Doubt Cast from Different Angle on Data Center Load Demand

A new analysis concludes there will not be enough computer chips produced in the entire world to supply the data centers some sources predict will be built just in the United States.  

The report is the latest of many doubts raised about sky-high expectations for data center load growth, and it warns about the huge cost of overbuilding the grid to meet the highest 2030 projections. 

The projections are varied, but most are large, and they are driving policy-making discussions. 

On July 7, the U.S. Department of Energy released a resource adequacy report noting that various organizations’ estimates of U.S. data center load growth by 2030 range from 35 to 108 GW.  

DOE adopted a midpoint assumption of 50 GW — plus 51 GW of non-data center load growth — to conclude the nation will be unable to meet projected demand “absent decisive intervention” because 104 GW of baseload retirement and only 22 GW of new baseload generation is planned by 2030. (See DOE Reliability Report Argues Changes Required to Avoid Outages Past 2030.) 

The DOE report called for rapid and robust reforms, lest adversary nations shape the digital norms and control digital infrastructure. 

But others say these are the latest overestimations of a trend and that Big Tech will not need all this electricity. 

“Uncertainty and Upward Bias are Inherent in Data Center Electricity Demand Projections” was written by London Economics International (LEI) and commissioned by the Southern Environmental Law Center (SELC). It also was released July 7. 

LEI totaled the projections of data center load growth from RTOs, ISOs and balancing areas covering 77% of U.S. electric load; surveyed global projections for semiconductor chip production and supply; and factored in potential increases in chip energy efficiency and computing capacity. 

The interior of Google’s data center in Council Bluffs, Iowa | Google

They concluded that under the implied projection of 57 GW of data center load growth, the U.S. would need to buy 90% of all chips produced worldwide from 2025 through 2030, and said that scenario is unlikely — the U.S. now buys less than 50% of the global chip supply, and other nations are ratcheting up their own data center development. 

LEI said these calculations support the anecdotal evidence that data center developers are submitting duplicate requests for grid interconnection in multiple jurisdictions that are being misinterpreted as unique requests. 

However, the totals are being treated as real by some policymakers. 

President Trump is easing and speeding the regulatory process in response to the national energy emergency he declared on the first day of his second term, in part to “power the next generation of technology” and “remain at the forefront technological innovation.” 

This speedup raises environmental and safety questions for some observers, as well as financial worries: If more pipelines, wires and generators are built than data centers need, someone else will have to pay for the resulting overcapacity. 

This is a central concern cited by SELC, which is headquartered in Virginia, home to the world’s largest concentration of data centers. 

“This report underscores a critical and ongoing concern: Inflated and speculative data center electricity demand forecasts in the Southeast are driving a dramatic and unnecessary overbuild of infrastructure that threatens to lock in fossil fuels, hike energy bills and crowd out more reliable, cost-effective clean energy,” said Megan Gibson, senior attorney at SELC. “Such speculative infrastructure investment creates significant economic risks for ratepayers, who ultimately bear the financial burdens.” 

Beyond the fundamental constraint of there not being enough semiconductor chips to supply the highest projections of data center growth, SELC noted, there are limits of powering a fleet of new data centers: There are equipment shortages for new large-scale natural gas-fired plants, nuclear reactors are expensive and slow to build, new-build coal appears unlikely, and wind and solar generation suffered major setbacks in the reconciliation bill Trump signed July 4. (See U.S. Clean Energy Sector Faces Cuts and Limitations.) 

Shelley Robbins, the Southern Alliance for Clean Energy’s senior decarbonization manager, said there is immense financial incentive for suppliers and developers to game the system and overestimate demand. 

“Data center growth has become a suspiciously convenient justification for pipeline and gas plant projects in the Southeast. Pipeline and utility companies make most of their money by building big things and then charging ratepayers for them,” Robbins said. “The result will be an expensive overbuild if we do not carefully scrutinize the genuine likelihood that data center loads will actually materialize.” 

New MISO Stakeholder Code of Conduct Forbids Rude or Callous Language

MISO debuted a code of conduct for its stakeholder meetings that forbids rude or callous language, deliberate meeting disruptions or disregarding committee chairs’ instructions.

