ISO-NE Analysis Details Benefits of Demand Flexibility

Increased demand flexibility could significantly reduce production costs, capital costs and transmission costs in New England by better aligning load with generation and reducing peak loads, ISO-NE said at the Planning Advisory Committee’s meeting July 23. 

Presenting additional results from its 2024 Economic Study, ISO-NE said demand flexibility could reduce production costs by 10 to 15% in 2050. The RTO found that capital cost savings would “increase linearly with increasing demand-side flexibility” by reducing reliance on “expensive resources that are only needed for short durations.” 

Demand flexibility would also provide emissions benefits by reducing load during the most carbon-intensive peak periods and would reduce the need for energy storage by limiting the imbalances between energy production and demand, ISO-NE found. 

As a caveat to its findings, the RTO noted that the demand flexibility modeling assumes “perfect foresight and total control over flexible load” and therefore may inflate savings projections. 

The study is intended to quantify the economic and environmental effects of state and federal energy policies and “evaluate competitive solutions to alleviate identified system efficiency needs.” (See “2024 Economic Study,” ISO-NE Details Evaluation Models for Transmission Solicitation; “Additional Economic Study Results,” ISO-NE Planning Advisory Committee Briefs: March 19, 2025; and ISO-NE Finds Advanced PV Panels Could Reduce Decarbonization Costs.) 

ISO-NE has previously forecast significant transmission savings associated with demand flexibility; it estimated in 2023 that the region could save up to $9 billion in transmission costs by reducing its forecast 57-GW peak load for 2050 to 51 GW. (See ISO-NE Prices Transmission Upgrades Needed by 2050: up to $26B.) 

Also at the PAC meeting, ISO-NE discussed a sensitivity analysis from the Economic Study reducing the capital cost assumptions for small modular nuclear reactors (SMRs). The RTO’s baseline assumptions for the study relied on conservative SMR cost projections from the National Renewable Energy Laboratory. 

“The lower cost assumptions for SMRs shifted [their] buildout from 2039 to the mid-2030s and reduced the buildout of other non-emitting resources,” said Kim Quach of ISO-NE. She noted that lower SMR costs also lowered reliance on peaker generation and largely eliminated the need for 100-hour battery storage. 

The RTO also discussed a model sensitivity reducing the emission-reduction requirements. It found that requiring only 75% decarbonization by 2050 would cut total costs by about 50% relative to the base case. The lower costs stemmed from decreased reliance on the most expensive clean resources needed to achieve deep decarbonization, including SMRs. 

While scaling back the long-term decarbonization of the power sector could significantly reduce electricity costs, it would make it extremely difficult for states to meet their climate targets and reach net-zero emissions by 2050. Rhode Island has set a goal of meeting 100% of its power demand with clean energy by 2030, while Massachusetts has estimated it will need to cut power sector emissions by 93% by 2050 relative to 1990 levels to reach its net-zero goal. 

The Intergovernmental Panel on Climate Change (IPCC) estimates that global emissions must decline significantly in the coming years and reach net zero by 2050 to limit warming to 1.5 degrees Celsius. Passing this warming threshold will intensify extreme weather events and have widespread negative impacts on human health, food and water supplies, and economic growth, according to the IPCC. 

Resource Outlook Study

ISO-NE anticipates minimal shortfall risks over the next decade, with the loss-of-load expectation falling below the one-in-10 reliability criteria for each year, ISO-NE’s Donald Poulin said in presenting the RTO’s 10-year resource outlook study. 

He noted that forecasted shortfall risks increase as the decade progresses because of growing load and the assumption of a stagnant resource mix. 

Asset-condition Projects

Chris Soderman of Eversource Energy presented a $24 million asset-condition project to replace 48 wood structures with steel structures on a 115-kV line in southern New Hampshire.  

The company has identified damage and deterioration on 25 structures and will replace additional “Category B” structures facing flooding, uplift issues or are in “close proximity” with more deteriorated structures, Soderman said. 

Under the transmission owners’ standardized PAC presentation guidelines, Category B refers to structures with moderate deterioration that may be replaced “in conjunction with other structure replacements.” 

Soderman also presented a $6 million project in New Hampshire to replace 15 wood structures on a separate 115-kV line. He said six of the structures have deteriorated to the point of needing replacement, while nine structures are categorized as Category B proximity structures. 

Connecticut Needs Study

ISO-NE also discussed a revision to its Connecticut 2034 Needs Assessment.  

Following an update to correct errors in the load distribution in Rhode Island, ISO-NE has reduced the extent of thermal overloads it forecasts for Connecticut in 2028 and 2034, along with the number of buses with low-voltage violations it forecasts for 2028. 

The revisions did not affect the number of high-voltage violations identified by the RTO, which are associated with minimum loads. 

The RTO plans to publish the draft assessment “in the near future” and aims to release the final version in August. It intends to begin work on the Connecticut 2034 Solutions Study in the third quarter of this year, focusing on short-term needs. 

GE Vernova’s Gas Power Equipment Surge Continues

GE Vernova’s gas power and electrification businesses continue to surge amid growing power demand.

The company on July 23 reported second-quarter financials that exceeded projections and offered an optimistic message that sent its stock price soaring to all-time highs.

CEO Scott Strazik said GE Vernova’s backlog for gas-fired turbines grew from 50 GW of orders and manufacturing slot reservations to 55 GW in the second quarter, and he expects to end the year at 60 GW. The longer-term expectation is 80 to 100 GW of backlog.

The company’s large heavy-duty gas turbines are in high demand, but there also is growing demand for its small aeroderivative gas turbine packages that leave the factory 95% preassembled.

Just a day earlier, GE announced it would sell 29 of these smaller units rated at 34 MW each — nearly 1 GW in total — to Crusoe for its AI data centers.

This technology — essentially a modified jet engine with emissions controls — is quick to deploy, quick to start up and can provide a bridge solution when the interconnection queue is moving more slowly than the customer wants to. Eventually, the aeroderivative turbines can become backup power sources for a facility or connect to the grid, Strazik said.

GE Vernova and Crusoe announced a deal for 29 of these LM2500XPRESS aeroderivative gas turbines to provide nearly 1 GW of power to data centers. | GE Vernova

GE Vernova also has its name on a massive installed generation fleet built by General Electric and is seeing strong growth in its service business, Strazik said.

“Our services backlog also grew approximately $1 billion in the second quarter,” he said. The company has been incrementally increasing its pricing on new equipment orders and will be doing so with its service business.

During an earnings call July 23, an analyst asked what effect sharp changes in federal energy policy are having on GE Vernova.

The reconciliation bill was finalized only a few weeks ago, Strazik said, so it is early to draw conclusions. However, GE Vernova has seen accelerated interest — but not yet orders — for grid equipment supporting wind and solar generation, he said. That is near- to mid-term interest, he said, which would match with the impending end of federal tax credits for wind and solar energy development.

“There also is very clear market sentiment that into the next decade, there’s going to be a need for more gas,” Strazik said. “I would say our pipeline of activity for gas demand is only growing, but it’s growing at even more healthy levels for ’29 deliveries, ’30, ’31 — periods of time where, maybe prior to the bill being signed, some of our traditional customers may have been intending more wind or solar.”

GE Vernova’s second-quarter results surpassed projections, pushing first-half 2025 revenue, earnings, free cash flow and backlog higher than year-ago levels. The company has increased its projections for the second half of 2025.

