November 1, 2024

Mass. Court Upholds Approval of Controversial Eversource Substation

The Massachusetts Supreme Judicial Court (SJC) on Sept. 11 upheld the Energy Facilities Siting Board’s (EFSB’s) approval of a controversial substation in East Boston, likely concluding the 10-year fight over the project.  

The court ruled that the petitioners, the Conservation Law Foundation (CLF) and GreenRoots, did not meet the heavy burden of proof required to overturn the EFSB’s approval of the project.  

“We conclude that the board’s decision is lawful, was supported by substantial evidence, and was not arbitrary, capricious or otherwise an abuse of the board’s discretion,” the SJC found.  

The project, currently under construction, is sited on the bank of the Chelsea Creek near a public park, homes and a new police station.  

Eversource Energy, the electric distribution company responsible for the project, had argued the substation is needed to meet load growth in the area and preserve electric reliability.  

However, the project was met with significant opposition by residents and environmental advocacy organizations, which argued it will add to the significant burden of pollution already facing the neighborhood. The surrounding area is classified by the state as an environmental justice neighborhood, meeting the definition’s criteria for income, minority population and language isolation.  

In a non-binding 2022 ballot question, 83% of Boston voters opposed the project at the selected site, while politicians including Boston Mayor Michelle Wu (D) and U.S. Sen. Ed Markey (D) have voiced their opposition to the project. 

In challenging the EFSB’s approval, CLF and GreenRoots argued the board did not adequately weigh the project’s environmental burdens with its benefits to the community and said the board improperly pre-empted the review processes of two local agencies. 

The groups also took issue with the substation’s designation as a water-dependent facility when granting its tidelands license.  

The court was not persuaded by these arguments, finding “no error in the board’s considerations of environmental protection, public health and public safety.” 

The project’s opponents expressed disappointment with the court’s ruling, arguing it is a failure to protect residents of the environmental justice neighborhood.  

“East Boston residents endure major pollution and other environmental hazards that threaten their health and safety, and this project was poorly sited in a flood-prone area,” said Anxhela Mile of the Conservation Law Foundation. Mile added that the decision underscores the “need to reform how the commonwealth permits energy infrastructure and assesses the cumulative environmental and health risks a community faces. 

“GreenRoots and the East Boston community affected by the Eversource project are disappointed with the MA SJC’s decision to allow the project to move forward, but honestly we’re not surprised,” said John Walkey of GreenRoots. “The siting and permitting process is broken from any perspective you look at it.” 

He noted that the fight over the substation was an important factor in passing environmental justice protections into state law in 2021, and in centering environmental justice protections in recent efforts to pass permitting reforms in the state.  

“We have also seen Eversource itself change its own approach to engaging communities in their recently proposed substation in the Hyde Park neighborhood in Boston,” Walkey added, noting that the company engaged the community before filing with the EFSB and “brought up the question of Community Benefits Agreements right out of the gate.” 

“However, this is cold comfort for an already environmentally over-burdened East Boston community now saddled with additional poorly and unjustly sited industrial infrastructure,” Walkey said. 

Eversource spokesperson William Hinkle said the court’s decision affirms the substation “is critically needed to address local capacity constraints, support a rapid growth in electric use and reliably serve our customers in East Boston and Chelsea.” 

“We cannot leave any customers or communities behind in the clean energy transition and achieving decarbonization and electrification goals while ensuring that all customers have access to clean energy opportunities will require a significant amount of new electric infrastructure,” he added. 

The Massachusetts Department of Public Utilities recently approved the electric sector modernization plans of the state’s three investor-owned electric utilities, establishing the framework for major new investments in electric infrastructure across the state. (See Mass. DPU Approves 1st Round of Utility Grid Modernization Plans.) 

Meanwhile, in a proposed supplemental budget bill, Gov. Maura Healey (D) included reforms to streamline and expedite the state’s clean energy permitting and siting processes. The proposal would reduce the timeline for reviewing infrastructure projects — including substations — while requiring a cumulative impact analysis to account for existing pollution sources and public health burdens, a requirement that was not in place for the review of the East Boston substation. (See Mass. Gov. Healey Includes Permitting Reform in Budget Proposal.) 

Hinkle noted the company has completed about 75% of the work on the station foundations, with construction expected to extend through the third quarter of 2025. The company expects the substation to come online in late 2025.  

The company estimated in late 2022 the project will cost about $103 million, compared to the initial $66 million estimate presented to the EFSB. Eversource attributed this increase to construction delays and higher costs of materials and labor.  

NYISO Operating Committee Briefs: Sept. 12, 2024

Expedited Delivery, Interconnection Studies

The NYISO Operating Committee on Sept. 12 approved revisions to the 2024-01 Expedited Delivery Study, which found that all nine proposed projects are deliverable at their requested capacity resource interconnection service (CRIS) levels without additional upgrades.

The OC also approved the interconnection impact study scopes for the Niagara Digital Campus and Project Sycamore Orangeburg.

Niagara Digital is a 140-MW data center in Niagara Falls. Project Sycamore is a non-curtailable financial services server looking to expand its load to a maximum of 31.8 MW.

The Monticello Hills Wind interconnection study report was approved by the committee. The study found the 31.5-MW Oswego County wind farm would not have an adverse impact on the grid. The interconnection cost would be about $3.4 million.