MISO said that by attending stakeholder meetings, all participants agree to maintain professional conduct, identify themselves and organizational affiliation before speaking, take turns speaking and make sure everyone has the chance to talk, stay on topic according to meeting agendas and minimize distractions caused by electronic devices.

The RTO added that it would not tolerate disruptive or disrespectful behavior, including name-calling or personal attacks; “dismissive, sarcastic or demeaning remarks,” speaking out of turn and repeated interruptions, not following the meeting chair’s direction and “conduct that impedes discussion or intimidates participants.”

MISO said participants’ failure to follow the rules and “repeated or egregious violations” could result in restricted participation or being refused entry into stakeholder activities. The code applies to participants attending meetings virtually or in-person.

In response to RTO Insider’s questions, MISO did not elaborate on whether a specific incident prompted the new rules, if the RTO noticed a pattern of troubling behavior in meetings or whether the rules were in the works for a while.

“MISO values stakeholder input and we want to ensure our stakeholder process reflects that,” spokesperson Brandon Morris said in an emailed statement to RTO Insider.

MISO said reliable operations, competitive wholesale markets and collaborative transmission planning requires “engagement built on a foundation of mutual respect, professionalism and fair debate and dialogue to solve complex regional issues.”

The code states that MISO’s proposals and presentations and reports from staff delivered during meetings are “often works in progress meant to promote discussion, negotiation and consensus-building.” It also said meeting participants are expected to describe the contents of meetings “accurately and contextually” — with the understanding that opinions evolve — when sharing meeting information in news reports, social media posts, blogs or the like.

In a July 9 letter to stakeholders introducing the code, MISO CEO John Bear said he valued stakeholders’ diverse perspectives but said MISO stakeholder forums “also demand professionalism and mutual respect.” He asked the stakeholder community to keep engagement “constructive” and treat fellow stakeholders with courtesy.

“Every comment should further respectful, solution-focused dialogue that fosters trust, encourages collaboration and upholds the high standards we hold at MISO, and you hold as representatives of your organizations,” Bear wrote. “Disagreements are natural in these forums, especially when things are changing so quickly, but we all must remember that our engagement must be grounded in professionalism and respect, which, in turn, encourages fair debate and dialogue.”

Chang Highlights Interrelated Challenges Facing Industry at WIRES

FERC Commissioner Judy Chang said atthe WIRES Group Summer Meeting that it’s vital the power industry expands infrastructure to reliably and affordably meet rising demand.

“There is some misalignment in the interconnection process and the transmission planning process and the competitive market,” Chang said July 10 in Woodstock, Vt. “So, without getting into the details of dockets that I cannot discuss here, I do see this moment where there are challenges to the way we traditionally think about open access and competitive access to transmission, and that has created some logjams at the interconnection level.”

Chang said she is not a big fan of temporary fixes and would rather have the overall process improved, maintaining open access and competition so generators interconnecting the grid know the rules of the game.

“All of you in this room are at the front end of that issue, which is, how do we allocate the cost of interconnection-related upgrades?” Chang said. “How do you build them? How do you build them fast enough? How do you interconnect generators fast enough? And of course, the generators have their jobs to do as well.”

Industry and regulators need to come up with enduring solutions before it leads to a backlash, she said, with rising prices leading to a new wave of skepticism of markets and some states considering changing their longstanding market policies.

“I worry about how much states might be willing to compromise the open access and competitive access to transmission and competitive markets by pulling back and finding interim solutions, or by complaining about competitive markets not meeting the challenge of the day,” Chang said.

FERC looks at transmission planning, interconnection and wholesale market issues separately, but they all are related and, taken together, represent a comprehensive way of thinking about the power system, she continued.

“I think we still have a lot of work to do to make sure that we uphold competitive markets, open access to transmission, and make sure that we plan and implement and invest in transmission in an adequate way for the future,” Chang said. “These are the major challenges in front of us. Ultimately, we need to ensure reliable service to all customers while keeping the cost down.”

Transmission planning is key to addressing those challenges, and it comes with its own tensions of ensuring developers have the right access to capital without overburdening consumers’ wallets, she said.

“I’ve worked enough in the transmission sphere of the business to know that while we want to build infrastructure and beneficial infrastructure, if we go overboard, consumers will complain and this whole thing is going to backfire,” Chang said. “So, I’m concerned about that, and I hope you are keeping that in your line of sight as well. We have to be responsible in making sure that we’re building the most beneficial projects.”