The price of GEV stock soared throughout the trading day, closing 14.6% higher than July 22 and 349.3% higher than on the close of its first day of trading in April 2024.

Also with its second-quarter financial results, GE said:

    • Steam power service orders jumped on efforts to upgrade existing nuclear reactors and extend their operation.
    • Even larger growth was seen in hydropower, again due to upgrades.
    • Progress continues on development of the 300-MW small modular reactor that is the first SMR being built in North America; more customer announcements are expected in the second half.
    • Demand for synchronous condensers, a longstanding but minor line for the company, is expected to grow with the need for grid-stabilizing technology, Strazik said. “We see this as a credible $5 billion market opportunity a year.”
    • Onshore orders in North America drove an increase in revenue for the wind business, offset by continued losses offshore; it may approach the break-even point in the second half.
    • The electrification business saw a $2 billion increase in backlog, driven by switchgear and transformers.

DOE Pulls $4.9B in Funding for Grain Belt Express

The Department of Energy says it has terminated its $4.9 billion conditional loan commitment for the long-delayed Grain Belt Express project, saying it is “not critical” for the federal government to support the project.

“After a thorough review of the project’s financials, DOE found that the conditions necessary to issue the guarantee are unlikely to be met,” the DOE said in a July 23 press release.

DOE said the Loan Programs Office’s loan guarantee, issued by the Biden administration in November 2024, was one of many conditional commitments “rushed out the door” shortly after the 2024 election.

A project spokesperson said the developers are disappointed with the withdrawn LPO loan guarantee, noting that the Grain Belt Express “will be America’s largest power pipeline.”

“A privately financed Grain Belt Express transmission superhighway will advance President Trump’s agenda of American energy and technology dominance while delivering billions of dollars in energy cost savings, strengthening grid reliability and resiliency, and creating thousands of American jobs,” the spokesperson said in an email to RTO Insider.

Rob Gramlich, Grid Strategies’ president, said the decision was “confusing,” given the administration’s focus on the need for energy to power artificial intelligence data centers.

“We really need interregional transmission and [DOE] Secretary [Chris] Wright and now the White House, through their AI plan, say transmission is important,” he told RTO Insider.

The DOE said it is conducting a review of every applicant and borrower, including the nearly $100 billion in closed loans and conditional commitments the LPO made between Election Day 2024 and Inauguration Day 2025.

DOE’s action is the latest hurdle facing the Grain Belt Express, an 800-mile HVDC project that has been under development since 2010. The project’s developer, Invenergy, says the $11 billion merchant transmission line would be capable of moving 5 GW of mostly clean energy from Kansas across Missouri and Indiana and into Illinois.

The news was celebrated by U.S. Sen. Josh Hawley (R-Mo.), who has called the project a “boondoggle” and twice sent letters to the DOE urging the agency to cancel the loan guarantee. Hawley took credit for the cancellation, charging that the project “has taken the land of numerous Missouri farmers across eight counties while padding [Invenergy’s] corporate profits.” (See Grain Belt Funding Appears on Shaky Ground with DOE; Invenergy Firm on Value.)

| Josh Hawley via X

The project has been approved by regulators in all four states involved. The Missouri Public Service Commission found the project would save the state’s customers as much as $18 billion, Invenergy has said. The company noted municipal utilities in 39 communities have contracts with it for power delivery and contractually guaranteed cost savings.

However, the project has faced opposition from Missouri landowners, who are opposed to a for-profit, private entity using eminent domain. Missouri Attorney General Andrew Bailey has criticized Grain Belt Express for filing nearly 50 eminent domain lawsuits against Missouri landowners. He opened a consumer protection investigation into the project in June. (See Missouri AG Opens Inquiry into Grain Belt Express.)

Bailey issued a statement saying his office has “won a battle in the war for Missouri landowners” in what he termed an “unconstitutional land grab.”

“If Invenergy still intends to force this project on unwilling landowners, we will continue to fight every step of the way,” he threatened.

The project’s developers filed a lawsuit against Bailey July 16, arguing that he does not have the authority to investigate Grain Belt Express or to interfere with the Missouri PSC’s final order.

Invenergy says the $11 billion project would provide $52 billion in energy cost savings over 15 years, create 5,500 jobs and power up to 50 data centers.

A 2022 economic analysis conducted for Invenergy found that the project would result in $20 billion in total investment and create more than 20,000 temporary jobs and more than 400 permanent jobs in Illinois, Kansas and Missouri.

Invenergy says the Grain Belt Express would move a “diverse mix of energy” from Kansas to Indiana. The project would save money and strengthen reliability for 29 states and D.C., and more than 40% of Americans, it said.

The project would create links between the SPP, MISO, Associated Electric Cooperative Inc. and PJM grids.

Grain Belt Express has been under development since 2010, when the now-defunct Clean Line Energy first proposed the transmission line. After years of regulatory, legal and political hurdles, Clean Line sold the project to Invenergy. (See Invenergy Renewing Push for Grain Belt Express.)

Grain Belt Express announced nearly $1.7 billion in combined contractor awards to Quanta Services and Kiewit Energy Group.

FERC Approves MISO Interconnection Queue Fast Lane

FERC on July 21 approved a controversial MISO proposal to create a fast lane for certain reliability-related projects in the RTO’s interconnection queue — just two months after rebuffing an earlier version of the plan (ER25-2454).

The commission in May rejected the first iteration of the Expedited Resource Addition Study (ERAS) proposal, which was designed to speed up interconnection of resources that state regulators have identified as necessary to ensure resource adequacy in areas under their oversight.

In its May decision, the commission found the original ERAS plan lacked clarity around standards for identifying true RA projects and that — absent a cap on potential applicants — the expedited process was at risk of becoming bogged down with too many proposed projects. (See FERC Rejects MISO’s Interconnection Queue Fast Lane.)

Responding to those concerns, MISO quickly developed a revised proposal that caps the ERAS fast lane at 68 project requests and includes a provision requiring the RTO’s relevant electric retail regulatory authorities (RERRAs) to verify in writing that a project will either address an RA risk or help load-serving entities meet previously unexpected load growth.

Of the 68 slots, MISO proposed that a maximum of 10 would be carved out to accommodate requests from independent power producers that have agreements with entities other than LSEs, while eight will be dedicated to requests for resources intended to serve retail-choice load.

The RTO also proposed to cap the number of expedited studies to just 10 per quarter and limit transmission service requests to 150% of the need identified by a RERRA. It also made clear the ERAS process would be a temporary fixture, concluding at the earlier of either August 2027 or when the queue is cleared.

While MISO’s rapid turnaround on the revision earned support from the RTO’s vertically integrated utilities, it provoked protests from independent power producers and clean energy groups, who argued the newer plan still retained “many of the shortcomings” of the earlier version while introducing additional legal concerns. They also argued it still offered “preferential access to thermal resources at the expense of renewable resources.” (See MISO’s Queue Fast Lane, Take 2, Nets Déjà vu Arguments.)

Michigan’s Public Service Commission also opposed the plan, arguing it lacked “sufficient enforcement of shovel readiness and project completion” and that a provision to cap the megawatt value of expedited projects at 150% of an identified RA need might exclude meaningful participation by developers of renewable energy projects, which have lower capacity factors than thermal projects.

In its comments to FERC, Invenergy argued the new proposal still vested RERRAs with “nearly unbounded discretion to select projects, without any objective criteria to judge whether such projects are capable of satisfying MISO’s resource adequacy needs.”