Operations Report

Aaron Markham, NYISO vice president of operations, presented the August operations report to the committee.

Markham said August’s peak load was 28,444 MW, which occurred on the first of the month. He said this was because the month started hot, but the heat quickly tapered off.

“Now that we’re in mid-September looking at our longer-range forecasts, it looks like our summer peak was July 8 at 28,990 MW,” Markham said.

Markham pointed out emergency demand response and special-case resources had been activated in all zones across New York on Aug. 1 because of the hot weather. Additionally, 31 hours of Thunderstorm Alerts were declared.

“The only other thing of note is that we did increase the behind-the-meter solar nameplate capacity about 65 MW from last month; all other nameplate values repeat the same,” he said.

BOEM Announces Gulf of Maine Offshore Wind Lease Sale

The U.S. Bureau of Ocean Energy Management announced Sept. 16 it will conduct an offshore wind energy lease sale on Oct. 29 for eight areas on the Outer Continental Shelf in the Gulf of Maine.

The gulf stretches from Cape Cod to Nova Scotia and the leases include areas off Massachusetts near Boston, New Hampshire and Maine. Unlike the rest of the East Coast, the Gulf of Maine has waters that are too deep for traditional offshore wind, so any projects would have to use floating turbines.

The announcement comes less than a month after U.S. Department of the Interior and BOEM announced a “research lease” that will allow the state of Maine build up to 12 floating turbines that could produce 144 MW. (See Maine Approved for Floating Wind Research Lease.)

“The growing enthusiasm for the clean energy future is infectious,” said Interior Secretary Deb Haaland. “Today’s announcement — which builds on the execution of the nation’s first floating offshore wind energy research lease in Maine last month — is the result of years of thoughtful coordination between our team, the Gulf of Maine states, industry and the Tribes and ocean users who share our interest in the health and longevity of our ocean.”

The leases could produce about 13 GW of offshore wind power if fully developed, which could power more than 4.5 million homes. Since the beginning of the Biden administration, BOEM has held five offshore wind lease sales and approved 10 commercial-scale offshore wind projects.

The announcement is based on the best available science, including an ecosystem-based spatial suitability model conducted by the National Centers for Coastal Ocean Science. BOEM also spent more than two years engaging with Tribes, the fishing industry and other stakeholders across the region to help shape the lease areas.

The overall area is about 120,000 acres less than what BOEM included in its proposed sale notice that was announced earlier this year. The bureau tried to avoid offshore fishing grounds, sensitive habitats, and existing and future vessel transit routes, while retaining enough acreage to support the region’s offshore wind energy goals.

Winning a lease does not confer the right to build an actual power plant, but it gives developers the right to submit project specific plans that would be subject to environmental, technical and public reviews before any approvals.

BOEM has identified 14 firms that are legally, technically and financially qualified to bid in the lease auction: Avangrid Renewables, Equinor Wind US, US Mainstream Renewable Power, Diamond Wind North America, Hexicon USA, Seaglass Offshore Wind II, TotalEnergies SBE US, Pine Tree Offshore Wind, energyRe Offshore Wind Holdings, OW Gulf of Maine, Repsol Renewables North America, Maine Offshore Wind Development, Corio USA Projectco and Invenergy NE Offshore Wind.

Bidders wishing to participate have to file financial forms by Sept. 27 and post $2 million deposits for each lease area they plan to bid on (up to a maximum of two) by Oct. 11.

EHV Tx Lines Coming into Focus for ERCOT

Texas regulators are narrowing in on a reliability plan for what one said will be a “monumental infrastructure buildout” and could include 765-kV transmission to meet growing petroleum and data center demand in West Texas. 

Native West Texan Lori Cobos is the commissioner behind the quote and leader of the Public Utility Commission’s effort to add transmission infrastructure supporting the oil-rich Permian Basin. She proposed during the PUC’s Sept. 12 open meeting three regulatory proceedings to secure the reliability plan’s approval (55718). 

Cobos recommended approving local projects required to serve the Permian through 2038; authorizing transmission service providers (TSPs) to begin preparing applications for five import paths into the region; and creating a monitor to oversee the plan’s completion. 

The reliability plan builds on a recent ERCOT report that projected oil and gas load peaking at nearly 15 GW by 2038 and an additional 12 GW of data center and other non-petroleum load by 2030. The total would come to about a third of the system’s current summer peak. Based on those projections, ERCOT said building the transmission facilities to meet that load could cost up to $15.32 billion. (See SPP Considering 765-kV Solution for Permian Basin.) 

The grid operator’s staff studied two case years, 2030 and 2038, and grouped projects as either local or import paths. The local projects are independent of the study years, while the import paths consist of 345-, 500- or 765-kV options. 

ERCOT filed an addendum to the plan identifying a new endpoint for one of the import paths. It said the new endpoint would “better align” with the PUC’s recommendation allowing TSPs to begin their preparatory work while the commission decides on voltage levels. 

Commissioner Jimmy Glotfelty, who has almost a decade of experience building HVDC lines, said if he had a magic wand, he would push for 765-kV lines over 345 kV. 

