing almost 4% of settlements for the Oct. 14 operating day.
Staff said a software issue led to an “inappropriate” effect on generation dispatch values. The issue was not discovered within the two-business-day deadline, meeting the criteria for a board-approved correction. ERCOT said the software bug’s cause has been identified and a fix deployed.
The board also rubber-stamped three staff recommendations to approve requests from market participants:
-
- BHER Power Resources’ bid for a permanent site-specific exemption from complying with metering protocols by placing it on the combination ballot. The company said its Falcon Seaboard facility in Big Spring was built in such a way that it can’t meet a 500-kW maximum load limit requirement for auxiliary distribution factors. The facility has been operating for 35 years.
- Lamar Electric Cooperative’s request to transfer about 60 MW of peak load from the Rayburn Country Electric Cooperative load zone to the competitive North LZ. The transfer will go into effect January 2030.
- Data center consultant Agentic Infrastructure’s ERCOT membership in 2026. The firm will align itself with the Independent Generator segment.
TAC Reps Set for 2026
The board confirmed TAC’s 30 representatives for 2026, as selected by ERCOT’s corporate members.
The committee will welcome three new members, including AEP’s Erin Rasmussen, who replaces long-time TAC member Richard Ross. The other new members are CenterPoint Energy’s Ebby John and Garland Power & Light’s Curtis Campo.
The directors also approved 11 NPRRs, two NOGRRs, a Planning Guide revision (PGRR) and a system change request (SCR):
-
- NPRR1263: remove the accuracy testing requirements for coupling capacitor voltage transformers.
- NPRR1274: update the estimated capital cost for the tier-classification rules used in the Regional Planning Group (RPG).
- NPRR1280: establish an RPG review process for proposals to permanently bypass an existing series capacitor or un-bypass a series capacitor previously designated as permanently bypassed.
- NPRR1285: expand the current reliability unit commitment opt-out window to incent self-commitment, increasing capacity available to the market at lower expense and reducing RUCs and associated costs.
- NPRR1287: replace the defined term “Maximum Daily Resource Planned Outage Capacity” with “Resource Planned Outage Limit” (RPOL) to align with the actual calculated RPOL; add the maximum duration of a proposed transmission outage with a described lead time to align with current outage-coordination practices; define conditions under which ERCOT can accept an outage request if it could exceed the planned outage limit; and clarify that energy storage resources submit outages.
- NPRR1293: clarify the “Update Network Operations Model Production Environment’s” milestone dates.
- NPRR1294: incorporate the other binding document “Demand Response Data Definitions and Technical Specifications” into the protocols, standardizing the approval process.
- NPRR1298: require comments on proposed rule changes to be delivered to ERCOT within 14 days of the revision request’s posting. Comments posted after the 14-day comment period can be considered at the Protocol Revision Subcommittee’s discretion.
- NPRR1299: clarify and clean up language related to the emergency response service program, including a data file produced at the end of the procurement process using code managed entirely within ERCOT’s Demand Integration group. The file is manually produced and must be posted manually, which is affected by weekends and holidays.
- NPRR1300: implement Senate Bill 1877 by including the Texas Office of Public Utility Counsel as an entity permitted to receive protected information or ERCOT critical energy infrastructure information without violating the protocols.
- NPRR1303: revise language to change the method for submitting and receiving declaration of natural gas pipeline coordination from a physical form to an electronic format.
- NOGRR279: modify the monitoring equipment installation deadlines established by NOGRR255 (High Resolution Data Requirements) to Jan. 1, 2029, consistent with NERC standard PRC-028-01 (Disturbance Monitoring and Reporting Requirements for Inverter-Based Resources), and clarify that synchronized resources with standard generation interconnection agreements executed prior to July 25, 2024, have 12 months after their commercial operations date to comply with the new equipment standards.
- NOGRR280: remove language governing communication path requirements for CREZ circuits and stations.
- PGRR131: implement mandatory reporting requirements for transmission service providers’ and ERCOT’s interconnection-cost reporting, and delete gray-box language superseded by the requirements.
- SCR831: modify the network model management system, operational data management system, topology processor and the modeling-on-demand system to incorporate short-circuit modeling data for maintaining models built by the System Protection Working Group.