But the revised plan had strong backing among MISO’s utilities, among them Alliant Energy, Ameren, Big Rivers Electric, Consumers Energy, DTE Energy, Northern Indiana Public Service Co. and Ottertail Power.

‘One-time Design’ Weighs Heavily

FERC’s July 21 order found the eligibility requirements set out in the revised proposal were adequate to “deter speculative interconnection requests from entering the ERAS process and minimize disruption” to resources already sitting in the definitive planning phase of MISO’s existing interconnection process.

“We find that MISO’s revised ERAS proposal sufficiently addresses these concerns identified in the May 2025 order by capping the number and size of ERAS projects, strengthening the RERRA verification requirement, [and] requiring ERAS interconnection requests to be located in the same local resource zone as the resource adequacy or reliability need that it will address,” the commission wrote.

“Additionally, we note that the limited, one-time design of the process weighed significantly on our decision here,” it added.

The commission also found that MISO had “strengthened” the “notification” requirement in the initial ERAS plan “to better ensure that RERRAs affirmatively verify interconnection requests will address specific resource adequacy needs that are not otherwise being addressed.”

The commission said it was “reasonable and appropriate” for MISO to allow RERRAs to select the ERAS projects and “implement their own processes for making such determinations, as this approach strikes a reasonable balance between state authority over resource procurement and commission authority over generation interconnecting to the interstate transmission system. Accordingly, we find that it is not necessary for MISO to establish scoring criteria or a ranking process for proposed ERAS projects, as protesters suggest.”

The commission rejected the argument by IPPs that the proposal intrudes on the commission’s exclusive Federal Power Act jurisdiction over the transmission service terms and conditions set out in MISO’s tariff.

To support their argument, the IPPs cited the U.S. Supreme Court’s Hughes v. Talen Energy Marketing decision, which held that the Maryland Public Service Commission’s authority over generating facilities did not allow it to “exercise control over the terms and conditions of interconnection service.”

“We find that the revised ERAS proposal is permissible under Talen because RERRA participation in the ERAS process would be wholly pursuant to a commission-jurisdictional process (i.e., the generator interconnection process), proposed by MISO and approved by the commission — not by state authorities — and under which a [generator interconnection procedure] is on file with the commission and any future revisions would be subject to commission approval,” FERC wrote.

The commission also rejected the contention that the proposal violates the “filed rate” doctrine because it allows states — through their RERRAs — to set the criteria for determining a resource’s participation in ERAS without subjecting that criteria to FERC approval.

“NextEra and MISO IPPs argue that the revised ERAS proposal violates the filed-rate doctrine because it allows RERRAs to establish criteria that would not be on file with the commission and that would determine whether or not an interconnection request is eligible for ERAS. We disagree. We find that the revised ERAS proposal does not present a filed-rate doctrine concern because it provides adequate notice of the ERAS eligibility requirements, including the RERRA verification requirement,” the commission wrote.

MISO intends to kick off the first ERAS process on Sept. 2.

Report Details Cost Savings of Heat Pump Rates for Mass. Consumers

Strong winter discounts on electricity delivery rates are needed to more fairly charge Massachusetts homes with heat pumps for their share of grid costs, according to a new report commissioned by a coalition of environmental groups. 

Written by climate policy think tank Switchbox, the report estimates that heat pump owners are being overcharged by an average of 23% during the heating season and finds that seasonal discounts could make electrified heating cheaper than natural gas heating for most residential consumers. It also finds that heat pump rates could help address significant cost barriers to heat pump adoption in the state. 

“Heat pump customers are subsidizing everybody else, and that’s why they’re being overcharged,” Juan-Pablo Velez, one of the authors of the report, said during a webinar July 22. 

Because New England has a summer-peaking power system, incremental demand during the heating season generally does not add to the cost of the grid, he said. However, volumetric delivery charges incurred during the winter frequently cause heat pump owners to pay more than their fair share of system costs, Velez said. “There is plenty of capacity to go before we run out of room with the existing [winter] capacity,” he said.  

ISO-NE forecasts the region transitioning from summer-peaking to a winter-peaking system by the mid-2030s, largely because of heating electrification. The timing of the shift likely will depend on the pace of heat pump adoption. 

The Massachusetts Department of Public Utilities already has directed the state’s investor-owned utilities to adopt specific heat pump rates. However, advocates for heating electrification argue that these rates do not fully address the issue of overcharging heat pump owners and have urged the DPU to direct the utilities to roll out steeper discounts aimed at more closely calibrating delivery costs with the grid impacts of electrified heating. 

In December, an interagency working group recommended that the DPU require the utilities to establish more aggressive winter heat pump discounts. (See Mass. Electricity Rates Working Group Issues Recommendations.) 

Under this updated discount, houses with heat pumps would pay roughly the same delivery costs as those heated by gas during the heating season. Supply costs would not be affected by the discount, and heat pumps still would pay for their full supply costs throughout the year. 

Kyle Murray, director of state program implementation at the Acadia Center, emphasized that heat pump rates do not represent a “handout to heat pump owners.” 

“Even though heat pump owners are using more energy than their non-heat pump counterparts, they’re not actually causing more stress on the system,” Murray said. “Heat pump rates just simply represent fairness in ratemaking.” 

The DPU in March opened an investigation into requiring new heat pump rates following the 2025/26 heating season (DPU 25-08). In comments in the proceeding, the Massachusetts Department of Energy Resources supported the working group’s proposed rate, writing that the lower, DPU-approved heat pump rate “would provide approximately one-third to one-half the savings each winter-heating season as compared to the [working group’s] proposed heat pump rates.” 

The Switchbox report found that “across all homes in Massachusetts, the median electric bill for heat pump customers would decrease by 12% under the DPU’s 1.0 rates and by 23% under DOER’s proposed 2.0 rates.” 

Under default rates, about 55% of customers switching to a heat pump would see an increase in their annual energy costs, the report found. Adopting the DPU-approved heat pump rate would improve this cost comparison, reducing annual energy costs for about 64% of customers that make the switch, the report notes. 

Unsurprisingly, the report found that the higher discount rate supported by the DOER would bring the greatest savings for heat pump owners and estimated that 82% of Massachusetts households converting to heat pumps would save money under the rate. 

Massachusetts has set aggressive targets for heat pump deployment and will need to significantly accelerate adoption in the coming years to meet its climate targets. The state estimated in early 2025 it will need to double its rate of heat pump conversions between 2025 and 2030 to meet its deployment goals. 

Seasonal heat pump rates likely will be a short-term solution for the state as its utilities work to deploy advanced metering infrastructure, speakers at the webinar noted. 

“In about three or four years, everybody in Massachusetts should have an advanced meter,” which will require a new set of rate structures, said Larry Chretien of the Green Energy Consumers Alliance. He added that while seasonal heat pump rates may be a relatively short-term solution, they are an important tool for eliminating excessive cost burdens on heat pump owners over the next few years. 

WRA Data Center Report Proposes Mandatory Clean Transition Tariffs

With data centers contributing to “staggering load growth” for Western utilities, a new report suggests that more utilities adopt clean transition tariffs for data centers or even make the tariffs mandatory for certain large customers.

The proposal is one in a set of recommendations from Western Resource Advocates, which released its report, “Data Center Impacts in the West,” on July 22.