“Let’s just do the 765 and get it over with, but I recognize that we’re not all there, so I think the path forward that you’ve laid out in your memo is right,” he told Cobos and the other commissioners. “The only one question that I have is the default back to 345. I would almost like that reversed, but that’s not something we need to solve today.” 

PUC staff recommends the commission adopt the 2038 case’s import path, noting 90% of the forecasting load for that year also is present in the 2030 case year. They also suggested waiting until mid-March to approve the import paths’ voltage levels. 

Representatives from the petroleum industry agreed with the approach, saying earlier is better. ERCOT also said it could work with any of the PUC’s recommendations.  

Citing concerns from the region over the need for certainty on the plan, the grid operator’s Kristi Hobbs, vice president of system planning and weatherization, said the TSPs “desire to start working on the [certificates of convenience and necessity] that take a lot of time to go through the contracting periods before they can actually file at the commission, so that allows that work to start now.” 

ERCOT is hosting a workshop at its Austin headquarters Sept. 18 on extra-high-voltage (EHV) lines. Vendors in the space will share information on supply chains, timelines, costs, construction timelines and operational characteristics of EHV lines. The grid operator also has added an EHV transmission plan to its annual Regional Transmission Plan, which will be filed in December. 

The Permian reliability plan is a result of legislation passed last year and is due Jan. 30, 2025. The PUC will consider the issue again during its Sept. 26 open meeting. 

“I think we’ll see a lot of economic development as a result of this. I think it’s going to pay for itself over time because of the amount of economic development that’s going to come as a result of that,” Glotfelty said. “765 is used in the U.S. It’s used in Canada, it’s used in Brazil, Venezuela, Russia, South Africa, South Korea and India. It’s been used since the ’60s, so this isn’t a new technology. It’s just new to us at ERCOT.” 

CenterPoint Case Delayed

The commissioners extended CenterPoint Energy’s appeal of a recent court ruling rejecting its request to withdraw its rate case, saying they want to hear from Houston residents first (56211).  

The PUC is hosting a workshop Oct. 5 in Houston to give CenterPoint customers and others a chance to weigh in on CenterPoint’s slow restoration of power after July’s Hurricane Beryl. It agreed to take up the matter during its Oct. 24 open meeting. 

“I think it’s important that before we make any decision, we go through that process and have our hearing in Houston,” Gleeson said. 

The State Office of Administrative Hearings (SOAH) in August rejected CenterPoint’s request to withdraw its rate increase to recover $6 billion of investments made since its last rate proceeding in 2019 and expand its return on equity. SOAH said the withdrawal would conflict with state law requiring investor-owned utilities in ERCOT to file a comprehensive rate review within 48 months of their most recent rate proceeding. (See CenterPoint Energy Still in Eye of the Storm.) 

The commission has been directed to file a report on CenterPoint’s restoration efforts with Gov. Greg Abbott by December. It has received more than 16,000 responses to a public questionnaire and an additional 120 responsive filings from utilities, cities and trade associations. 

Engie-ERCOT Dispute Deferred

The commission heard oral arguments but took no action on a two-year dispute between Engie North America and ERCOT over compensation for the response reserve service (RRS) the company provided during the February 2021 winter storm. It deferred making a decision until a later open meeting. 

Engie and Viridity Energy Solutions ask to be reimbursed $47.5 million or credited for the 27 MW of RRS it delivered each day during Feb. 15-19, 2021. ERCOT said the complainants did not provide the RRS after Feb. 15, citing their failure to have confirmed trades for the ancillary service in the day-ahead market during those days. Engie and Viridity contend that following normal procedures was effectively impossible during the storm, when ERCOT’s grid came within minutes of a total collapse (53377). 

SOAH’s law judges in June rejected the Engie and Viridity complaint. They found the complainants did not show that ERCOT’s actions violated any applicable law. 

At issue is the grid operator’s requirement to have capacity that supports an ancillary service trade or offer. Its protocols define capacity for noncontrollable load resources as their net power consumption minus low power consumption, which is the load available for interruption. 

Engie’s legal counsel said the load resources lost their capacity when deployed, preventing them from being scheduled in the next day-ahead market. Engie and Viridity sought remedial relief to receive $47.5 million for the service they provided during the storm. 

ERCOT says the evidence indicated Viridity benefited by not participating in the day-ahead market, avoiding $65 million in ancillary service imbalance charges. 

PUC Adopts EOP Report

The PUC also adopted staff’s recommendation to approve a report on the power sector’s weatherization preparedness and companies’ emergency operations plans (EOPs). The report is due to the state legislature, which directed the report last year, by Sept. 30 (53385). 

Business management consultant Guidehouse reviewed 691 electric entities’ EOPs, checking the grid’s ability to withstand extreme weather events in the coming year. It found the sector is “largely prepared” across the state for extreme weather, and its participants exhibit “basic” emergency preparedness programs and have measures in place to respond to weather events. 

The firm noted its review was limited in scope and did not “comprehensively” cover resource adequacy, weatherization, system-hardening efforts or spare critical inventory. Guidehouse’s suggested improvements included financial penalties for noncompliance and a greater focus on EOPs’ actions to withstand extreme weather events.  

“One example identified in multiple EOP submissions is the inclusion of a detailed list of food items needed for an entity’s staff during emergency situations … but the plans did not include strategies or equipment needs for field response,” the report said. 

About 70% of applicable entities provided EOPs or affidavits on no material changes. Guidehouse said the remaining 30% were “overwhelmingly low risk.” 

MISO Says 2nd Long-range Tx Plan to Cost $21B, Deliver Double in Benefits

MISO said its second, mostly 765-kV long-range transmission plan will provide the Midwest region with at least a 1.9:1 benefit-cost ratio and cost $21 billion, lower than its earlier estimated $23 billion to $27 billion.

The grid operator announced the approximations at stakeholder workshops Sept. 10 and 13. Even with the slightly lower costs, MISO’s Independent Market Monitor is incredulous the portfolio would deliver nearly double its cost in benefits.

Jeremiah Doner, MISO director of cost allocation and competitive transmission, said MISO refined its cost estimate using facility-specific details.

“That number may move around a little bit. But I think that $21 billion is where the portfolio stands,” he told stakeholders. “We don’t expect at this point in the process to be adding projects, so we don’t expect that number to materially change.”

Doner said MISO tried to minimize costs by proposing to co-locate some of the new 345- and 765-kV lines with existing structures.

“We know there’s always more risk in the regulatory permitting process when you have to seek new rights of ways,” Doner said. He added that MISO is in discussions with its transmission owners about what would be the most feasible route for the line.

MISO also is exploring routing a 765-kV line on an existing 161-kV route because it will cross an “environmentally sensitive” area from Wisconsin into Minnesota over the Mississippi River, Doner said. “We recognize that’s not a common practice,” he added.

At $21 billion and roughly 4,000 line miles, the second plan doubles the first LRTP portfolio, both in terms of costs and line miles. Doner reminded stakeholders the second portfolio has been in the works since 2022, when MISO moved to establish a projection of what the system would look like in 20 years.

The Ratio

Doner said the portfolio demonstrates “at least” a 1.9:1 benefit-to-cost ratio when analyzing its projects using MISO’s nine benefit metrics, which include the advantages of decarbonization, ability to withstand extreme weather and assistance in avoiding loss-of-load events, in addition to the more mundane adjusted production costs.

“We know these assets are going to be in service much longer than that,” Doner explained, adding that MISO was intentionally conservative to show the projects will more than pay for themselves over their first 20 years of service.

Doner said if MISO assumes the lines have a 40-year lifespan, total benefits could rise to 3.8:1. He added that with the conservative estimate, all of MISO’s cost allocation zones in the Midwest region are set to experience at least a 1.3:1 benefit-cost ratio.

“I think it’s important to show at least a 1:1 benefit-cost ratio in each of the cost allocation zones,” Doner said.

On a 20-year basis, MISO estimates the second LRTP portfolio will conservatively save MISO Midwest $16.3 billion because of the mitigation of reliability issues; $15.7 billion from avoided capacity costs; $8.1 billion in congestion and fuel savings; at least $7 billion in decarbonization assistance; nearly $3 billion in capacity and energy savings from a decrease in system losses; and $1 billion in avoided transmission investment. MISO also estimates the LRTP portfolio will save the Midwest at least $392 million from the reduced risk of extreme weather and $76 million in reduced transmission outage costs.

Skepticism

However, Monitor David Patton said he continues to believe three of the nine benefit metrics (avoided capacity costs, avoided reliability risk and decarbonization) are outright invalid or overstated and if they are deleted or significantly scaled back, the portfolio’s benefits would not come close to covering its costs. (See MISO Closing in on Final, $25B LRTP; Monitor Repeats Reservations.)

“If you adjust for those metrics, the overall benefit metric goes down to 0.5:1,” Patton said, adding he thinks it is “really, really important to scrutinize” MISO’s methodology.

“This is not about reliability. This is about a choice to build generation to further others’ policy goals,” North Dakota Public Service Commission staffer Adam Renfandt said in criticizing the portfolio.

Doner said when MISO developed its 20-year outlook that the portfolio is built upon, it examined which direction members were taking “across the whole footprint, not just in pockets of the MISO system.”

MISO planner Joe Reddoch said the analysis showed the portfolio would reduce constraints and increase system capacity so the RTO can meet its capacity needs with fewer resources.

Patton pushed back on the message that MISO faithfully followed its members’ resource plans when crafting the portfolio. He said that to model resources, the RTO relied on the Electric Power Research Institute’s Electric Generation Expansion Analysis System (EGEAS), which he said only minimizes costs in deciding what to build and ignores potential revenues entirely, leading to “very unrealistic” fleet assumptions.

Patton said he doubted the avoided capacity costs MISO has estimated and that members naturally would build more deliverable resources on the other side of transmission constraints if the transmission were never constructed. He said it’s highly unlikely members would continue to build generation in sites that are undeliverable to load. Patton added that if MISO approached its members and said it was not going to meet its resource adequacy obligations, members would adjust resource planning, which “pretty quickly” would reduce the LRTP’s benefits by “tens of billions.”

“You’ve cited an undeliverable collection of resources if we don’t build [the second portfolio], but our markets are designed to take care of that. To characterize that as a benefit is pretty misleading,” Patton said.

Doner said members have asked MISO to build a dependable system around their future plans. He also said it is not so simple for members to “move generation around,” citing wind- and solar-rich locations in the footprint.