The report examines seven of the eight largest utilities in the Interior West: Public Service Company of Colorado, Public Service Company of New Mexico, NV Energy, PacifiCorp, Arizona Public Service, Salt River Project and Tucson Electric Power. These utilities are seeing a surge in large-load interconnection requests, and data centers are the largest factor in their load growth, the report says.

“Data centers are driving staggering increases in electricity demand,” WRA says in its report.

And the surge in demand is a threat to climate progress, unless it can be met with clean energy resources, according to WRA. That’s where clean transition tariffs can play a role.

“If properly designed, these tariffs can enable data centers to do more than just mitigate their climate impacts with conventional clean resources like solar, wind and battery storage; they can help drive innovation by scaling new clean technologies,” the report says.

The report notes that companies such as Google, Meta and Amazon have corporate climate and clean energy goals — along with “expansive financial resources.” Under a clean transition tariff, a utility may develop new, clean resources on behalf of a large-load customer, with the large customer paying any premium cost of the clean resource.

For example, Nevada regulators in March approved NV Energy’s clean transition tariff, a framework developed in partnership with Google. NV Energy added to its integrated resource plan an enhanced geothermal energy project from Fervo Energy that will help power Google’s northern Nevada data center. Without Google’s involvement, the utility would not have included the project because of its cost. (See Nevada Regulators Give Nod to NV Energy Clean Transition Tariff.)

WRA said clean transition tariff structures should be developed before a data center asks for interconnection and clean resources, because fast interconnection typically is a priority for the centers.

Only zero-carbon resources should be eligible for the tariff, the report says. One approach for finding resources would be for the utility to issue a request for proposals based on its completed IRP, select resources to serve customer loads and then make any resources not selected available to customers under its tariff. Utilities also could solicit bids for resources under their tariffs between IRP cycles.

Regulators should encourage utilities to develop clean transition tariffs, WRA says, and they could even consider making them mandatory for larger loads or those that are steady around the clock.

Surging Demand

The seven utilities’ energy demands are projected to be 32% higher in 2030 and 55% higher in 2035, compared to 2025 levels, representing a compound annual growth rate of 4.5%. Those figures are significantly higher than what utilities predicted just a few years ago.

The growth rate also is higher than the rates projected by WECC (2.1%) and Grid Strategies (2.4%), which looked at regional and national trends, respectively.

The difference among the forecasts could mean that utilities in the WRA study are overestimating their load growth, the report says, or that they are “burgeoning hubs” for data centers with concentrated load growth.

As for peak demand, the utilities now expect a peak of 9,500 MW in 2030, 19% higher than in 2025, and 16,900 MW in 2035. The projected compound annual growth in peak demand is 2.9%.

The WRA report makes other recommendations for utilities and regulators, including:

    • establishing best practices and requirements for utility load forecasting;
    • revising IRP processes to better accommodate the rapid and uncertain nature of data center growth;
    • allowing data centers to install behind-the-meter clean resources and storage systems; and
    • developing interconnection standards that allow for load interruption in exchange for faster interconnection.

NextEra Energizes 2nd Competitive Project in SPP

NextEra Energy Transmission (NEET) has completed the second of its three competitive projects in SPP’s footprint, the 92-mile, 345-kV Wolf Creek-Blackberry project in Kansas and Missouri.

NEET Southwest, a NextEra subsidiary, confirmed in an email to RTO Insider that the project was energized on July 16. It said the project was completed “within budget” and nearly five months ahead of SPP’s required in-service date.

The project was awarded to NEET Southwest in October 2021. The developer’s bid came in at $85 million, far below the high proposal of $151 million. (See “Expert Panel Awards Competitive Project to NextEra Energy Transmission,” SPP Board of Directors/Members Committee Briefs: Oct. 26, 2021.)

Matt Pawlowski, NEET’s vice president of development, celebrated the announcement during the July 17 Strategic Planning Committee meeting.

Interrupting himself mid-comment, Pawlowski said, “Did I mention that we energized Wolf Creek to Blackberry a couple days ago? I’m sorry, I think I forgot to mention that earlier. Did I? Did I mention that yet? No? OK.”

In January, NEET Southwest also energized the Minco-Pleasant Valley-Draper project, a 48-mile, 345-kV transmission line in Oklahoma. NEET submitted a winning bid of $55 million for the project, which was awarded in 2022. (See “Directors Approve RTO’s 4th Competitive Project Under Order 1000,” SPP Board of Directors/Markets Committee Briefs: April 26, 2022.)

The projects are the only two of five approved by SPP under FERC Order 1000 that have been completed.

SPP also has awarded NEET Southwest Crossroads-Hobbs-Roadrunner, a 137-mile, 345-kV project in Southwestern Public Service Co.’s service territory in Texas and New Mexico. NEET’s $291 million bid was higher than incumbent SPS’ $220 million proposal, but the former offered a one-year construction timeline. (See SPP Awards NextEra 3rd Competitive Project.)

The project is scheduled to be completed by mid-2026.

PJM Capacity Prices Hit $329/MW-day Price Cap

PJM capacity prices soared to $329.17/MW-day (UCAP) RTO-wide for delivery year 2026/27, hitting the price cap approved by FERC after prices rose nearly 10-fold in the July 2024 auction. 

The clearing price is the highest in PJM history and an increase of $59.22 (22%) from last year’s record for the RTO. 

Prices would have hit $388.57/MW-day without the cap, PJM said in its report on the auction. The cleared supply totals $16.1 billion, up 9.5% from the $14.7 billion last year.  

“This is a continuation of trends that we’ve been seeing: a tightening of the supply and demand conditions,” Stu Bresler, executive vice president of PJM market services and strategy, said in a press briefing after results were announced July 22.  

PJM’s forecast peak load for 2026/27 increased by 5,446 MW from last year due to data center expansion, electrification and economic growth. “It’s probably a true statement to say that the majority of the demand increase we saw was … those data center additions,” Bresler said. 

However, prices fell in the Baltimore Gas and Electric (BGE) and Dominion zones, which cleared at $466.35/MW-day and $444.26/MW-day respectively last year. Thus, although the increased capacity costs will boost many retail customers’ bills by 1.5 to 5%, Dominion customers could save money, Bresler said. 

Supply offered dropped 500.5 MW (UCAP) to 135,191.8 MW. New generation and uprates totaled 2,669 MW, the first increase in the past four auctions. In addition, 17 generating units with 1,100 MW of Capacity Interconnection Rights withdrew their retirements since the 2024 results were announced. 

“We were pleased to see the new resources and the uprates that came in,” Bresler said. “We’re pleased to see the reversals of retirements, because that’s the kind of thing we need and the kind of thing that one would expect from the collection of information that’s out there, including the results of the last capacity auction.” The Base Residual Auction (BRA) procured 134,311 MW of unforced capacity generation (UCAP) and demand response. Regions under the Fixed Resource Requirement acquired an additional 11,933 MW (UCAP) for a total of 146,244 MW (UCAP). 

The reserve margin is 18.9%, 309 MW ICAP lower than the target of 19.1%. 

Cleared resources were dominated by natural gas (45%), nuclear (21%) and coal (22%), with contributions from hydro (4%), wind (3%) and solar (1%). Declining fleetwide accreditation values pushed the amount of supply offered down by about 326 MW from the 2025/26 BRA. PJM’s auction report stated that 3 GW less gas was offered in the 2026/27 auction. 