“We have transmission planning responsibilities, not resource planning responsibilities. We really do rely on what our members are telling us that they’re going to build,” Doner countered.

Patton also said MISO is off base by establishing the value of the portfolio’s avoided reliability risks on the value of lost load (VoLL). He said in “no world” would the RTO allow reliability risks to become severe enough to shed load. Instead of lost load, Patton argued MISO should base the benefit on which transmission facilities would be built without the LRTP portfolio. MISO needs “an accurate ‘but for’ case,” in which it analyzes which shape its system will take without the second portfolio, he argued.

“Calculate something that’s real. This is not real,” Patton said. It’s “unconscionable” to expose customers to transmission investment based on “imaginary” and “massively overinflated” benefits, he said.

Jim Dauphinais, an attorney representing multiple industrial customers in MISO, said the use of VoLL in the benefit is “highly problematic.”

However, Jeff Eddy, director of transmission planning for ITC Holdings, warned stakeholders “there are big dollars behind outages” and pointed to Texas as an example. Eddy said that if anything, MISO was being conservative on the portfolio’s $16 billion reliability value.

“We know that these backbone lines really do provide benefits,” Sustainable FERC Project attorney Lauren Azar added. “I hope no one is questioning the benefits that regional backbone lines bring to the region.”

Reddoch said it’s difficult to compare the numerous, scattershot baseline reliability projects MISO would need on a five- to 10-year horizon with the 20-plus-year reliability benefits that the second LRTP portfolio would achieve. However, he said the portfolio likely would be more economical than smaller, piecemeal projects to comply with NERC standards.

“This has always been a challenge in the industry to monetize reliability,” Doner added.

North Dakota PSC Commissioner Julie Fedorchak said she was “dubious” that all MISO members would know where their projects will be located 20 years into the future, suggesting the RTO took liberties with its siting assumptions.

WEC Energy Group’s Chris Plante said he would like MISO to admit its planners fashioned a hypothetical resource expansion only with its members’ carbon reduction goals in mind. “My expansion plans don’t go out much more than seven years,” he said.

Doner said while it is not “100% member plans” that make up the 20-year future, it nevertheless comprises mostly member plans, and where there are not explicit plans, MISO sought extensive member input.

MISO Vice President of System Planning Aubrey Johnson said the RTO made “over 500 adjustments” to its original resource siting assumptions after speaking with its stakeholders throughout the planning process.

“Good golly, I really wish we could build regional backbone projects sooner than eight to 15 years in the future,” Azar said, urging stakeholders to consider the timeline to build transmission. “MISO has no choice but to essentially site the resources in the models. All modeling is necessarily wrong, but that doesn’t mean we shouldn’t be doing it. I really just urge folks to think about the reality of how long it takes to build these really big projects.”

“I’ve never known a resource planner who can tell me exactly what they’re going to do,” Eddy agreed. “This is high-level stuff, and I support what MISO is doing.” He said stakeholders seem to be losing sight of what MISO’s big-picture, future planning was intended to accomplish.

Plante said it seems MISO is rushing for December board approval rather than making sure “sound planning principles” are applied to the portfolio.

“Given the magnitude of the expansion planning here, we need to be careful that we establish sound foundations,” Plante said, adding  the projects will be subject to scrutiny at state regulatory agencies.

“We disagree that there’s a lack of analysis here. We believe this is thorough,” said Jeanna Furnish, MISO director of expansion planning.

Equinor Yanks Request for Empire Wind 2 Export Cable

An offshore wind proposal that was placed on hiatus amid the industry’s recent financial turmoil is taking a further detour, halting its attempt to bring an export cable onshore in New York. 

Empire Offshore Wind on Sept. 12 withdrew its application (Case No. 22-T-0346) with the state Department of Public Service for a Certificate of Environmental Compatibility and Public Need for the transmission line that would have served Empire Wind 2. 

Without a certificate, Empire cannot build a line. 

The application had become highly controversial in the 27 months since it was submitted, attracting strong resistance in Long Beach, the oceanfront city it would pass through. (See ‘What Did We Do to Deserve This?’) Nearly 1,000 comments have been submitted in the Public Service case. 

Gov. Kathy Hochul (D), a vocal wind power proponent, further complicated the effort when she vetoed an attempt to facilitate construction of the cable through the city. (See New York Governor Vetoes Planned Offshore Wind Transmission Act.)  

A spokesperson for Equinor said Sept. 13 the company remains committed to development of the Empire Wind 2 lease area in a manner that is profitable and will assess future offtake opportunities. 

Both Empire plans have been approved by federal regulators, but only Empire 1 is progressing at this point. (See BOEM Approves Empire Wind.) 

Equinor anticipates a final investment decision on Empire 1 this year. The company is building an $861 million offshore wind hub in Brooklyn to service this and future projects, and it is looking for an equity partner for Empire 1. 

Empire 1’s export cable would connect with the grid in Brooklyn, in a location and manner that has not attracted opposition similar to that seen in Long Beach. 

Empire Wind 1 and 2 and Beacon Wind 1 and 2 were joint ventures of Equinor and bp; the two companies previously were awarded New York state contracts for Empire 1, Empire 2 and Beacon 1. 

The anticipated cost of construction soared in 2022 and 2023, however, rendering the financial terms of those contracts untenable, and all three contracts were canceled, along with contracts for many onshore renewable projects. (See Sweeping Reset Underway for NY Renewable Development.) 

The two companies ended their partnership and split their portfolio. Beacon went to bp, which said in June it still was evaluating its options. (See Bp Says It is Still Evaluating Beacon Wind.) 

Equinor bid Empire 1 into the rush solicitation New York launched in an attempt to get its offshore wind aspirations back on track when its portfolio collapsed. Equinor won a new contract this year for 810 MW of capacity at a much higher price than the original contract. (See Empire, Sunrise Wind Back Under Contract in NY.) 

Equinor did not rebid the 1,260-MW Empire 2 into the rush solicitation, and the spokesperson said it also did not rebid the project into the current New York solicitation, which closed Sept. 9. 

The current solicitation attracted some other familiar names, however: Attentive Energy, Community Offshore Wind and Excelsior Wind all announced that they had submitted proposals for plans that have been in the works for years. (See NY OSW: If at First You Don’t Succeed, Try, Try Again.) 

New York awarded tentative contracts to all three proposals in October 2023, but they had to be scratched in April 2024, when development of the turbine specified in those contracts was halted. (See NY Offshore Wind Plans Implode Again.) 

Mass. Gov. Healey Includes Permitting Reform in Budget Proposal

Following the failure of the Massachusetts House of Representatives and Senate to reach common ground on a climate bill this summer, Gov. Maura Healey (D) has proposed to include clean energy permitting and procurement provisions in a supplemental budget bill announced Sept. 11.

While the permitting and siting reform framework largely has been agreed on for months, legislators were unable to overcome disagreements between the House and Senate over natural gas and competitive electricity supplier reforms before the end of the formal legislative session in July. (See Mass. Lawmakers Fail to Pass Permitting, Gas Utility Reform and Mass. Legislature Faces Looming Deadline to Pass Permitting Reform.)

The permitting and siting proposal would consolidate the approval process for clean energy infrastructure projects and impose a 15-month cap on the review of large projects and a 12-month cap on the review of small projects.

Sen. Mike Barrett (D), the lead Senate negotiator on the climate bill, has argued that expediting the permitting process — while important for the clean energy transition — could lead to increased infrastructure costs to ratepayers, and therefore must be coupled with the gas and competitive electricity supplier reforms intended to help offset some of the costs to ratepayers.

The Senate version of the climate bill would allow gas utilities to retire portions of the gas network if viable alternatives are available, update the state’s pipeline replacement program with the goal of reducing ratepayer costs, and require annual filings from the gas utilities on their efforts to reduce emissions and minimize risks of stranded assets.

Healey’s supplemental budget, however, declined to include gas or competitive supplier reforms. The governor wrote in a letter to legislators that the clean energy permitting reforms would help the state “capitalize on the potential to grow our clean energy sector and advance our climate goals.”

The supplemental budget — if brought up in the informal session — could be halted by the vote of a single legislator; passing a bill in an informal session requires unanimous approval of all present lawmakers. This makes it unlikely the legislature will approve any of the more controversial climate proposals, and also could pose a challenge for the slimmed-down permitting and procurement proposals.

The legislature’s next formal session starts in January, although the governor and top lawmakers have signaled interest in calling a special formal session focused on a separate economic development bill that legislators also failed to pass in July.

The inclusion of the permitting provisions without gas reforms spurred criticism from Barrett and climate activists.

“The governor and the House want us to pay for two separate — and expensive — systems to serve the same population’s energy needs,” said Becca Glenn of the advocacy group Mothers Out Front in a statement. “Massachusetts residents can’t afford to prop up an aging gas system while also paying for a modern, clean energy system.”

Barrett told NetZero Insider he’s disappointed with the supplemental bill proposal, noting that “all the Senate reforms intended to provide ratepayer relief have been stripped out.” The proposal has undermined ongoing negotiations between the Senate and the House over the climate bill, he added.

“I’m not sure that the House will have any incentive to negotiate with us, because [the supplemental budget] gives them the minimalist outcome that they seek,” Barrett said. “We had actually reached agreement on a significant number of secondary items, so there was real promise to these negotiations. The governor has upset all of that.”

Rep. Jeff Roy (D), the lead negotiator on the House side, did not respond to requests for comment in time for publication, but he told the State House News Service he’s “encouraged by what the governor is attempting to do.”

Kyle Murray of the Acadia Center said the administration’s inclusion of the permitting reforms in the budget bill “probably signals that they didn’t sense likely movement” in the negotiations between the House and Senate.

He said reforms to expedite clean energy permitting and to enable the transition off natural gas are key aspects of the state’s clean energy transition but added that “any climate bill that moves forward must take practical and common-sense steps to address the gradual decommissioning of the sprawling natural gas system. Any bill that does not do so is not acceptable.”

A spokesperson for the Executive Office of Energy and Environmental Affairs said the governor’s office “included time-sensitive energy provisions critical to the procurement, permitting and siting of energy projects” in the supplemental budget, adding that the administration “continues to support the climate bill and will continue to work with the Legislature on its passage.”