An additional 2 GW of wind generation cleared in the auction, followed by 867 MW of coal and 578 MW of oil. While the amount of DR offered was nearly flat, the resource class saw a significant drop in its effective load-carrying capability (ELCC) rating, causing the amount of UCAP clearing to fall by 224 MW. 

Bresler said almost every resource that submitted offers cleared, aside from one that had its minimum offer set above the maximum clearing price. He said the results follow a trend of tightening supply and demand in recent auctions, which PJM has argued could lead to a capacity shortfall in the 2029/30 delivery year. 

“I think this auction, just as the last one, served its purpose and very transparently reflected supply and demand,” Bresler said. 

RMR Impact

Bresler said including generators on reliability-must-run (RMR) agreements as supply helped dampen prices and reduced constraints, allowing BGE and Dominion to clear along with the rest of the RTO. 

“I think that there was a significant impact from including the RMRs at zero [dollars] in the supply stack, and … there were probably transmission upgrades going into place that changed the transmission import capabilities for those two zones as well,” Bresler said. “So, even without the lower cap, we still would not have had price separation in this auction.” 

In the 2024 auction for 2025/26, the clearing price for most of the RTO jumped to $269.92/MW-day, the result of load growth, generation deactivations and changes to risk modeling that shrank reserve margins. (See PJM Capacity Prices Spike 10-fold in 2025/26 Auction.) The 2024/25 auction had seen a price of $28.92/MW-day for most of the RTO, with BGE hitting $73/MW-day. 

Pa./PJM Settlement Lowered Clearing Prices

The 2026/27 auction design has been the subject of several rule changes and FERC complaints, including a settlement between PJM and Pennsylvania Gov. Josh Shapiro (D) to lower the maximum clearing price to $325/MW-day and establish a $175/MW-day floor. The settlement is effective for the 2026/27 and 2027/28 auctions (ER25-1357). (See FERC Approves PJM-Pa. Agreement on Capacity Price Cap, Floor.) 

Base Residual Auction clearing prices by beginning delivery year for the RTO, EMAAC, SWMAAC and MAAC Locational Delivery Zones. All four LDAs cleared at $329.17 for 2026/27, a $59.25 (22%) increase from $269.92 for 2025/26. | PJM

While the price band initially would be set at $175 to $325/MW-day, those values would be readjusted annually based on the accreditation of the reference resource. 

PJM and the governor argued the settlement would stabilize prices while several market changes are implemented. A complaint filed by Shapiro’s office said a lower maximum price was needed as the capacity market is unable to send adequate price signals under a compressed auction schedule and while the interconnection queue remains backlogged, preventing developers from bringing new supply in response to high prices (EL25-46). 

In a statement following the posting of the auction results, Shapiro said the settlement avoided “grossly excessive price increases” and saved consumers $8.3 billion. 

NRDC Senior Advocate Tom Rutigliano said the settlement prevented windfall payments to generation owners without compromising on reliability. He said the resulting price signals are ample to maintain existing resources and support new development and so long as there are barriers to new entry, such as the backlogged interconnection queue, higher prices would have served no purpose. 

In a statement, Illinois Citizens Utility Board Executive Director Sarah Moskowitz noted the settlement blunted capacity prices but argued the spike in capacity prices remains unacceptable and follows policy shortcomings at PJM. 

“The power grid operator’s policy decisions too often favor outdated, expensive power plants and needlessly block low-cost clean energy resources and battery projects from connecting to the grid and bringing down prices. This extended price spike was preventable. It ramps up the urgency of implementing long-term reforms at PJM and comprehensive energy legislation in Illinois, such as the Clean and Reliable Grid Affordability Act, to protect customers from price spikes that serve only to give power generators windfall profits,” she said. 

Auction Design Changes

PJM also received FERC approval to rework several market components, including modeling some resources operating on reliability-must-run agreements as supply in the capacity market (ER25-682). One of the factors that drove a spike in capacity prices in the 2025/26 BRA was two generators leaving the supply stack to begin running as RMR resources — the 1,289-MW Brandon Shores coal plant and the 843-MW H.A. Wagner oil-fired plant. (See FERC OKs Changes to PJM Capacity Market to Cushion Consumer Impacts.) 

The filing also established an RTO-wide non-performance charge rate and maintained the reference resource for the 2026/27 auction as a combustion turbine, rather than going through with a scheduled shift to a combined cycle unit. 

This is the first auction in which intermittent, storage and hybrid resources holding capacity interconnection rights (CIRs) were required to submit capacity offers. FERC granted PJM’s proposal to eliminate an exception from the capacity must-offer requirement for those resource types after the RTO said there was about 1.6 GW of capacity not offered. PJM argued that requiring all resources holding CIRs to submit capacity sell offers will prevent the exercise of market power and more accurately reflect supply and demand (ER25-785). 

Cleared new generation, uprates, imports and reactivated capacity by delivery year | PJM

The order eliminating the must-offer exemption also established an alternative market seller offer cap (MSOC) set at a resource’s capacity performance quantified risk (CPQR). The filing argued the change would allow intermittent and storage resources to more accurately reflect the risks they face by taking on a capacity obligation. 

Rising capacity clearing prices, and wholesale market costs generally, have been a source of consternation for consumer advocates and political leaders across many PJM states. Both Pennsylvania and New Jersey have raised the specter of leaving the RTO if reliability and cost concerns go unanswered. In July, nine governors signed onto a letter requesting that the qualifications for candidates to replace CEO Manu Asthana and to fill two open Board of Managers positions include the ability to restore public confidence and address “difficult decisions that could substantially raise consumer bills.” 

“In the past, other regions looked to join PJM due to its many strengths; today, across the region, discussions of leaving PJM are becoming increasingly common,” the letter said. “These unwelcome developments reflect legitimate concerns about PJM’s trajectory. We write, as a bipartisan group of governors elected by the many millions of citizens of our respective states, to tell you that fundamental changes, and new leadership, are needed to restore confidence in PJM’s ability to meet the many challenges of this moment.” 

Rutigliano said prices increased due to the combination of increasing data center demand and risk modeling capturing reliability issues with gas generation. Without the increase in wind generation, he said PJM would not have been able to meet reliability standards, underscoring the need for PJM to continue clearing its interconnection queue and for states and the federal government to address siting and permitting barriers. 

“The bright spot in this auction is a 75% increase in wind and solar. That jump will save PJM from an unacceptable risk of blackouts in 2026. PJM will stay reliable in 2026 thanks to the increase in renewable power. However, these low-cost resources still only account for 4% of the PJM’s supply, so PJM must continue to significantly speed up approvals of the 85 GW waiting to connect. The only real solution to higher energy prices is to keep adding more renewable energy and storage to the grid,” he said in a statement. 

Rutigliano told RTO Insider that states pushing for winterization of gas plants and PJM easing its restrictions on external resources selling capacity into PJM could buy the RTO at most two years before reliability issues become paramount, but the long-term solution lies in ensuring that renewable penetration accelerates. 

Advanced Energy United Policy Director Jon Gordon said the auction results show that new resources are needed to meet forecast demand. However, long interconnection queues prevent developers from bringing new supply to market. He said fast-track study processes, advanced transmission technologies, load flexibility and virtual power plants can facilitate new entry while PJM advances its cluster-based interconnection study process. 

“When prices go up, it’s meant to send a signal to energy developers: ‘We need more supply.’ But at the same time, PJM is holding up a big red ‘STOP’ sign to energy developers,” Gordon said. “Many projects have been stuck in the closed queue for over six years, a significant delay that adds additional risk and cost for developers and is likely to contribute to some otherwise viable projects never getting built.  