Beyond the specific reforms at hand, Barrett also expressed dismay at the strong opposition that has come from the gas industry to the Senate’s efforts to facilitate a transition away from gas.

“This has been an eye opener,” Barrett said. “We’ve got to get off natural gas — consciously but effectively — but after this year’s experience, I can predict a tough road ahead even in a very blue state.”

The state’s electric and gas utilities historically have been the most influential interests on climate policy in the state, according to a 2021 analysis from Brown University researchers. Over the course of the 2023/24 legislative session, investor-owned gas and electric utilities cumulatively reported about $1.6 million in spending on lobbying in the state.

Clean Energy Procurement

The supplemental bill also proposed significant changes to the state’s clean energy procurement process, incorporating aspects of both the House and Senate climate bills.

The bill would enable the state’s Department of Energy Resources (DOER) to pursue coordinated solicitations with other states for clean energy generation or transmission that would help the state meet its policy goals in a cost-effective manner.

It also would direct the DOER to review the effectiveness of the state’s existing clean energy procurements, and to “make recommendations regarding the future procurement of clean energy resources for the purposes of ensuring compliance with statewide greenhouse gas emissions limits.”

It also specifically directs the DOER to solicit up to 5,000 MW of storage resources over the next four years, including 3,500 MW of mid-duration storage (lasting between four and 10 hours), 750 MW of long-duration storage (between 10 and 24 hours) and 750 MW of multi-day storage (greater than 24 hours).

ICF Report Forecasts Significant Demand Growth This Decade

ICF International forecasts that demand could increase by 9% by 2028, while peak demand could increase by 5% over the same period, according to a report it published Sept. 12. 

The consulting firm expects that growth to continue, as overall demand will increase by 18% by 2033 and peak demand by 10.7%. The shift to demand growth comes after decades of relatively flat levels in the U.S. 

A robust economy, electrification, growth in manufacturing, data centers and cryptomining are all contributing to the rising demand for electricity. Growth will vary by region, with ICF seeing the largest increase overall in the Mid-Atlantic region because of vehicle electrification and data centers, where demand is expected to grow by 68% by 2050, compared to the national average of 57%. 

“What makes this stark increase in energy demand, particularly peak demand, so challenging is that it simply wasn’t [forecast] in most projections until very recently,” the report says. “The latest demand projections are significantly higher than projections made as recently as 2023. The divergence between last year’s projections and current projections is broad by 2033 and only continues to grow in the coming decades.” 

New supply, including utility-scale solar and wind, could help meet the rising demand, but ICF notes that it faces hurdles for that to happen, including the need to upgrade the grid, cutting the time frame of the permitting process and finding suitable locations to build. 

The grid is not designed to accommodate major amounts of new generation immediately, with ICF noting that on average, it can handle just 189 MW at once, with upgrades needed to handle additional supply. The Mid-Atlantic, northern New England, parts of the Southeast and the Upper Midwest are particularly constrained in that way, the report says. 

And the industry needs to worry about getting that down to the distribution level, with the average amount of such “withdrawal capacity” being 153 MW before upgrades are required, with the biggest challenges in areas with high peak demand growth such as Northern Virginia and parts of Texas. 

The growing demand could slow progress in the transition to clean energy, as it might force utilities to keep fossil-fueled power plants running longer than otherwise, the report says. 

“With enough investment, the U.S. can make major upgrades to the grid and install vast amounts of renewable energy, meeting demand growth while decarbonizing the grid. Americans will likely pay higher utility rates, taxes to pay for federal and state subsidies, or both.” 

The wholesale prices that many utilities pay for electricity could go up by an average of 19% by 2028, and “much of” that would be passed onto customers, the report says. ERCOT could see even higher price increases of 22% by that year. 

The report suggests utilities start engaging in more sophisticated planning that considers the entire system from generators to end-use customers. 

“This requires an integrated approach across all asset classes, including generation, transmission, distribution, distributed energy resources, conservation and load management,” the report says. “This holistic approach equips utilities to consider long-term investment strategies that enhance grid reliability, resilience and operational efficiency by adding greater flexibility and responsiveness to traditional generation and transmission solutions, like virtual power plants.” 

Other suggestions include identifying areas with plenty of renewable resources that can be connected to the grid, enhancing the distribution grid, expanding load-management programs, using artificial intelligence to improve planning and grid management, and staying engaged with regulators on the issues. 

MISO, TOs Argue Self-funding Necessary for Transmission Development

MISO and its transmission owners defended their practice of allowing transmission owners to self-fund network upgrades in separate filings Sept. 11 responding to FERC’s Order to Show Cause (EL24-80).

FERC in June said grid operators’ practice of allowing TOs first crack at financing — and therefore earning a return on — the network upgrades necessary to bring generators online could be biased against interconnection customers, who may experience higher interconnection costs as a result.

The commission ordered MISO, PJM, SPP and ISO-NE to explain how their tariff language on the initial funding is fair or, alternatively, propose changes to make their policies impartial. It also suggested that TO self-funding creates barriers to interconnection (EL24-80, et al.). (See FERC Issues Show-cause Order on TO Self-funding in 4 RTOs.)

For more than a decade, MISO’s practice of TO self-funding has been the subject of oscillating rulings between FERC and the D.C. Circuit Court of Appeals. RWE Renewables, NextEra Energy and EDF Renewables recently claimed their costs “double or increase exponentially” when TOs take the lead on funding network upgrades.