“Given the magnitude of this crisis, PJM, transmission owners, project developers and states need to do everything they can to move projects in the current interconnection process through to completion while finding additional ways to accelerate the interconnection process immediately. The high auction prices underscore the urgency of allowing project developers to begin to propose new projects for the queue that reflect today’s economic realities and come online in time to lower prices and ensure resource adequacy.” 

PJM Power Providers Group (P3) President Glen Thomas said the capacity market is successfully delivering reliability at a price that remains below surrounding regions. 

“The auction results show a market that is responding but remains tight. New generation is being added, existing generation retained, external capacity imported and retired capacity reactivated. The resource mix remains diverse, and it is important for the market to continue to send the signal that more capacity is needed. In the meantime, consumers should feel comforted that PJM has secured capacity commitments sufficient to maintain reliability through May of 2027 at a price below what many other regions of the country are paying,” he wrote in a statement. 

Electric Power Supply Association CEO Todd Snitchler said the auction prices show new resources, not political interventions, are urgently needed. 

“Higher prices are a signal to build more generation resources, and reflect increasing stress on the system,” Snitchler said. “In recent years, a combination of state and federal policy shifts and poor market signals led to the premature retirement of essential generation. Now, as demand grows and supply tightens, we can’t ignore the consequences of past decisions, and we must accept that reliability comes at a cost. Investment follows clear, consistent rules.”  

He argued that competitive wholesale markets have kept energy prices stable and efficient, whereas rising retail rates can be attributed to state policy mandates, as well as transmission and distribution spending not subject to the same transparency and market pressures. 

CATF Report Argues for ‘No-regrets’ Approaches to Meet Demand Growth

The power industry can meet growing demand in a timely and cost-effective way by deploying commercially available new technologies to increase the use of the existing grid and proactively planning for new infrastructure, a new report from the Clean Air Task Force said. 

The “Optimizing Grid Infrastructure and Proactive Planning to Support Load Growth and Public Policy Goals” report, prepared for CATF by The Brattle Group, highlights how to deal with demand growth from data centers, reshoring manufacturing and electrification. 

“By mobilizing demand-side flexibility, increasing the utilization of the existing grid and recognizing uncertain future needs through proactive planning, utilities and other grid operators can serve new loads while mitigating cost increases, thereby avoiding large bill increases for existing retail customers and protecting them from future risks,” the report said.  

“Combining more efficient capital utilization with more proactive planning thus offers a win-win proposition that protects customers, serves new loads more quickly, benefits utilities and grid operators, and supports a wide range of public policy goals for clean energy and economic development,” it said. 

Demand growth has come back at a time of stressed supply chains, compounded by long interconnection queues and other factors contributing to a slowdown in the speed and scale of deploying new resources, CATF Electricity Director Kasparas Spokas said in an interview. 

“We hope this report serves as a little bit of a menu of options of underutilized, but effectively no-regrets solutions that policymakers can evaluate and assess and hopefully adopt to both grow load while minimizing emissions and cost as much as possible,” Spokas added. “And so, the goal really here was to highlight … some of the near-term, no-regrets solutions that even if demand, which is highly uncertain, were not to materialize, would still be beneficial for ratepayers.” 

The paper offers actionable recommendations for grid planners, but it does not cover the full scope of potential reforms that could be needed under the new demand paradigm, such as changes to wholesale power markets or technology innovations that might become commercially viable. 

The pressure from demand is most acute with large loads such as hyperscale data centers and advanced manufacturing facilities because they often require access to vast amounts of reliable electricity and can start operating in a few years, while installing new infrastructure can take decades. 

Some of the quicker ways to help manage that rapid demand growth include use of demand-side resources, grid-enhancing technologies and advanced transmission technologies, as well as taking advantage of upsizing opportunities when power lines are refurbished and facilitating interregional trade, the report said. 

“Regulators and advocates just have to be very disciplined about requiring planners to effectively evaluate some of these [virtual power plant] demand-side solutions and advanced transmission solutions before committing to new buildout,” Spokas said. 

‘Political Feasibility’

Policymakers also should establish and expand efficiency and bill assistance programs for low-income customers and extend demand-side management to those customer classes. Another option is to establish rules that ensure customers with large loads don’t end up imposing stranded costs and financial risks on other customers, the report said. 

“I think that there’s a lot of very acute and near-term political pressure that policymakers and legislators and others are feeling with regard to increases in customer prices for electricity, increases in utility bills,” Nicole Pavia, CATF’s director for clean energy infrastructure, said in an interview.  

“We think that the political feasibility of implementing a broad suite of solutions kind of depends on gaining and maintaining political will for the energy transition,” Pavia said. “A lot of that has to do with how consumers feel about rates and if affordability is top of mind. And, so, we think some of the measures around affordability can help reduce the political pressure in terms of the increasing rates and utility bills.” 

Transmitting energy more efficiently, speeding up queues and addressing affordability concerns will help, but the power system eventually will need new generation and transmission. Those investments can be assisted by facilitating customer-sponsored generation investments and procurements, and collocating generation and load in “energy parks.” 

Planning and procurement process should pick the flexible, least-regrets solutions and, where needed, attract new investments in a timely manner. Load forecasts can be improved, clean energy development can be sped up by picking zones that can be connected proactively with transmission and deliberately planning the distribution system to more cost-effectively manage load growth. 

The return of demand growth also has increased interest in developing new natural gas-fired power plants around the country. 

“There are a lot of low-cost, no-regrets solutions that need to be considered before you get to the point of building a new gas plant,” Spokas said. “Once you get to that point as well, you need to consider the life of that asset.” 

Spokas thinks there’s “a lot of talk” about future gas-fired plants being built as “hydrogen-ready” without much consideration about the investments needed to make them so.   

“Where will the hydrogen come from? What will be the cost? So, I just think we all need to be very disciplined about what it takes to get to the point of saying, yes, a new gas plant is the solution,” he said. 

SPP MOPC Briefs: July 15-16, 2025

Members Shoot down Staff’s Proposal for Integrating High-impact Large Loads

LITTLE ROCK, Ark. — The SPP Markets and Operations Policy Committee resoundingly rejected a proposed tariff change to integrate large loads, pushing back against what some say is a rushed process outside of the normal stakeholder structure. 

The committee’s decision during its July 15-16 meeting won’t stop the revision request (RR696) from going before the Board of Directors during its next quarterly meeting Aug. 5. The board in April directed SPP staff to deliver a draft proposal during the meeting that helps integrate large loads, and that includes the “requisite stakeholder engagement.” (See “Cupparo Issues ‘Executive Order,’” SPP Board OKs 1-time Study for LREs’ Gen Needs.) 

The measure failed with only 53.7% approval. The Transmission Owner segment voted 11-5 for the measure, while Transmission Users voted 24-38. There were 12 abstentions. 

“As SPP members continue to receive or — really, in the case of some members — actually submit large load requests to us, we’ve needed to develop an effective policy that allows our members to be both responsive and competitive in the pursuit of these loads,” COO Antoine Lucas said in setting up the discussion, which ate up much of the meeting’s two days. 

“The large load policy is essential to responsibly allow this new industrial-scale electricity demand such as AI, data centers, advanced manufacturing and even energy-intensive production processes to integrate and operate,” he added. 