In their filing, the TOs argued that eliminating their unilateral ability to self-fund upgrades would decrease, rather than promote, the capital investment needed for transmission projects. They also said FERC has no basis to eradicate TO self-funding after establishing it in Order 2003.

MISO insisted its TO initial funding practice is fair and said it never has “observed any instances of [it] being used as a tool to inflate the costs of network upgrades or create advantages for some generation projects vis-à-vis others.” The RTO said a TO electing to self-fund does not affect the interconnection service, but it did acknowledge it does increase the costs for interconnection customers.

“TO initial funding does increase the cost of interconnection service to the interconnection customer, but only because that cost would not otherwise include a … return on capital,” MISO said. “From the perspective of [a] transmission owner, the actual cost of the operating and maintaining the funded network upgrade is unchanged.” It added that eliminating the self-funding option will not necessarily result in lower costs because interconnection customers also could require a return on capital and shift that cost to ratepayers.

MISO also said its procedure affords interconnection customers the opportunity to suggest alternatives to and investigate the justification for a network upgrade so they’re not on the hook for oversized projects that would pad TOs’ bottom lines. The RTO also said interconnection customers can pursue alternative dispute resolution or choose to file unexecuted facilities service agreements to challenge upgrade costs.

The RTO insisted its three-phase interconnection queue design provides enough oversight so that “any network upgrade and corresponding self-fund election has a transparent, multistep history, with MISO involvement at each step.”

However, MISO added a caveat that it “has only limited insight into its transmission owners’ internal functions, needs and decision-making,” so it could not answer all questions posed by the commission. In those cases, MISO submitted its TOs’ answers.

The TOs adopted a more full-throated defense. They said FERC’s show-cause order “poses questions that make it apparent the commission has made up its mind” to eliminate the self-funding option “without regard to the long-term effect this will have on transmission owners and other customers they serve.”

They argued it is imperative they be able to earn a return on assets they will own, operate and maintain for the duration of their useful lives. They said the show-cause order amounts to “misguided policy goals behind an undue discrimination theory” and argued that no one has been able to produce evidence that TO initial funding causes undue discrimination “in the 13-plus years that TO initial funding has been before the commission.”

The TOs also said that, in an era of supersized transmission expansion, it appears FERC has forgotten to “balance interests and to ensure that native load customers are not negatively affected as a result of third-party generator interconnection.” They said their financial viability should be maintained and FERC should be careful not to “strike a one-sided ‘balance’ in favor of cheaper interconnections for generators.”

“Transmission owners bear substantial risks associated with owning, operating and maintaining said transmission facilities, and stand to lose the right to self-fund network upgrades and, with it, the ability to earn a just return on an entire class of interstate transmission facilities, in a grossly unfair proceeding,” the TOs said.

If they are denied the opportunity to make a return on network upgrades, the TOs argued it would constitute an attack on their business model and is akin to the “taking of private property for public use without just compensation.” It is “overly simplistic” and “reductionist” to think  TOs should not be able to earn a return on network upgrades simply because the money for them comes from generation developers, not themselves, they argued. They also said they never would build unnecessary network upgrades because MISO independently studies interconnection needs.

FERC should terminate the proceeding with prejudice, the TOs concluded.

ERCOT Sets Go-live Date for RTC, ESR Project

ERCOT has set a target go-live date for its real-time co-optimization project, which is expected to add millions in savings to its market. 

The Texas grid operator said Sept. 13 that it has set a Dec. 5, 2025, goal for the market change, about six months ahead of its original mid-2026 timeline.  

Real-time co-optimization (RTC) is used by most other grid operators in North America. The market tool procures energy and ancillary services every five minutes, automating many processes that currently are managed manually. ERCOT currently procures ancillary services in the day-ahead market and typically does not move them between resources in the real-time market. 

CEO Pablo Vegas said RTC’s implementation is “the most significant market enhancement” to ERCOT’s nodal design since its inception in 2010.  

“The target go-live date represents an important milestone in ERCOT’s confidence for planning and tracking the completion of the RTC project for a more dynamic and efficient wholesale power market,” he said in a statement. 

The ISO’s Independent Market Monitor in 2018 released a report that evaluated RTC’s effect on the market. Using 2017 as its simulated operating year, it found a $1.6 billion reduction in total energy costs; an $11.6 million reduction in production costs to serve load; a $257 million reduction in congestion costs; a $155 million reduction in AS costs; and reliability improvements due to a reduced overloading of transmission constraints and a decrease in regulation up. 

Staff and stakeholders have been working on the RTC project since 2019, when the Public Utility Commission directed ERCOT to add the mechanism after the commission assessed its costs and benefits. (See “Real-time Co-optimization Go-live Date Could be Accelerated,” ERCOT Technical Advisory Committee Briefs: Aug. 28, 2024.) 

The project has been expanded to address the growth of energy storage resources in ERCOT. Texas began 2024 with about 5,000 MW of energy storage online, second only to California. It is expected to add more than 6,000 MW this year, according to the U.S. Energy Information Administration. 

System testing will begin early next year. Market trials are planned to begin in May and run through November.