SPP slide showing growth of data centers in recent years | SPP

SPP says its 2025 Integrated Transmission Planning assessment includes about 10 GW of large loads, with an average size of 235 MW. The 2026 ITP includes more than 20 GW of large loads. 

The grid operator’s solution addresses gaps in current planning processes that have resulted in long wait times for projects, a lack of flexibility for limited connection or operation of load with system limits and cost uncertainty for transmission upgrades. 

The proposal is built around 90-day studies that allow faster load connection with certain reliability-driven conditions. The policy defines several large-load types or services, including: 

    • high-impact large loads (HILLs): any commercial or industrial individual load facility or aggregation of facilities at a single site, connected through one or more shared points of interconnection or points of delivery that can pose reliability risks to the grid. HILLs are nonconforming loads of either 69 kV or below with a peak demand of 10 MW or greater, or greater than 69 kV with a peak demand of 50 MW or more. 
    • conditional high-impact large load (CHILLs): the portion of a HILL that is receiving conditional high-impact large load service (CHILLS). This is intended for any HILL specifications that cannot reliably be served on a firm basis by existing designated resources or the current transmission system. CHILLs can exist at the same delivery point as firm load. 
    • CHILLS: a new transmission service available to HILLs to transfer energy to designated points of delivery to serve a transmission or network customer’s CHILL. The service will be available for yearly periods ranging from one to five years. 

“HILLs, CHILLs and thrills,” cracked one wag at the table. 

“A big principle in this is to have a path to firm service and balanced reliability,” said Casey Cathey, SPP’s vice president of engineering. “Our solution is to be the fastest connection study in the United States. We’ve looked at all of our fellow ISOs and RTOs. We work with them at least quarterly and share best practices. We also looked at Southern Co. We looked at a number of different areas that are challenged with similar challenges. … We want to provide transmission customers all the options necessary in the toolbox.” (See SPP Embraces Need for Speed to Meet Change Head-on.) 

SPP said the rules for large load’s cost allocation are consistent with the existing tariff and aim to minimize cost shifts from HILLs and CHILLs to other customers, aligning costs with those causing the upgrades. Those costs are directly assigned to the large-load customer until it secures firm service and is potentially eligible for base plan funding. 

CHILLS is billed on reserved capacity megawatts. If curtailed, charges adjust to the curtailed megawatts. 

In opening the second day of discussion on large loads, CEO Lanny Nickell expressed the need for speed and stakeholder input. To bolster his case, he said a person could draw circles around any 14 contiguous states in the country — as he did — and they would find more data centers in that region than in SPP’s 14-state service territory.  

Quoting ChatGPT, Nickell said the lost opportunity of a more-than-$1 billion capital investment for a 100-MW load amounts to more than the $1 billion: It also results in $200 million to $500 million lost construction and ongoing jobs, $50 million to $150 million of lost tax revenue over 10 years and $25 million to $75 million of lost grid and system value. 

“That’s the pure evidence. That’s the pure data,” he said. “That’s not something I really want to go to the governor and say, ‘You know what? Because we couldn’t get this done in a timely fashion, you just lost another 100 MW.’ 

“It was made clear to me several months ago [by members’ leadership] that this is an opportunity that we have to take advantage of, and if we don’t, it’s not only hundreds of millions to billions of dollars of lost opportunity if we don’t take advantage of this. It turns into a threat to our long-term existence. So that’s why we’re doing this, and that’s why this is urgent, and that’s why we’re doing it as fast as we can, but we still are trying to do it in a way that considers as much input as we can possibly get. We want every piece of input that we can get.” 

Over two days, including a half-day education session on large loads, SPP got that input. 

“My background has always been in operations, and I have extreme concerns about the reliability impacts of large loads. I don’t think we’ve thought of all the potential issues that can come from bringing these large loads on,” NextEra Energy’s Jeff Wells said, calling for more time. “I’m not saying we need three months. I’m not saying we need six months, but we need time to go to our experts in SPP that aren’t SPP employees. … We need to get their feedback, and we need to make sure that we’ve addressed all those concerns.” 

The Advanced Power Alliance’s Steve Gaw said SPP has not followed its stakeholder process. Members, some constrained by a lack of internal resources, have struggled to keep up as the policy and revision requests are developed at the same time. 

“There’s a reason why we need to prioritize things,” he said. “There are lots of investment dollars that have been lost because of road blocks to getting generation interconnected over the last several years. We would not have the same kinds of problems in having resources to match this load if we had done some additional work to prioritize things in that fashion as well.” 

Gaw also complained about the little time stakeholders have had to comment on the proposal’s “500-plus pages that were dropped on us” in late June. 

Noting that additional comments to the board on the tariff change are limited to two pages, Western Farmers Electric Cooperative’s Matt Caves asked whether the directive could be reciprocal. 

“Can SPP reduce this RR to, say, 100 pages?” he asked, drawing chuckles from staff and stakeholders. 

Olivia Hough, a regulatory strategist with City Utilities of Springfield in Missouri and MOPC’s vice chair, said the utility has formed a task force to go over the “voluminous” document. 

“It’s a lot to go through, and I understand that everyone maybe can’t read every single line item of it,” she said. “In whole, we want to see this move forward. We don’t want to miss out on the opportunity, and we think that the economic development potential and the challenge is worth it. I appreciate SPP’s commitment to putting this together at the same time that all the utilities are trying to develop their own frameworks.” 

“This is what SPS has been asking for: help to serve loads,” Southwestern Public Service’s Jarred Cooley said. “We really see that this is something that needs to be done. … We get the opportunity to get in front of FERC, get that feedback, figure out maybe what changes we need to make in the next iteration, and continue to push forward.” 

SPP’s Market Monitoring Unit also weighed in, saying that despite a “high level” of engagement with the RTO, it still has concerns that the proposal introduces risk to the market and other participants. It recommended risks be mitigated before any implementation and said it may identify additional risks and make further recommendations in the future. 

MOPC passed a motion to hold a special workshop and further consider RR696 no later than the end of September. The motion passed with 69.9% approval. 

COO Lucas emailed MOPC’s membership on July 18, laying out the several channels open to stakeholders who want to continue shaping the proposal before it goes to the board. SPP followed the email with a survey that members can use to share their concerns and recommended solutions. 

Members can also provide “high-level, strategic feedback” directly to the board. The feedback, using a template to ensure consistency and focus, is due July 28, the same date the grid operator is keeping the comment period open for RR696. Several working groups will each review the proposal during their scheduled meetings before Aug. 5. 

“Your continued participation in this process is valued and vital,” Lucas wrote. “You have our continued commitment to incorporate our stakeholders’ diverse perspectives as thoughtfully and equitably as possible. With your help, we aim to bring a proposal to the board that reflects both the urgency of this issue and the collective wisdom of our stakeholders.” 

Seams Cost Allocation Rejected

MOPC also rejected a proposed tariff change RR681 that would provide a cost-allocation mechanism for projects that don’t qualify as interregional projects and where SPP shares cost with one or more neighbors. The measure received only 54.9% approval. 

Aaron Shipley, the RTO’s senior interregional coordinator, said the proposal would make the process of building future jointly funded projects more efficient. He said it would be helpful to have the tariff change in place as SPP moves forward with the RTO’s Western expansion. 

“We would expect to receive efficiency in our processes by having this cost-allocation tariff mechanism already approved and thus eliminating individual at-the end-of-the-process cost-allocation debates that we have all been through before and provide significant risk at the end of a project and process,” he said. “This is something we’ve heard support from both stakeholders and regulators all the way from the beginning of this effort.” 

SPP’s membership first raised the issue in 2014, and it was later readdressed and confirmed through the Strategic and Creative Re-engineering of Integrated Planning Team’s (SCRIPT) work in 2020-2021. The RTO’s state regulators in October 2024 endorsed a seams policy white paper and directed staff to move forward with a recommendation to seek FERC approval. 

Stakeholders pushed back against RR681 over concerns the seams projects would be subject to the grid operator’s competitive process screening. They wondered whether staff would be able to take on the number of new planning processes feeding into the process. 

“I’m not opposed to following this kind of process in general,” American Electric Power’s Richard Ross said. “I’m opposed to just automating it so that it’s just there all the time. I think there may be some serious instances where we do things in one area that really don’t have greater benefits across the region, and so they ought to be allocated more. I do hope you will share with me that we ought to take a closer look at these on an individual basis.” 

Three RRs Endorsed

Members endorsed three other revision requests with varying levels of approval. 

RR693 received 76.5% approval, with SPS the only transmission owner of 17 to vote against it. The first phase of Surplus Plus and its suite of initiatives designed to accelerate the addition of new generation, the measure would quickly add shovel-ready incremental capacity at existing generating sites. The process would end when the Consolidated Planning Process begins in 2026. (See SPP ‘Blazes Trail’ with Consolidated Planning Process.) 

Under the proposal, priority requests would be queued higher than study clusters that haven’t started. The process would be conducted on an accelerated time frame, not subject to waiting for open seasons or processing as part of a cluster or from needs driven by other requests. 

Assuming FERC approval in October, the first requests would be submitted for a 90-day system impact study, with the first GI agreements issued by April 1. 

RR693 was an outgrowth of discussions at the Resource and Energy Adequacy Leadership (REAL) Team, said Steve Purdy, SPP’s technical director of engineering policy. 

“It is another tool in the toolkit for customers to be able to add new generation to the system, in addition to all of the existing processes that customers have available to them,” he said. “It’s a new process that will allow a customer to make a request and submit that outside of the DISIS [definitive interconnection system impact study] window.” 

RR689, which passed with 95.8% approval, was opposed only by four members of the Transmission Users segment. The proposal would reject market participant bids in the transmission congestion rights (TCR) market when sourcing from an electrically equivalent settlement location (EESL) to another settlement location on the system, or when the participant adds another bid from a settlement location back into the original EESL group that sinks at a different settlement location than the source. 

“We saw some concerning TCR bidding strategies in the TCR market,” said Micha Bailey, SPP’s manager of congestion hedging. “[EESLs] don’t have to be co-located, but electrically equivalent settlement locations basically have what we like to call unconstrained flow between them. So, you can basically get an infinite amount of TCR awards.” 

The MMU’s Raleigh Mohr said the Monitor was supportive of the measure. 

“Essentially, the message is this behavior is bad. FERC has ruled in other markets and in our market that this behavior is manipulative. We wanted to make sure that at this full representation body, that everyone heard that message,” he said. 

Antoine Lucas, SPP | © RTO Insider

A motion to include comments from The Energy Authority (TEA), speaking for six market participants, failed with only 35.8% approval. TEA recommended restricting implementation to auction revenue rights (ARRs) submitted for self-conversion to TCRs and not applying the restrictions to settling ARRs. 

“Our general principle is if a gaming opportunity exists and it can be closed, then it should be closed,” Mohr said, arguing against TEA’s comments. 

RR676 came within a percentage point of unanimous approval, receiving its only opposing vote from NG Renewables Energy Marketing. The measure creates a process for studying electric storage resource loads subject to SPP’s generator interconnection process and ensure compliance with FERC Orders 845 and 2023 and NERC reliability standard FAC-002-2.

“Today, our studies assess them for injection as a resource,” Evergy’s Derek Brown said. “One of the reasons for the enhancement is to better assess the impacts of these electric storage resources.” 

The RTO currently has 179 active storage projects, totaling 31 GW, in the queue. 

“We just think this is a crucial step forward for ensuring reliability and compliance of ESRs within the SPP transmission system,” Eolian’s Kyle Martinez said. “This is generation that can come online [and] provide ancillary service products off of the market.” 

DR Policy Endorsed

MOPC endorsed SPP’s demand response and load-responsible entity peak-demand assessment policy proposals, designed to help ensure realistic forecasts that reflect the effect of flexible load. 

Members amended the original motion to direct staff to prepare an RR based on the DR policy framework and conduct stakeholder reviews in conjunction with the LRE peak-demand assessment’s policy and RR. 

From left: SPP’s Chris Nolen, Natasha Henderson listen to Yasser Bahbaz during panel on demand response. | © RTO Insider 

Assuming their eventual approval, SPP plans to file both tariff changes together at FERC in early 2026 because of the “interdependency” between the two. A joint filing would provide a single, transparent foundation for resource adequacy and tariff evolution, staff said. 

The DR framework includes various metrics, criteria and thresholds for both reliability and market-registered DR to reduce consumption during tight grid conditions. 

The REAL Team approved the policy earlier in July during a special meeting. (See SPP REAL Team Endorses Demand Response Framework.) 

Consent Agenda Passes

MOPC endorsed RR692 by more than 91% approval after it was pulled from the consent agenda over timing concerns.  

The change allows multiple Phase 1 restudy iterations within the DISIS process in the face of growing interconnection clusters. The 2024-001 cluster has 380 requests totaling more than 100 GW of capacity, almost double the size of the previous largest cluster. 

“We’re seeing large amounts of dropouts between phases. Customers are being asked to make decisions about moving to the GIA portion of the DISIS analysis before we really have an understanding of what customers are going to remain when we’re through the entire process,” SPP’s Natasha Henderson said. “What’s proposed here is that we add additional Phase 1 studies. For instance, if 30% of the projects drop out in Phase 1, we would repeat Phase 1 again if we’re going to Phase 2, which adds stability to the mix.” 

The measure received 91% approval from members. 

The consent agenda included eight other revision requests that, if approved by the board, would: 

    • RR675: modify the local market power test for resources in a nonbinding frequently constrained area. 
    • RR677: add language that was inadvertently omitted from the settlement calculations changes approved in RR628 (Price Formation) that checks whether a resource is below its day-ahead market position. 
    • RR678: remove outdated references to quick-start resources, which have been replaced by fast-start resources, from the protocols because of updates in registration parameters. 
    • RR679: revise the ITP manual to remove conflicting language and references to the Model Development Procedure Manual’s new process. The new method allows for more data points to be included in calculating the number used for renewable resource dispatch, resulting in increased accuracy and confidence in the base reliability model. 
    • RR680: establish the incremental market efficiency use (IMEU) mechanism to provide revenue that offsets the increased operational costs of the West DC ties because of more frequent market-directed dispatches under the five-minute market. 
    • RR683: clarify and align governing document language with actual operational practices for notifying market participants during emergency conditions, including cleanup edits and new language allowing operations to issue notifications as soon as practical when emergencies are anticipated. 
    • RR685: update the Integrated Marketplace rules to allow SPP’s Western balancing authority area to join the Western Power Pool’s Reserve Sharing Group, lowering ancillary service costs and strengthening system reliability. 
    • RR691: revert tariff language back to its correct verbiage regarding changes for the RTO’s Western expansion.