Order 1920 provides a good basis for the industry to work through that balancing of interests, ensuring that the right mix of transmission is available to meet rising demand at a reasonable cost, she added.

Consumer groups need to understand why the transmission projects in long-term plans are picked, she argued, and the industry can help accomplish that by being transparent about why the plans were developed and what issues the projects are addressing.

Chang encouraged the transmission side of the industry to be creative and embrace new technologies, which fall under the umbrella of grid-enhancing technologies, and to explain to FERC what they want if they need with implementation.

“Whatever it is that you need, come and talk to us,” Chang said. “But I really see this as not only the future, but the present, right? I think the U.S. needs to lead in technological innovation, and you’re part of that equation. All the transmission companies are part of that equation.”

Chang has been at FERC for slightly more than a year, and she said the commission is busy with pending issues. Its staff members are stretched thin, as some took buyouts from the Trump administration to retire early, and they have not been replaced due to the commission abiding by a federal hiring freeze.

“Under Chair [Mark] Christie’s leadership, we’ve been able to keep working hard,” she said. “And I would say that it seems like that’s actually working out.”

Chang was one of three commissioners to join FERC about a year ago, and she said the group works well together with Christie. They all have different backgrounds and different areas of focus in FERC’s jurisdiction.

“We’ve been able to talk through all of those things,” she added. “When dockets before us are contentious, we take the time to listen to each other. And it’s been really just a great experience working with them.”

NEPOOL Markets Committee Briefs: July 8-9, 2025

ISO-NE continued work with stakeholders on its capacity market overhaul at NEPOOL Markets Committee meetings, giving updates on its proposals for generator retirements, market power mitigation, and resource qualification and reactivation. 

Deactivations

ISO-NE has modified its proposed timeline for resource owners to notify the RTO of resource retirements, cutting the notification lead time from two years prior to the capacity commitment period (CCP) to just one year. In the forward capacity market, resource owners historically have been required to submit retirement notices about four years prior to the relevant CCP. 

The change came in response to stakeholder feedback that a lengthy lead time for retirement notifications could create risks of premature retirements.  

“Some stakeholders wondered whether a shorter, irrevocable notice [would] provide more certainty to the market,” said Kevin Coopey, principal analyst at ISO-NE. He added that Potomac Economics, the RTO’s External Market Monitor, “voiced concerns with a comparatively long notification lead time and the lack of revocability.”  

He said a shorter timeline “allows resources to consider as much relevant information as possible, maintaining as much option value as possible, hence improving the probability of efficient deactivation decisions.” 

Under the proposal, retirement submissions would be binding, though resource owners would have the option to accelerate retirements. 

While some stakeholders have pushed the RTO to allow resource owners to rescind retirement notifications in some circumstances, ISO-NE said revocability could lead to “numerous thorny issues,” including coordination of transmission upgrades triggered by the resource deactivation and the release of capacity for interconnecting resources.  

“The shorter notification lead time achieves most of the benefits of allowing revocability while being significantly simpler in scope and execution,” Coopey said. 

Bilateral Trading

ISO-NE does not plan to include the development of new bilateral markets or changes to monthly reconfiguration auctions in the capacity auction reform (CAR) project, said Chris Geissler, director of economic analysis at the RTO. He said efforts would require a “considerable body of work that would jeopardize the ability to deliver the core changes” in time for the 2028/29 CCP. 

He added that the RTO expects the move to a prompt and seasonal capacity market to create new opportunities for bilateral trading. 

Some stakeholders have expressed interest in the development of new ISO-NE-administered voluntary forward markets, along with the introduction of sloped demand curves to monthly reconfiguration auctions to allow different amounts of capacity to be sold for each month.  

Geissler said the RTO may consider both initiatives after the CAR project is completed. 

Market Power and Mitigation

Also at the meeting, ISO-NE responded to feedback from the June MC meeting about the proposed approach to market power mitigation in a prompt auction. (See “Market Power Mitigation,” ISO-NE Internal Market Monitor Weighs in on Capacity Market Changes.) 

At the June meeting, the ISO-NE Internal Market Monitor recommended ISO-NE replace its pivotal supplier test with a “conduct and impact test framework,” making the case that the pivotal supplier test could cause the “over-mitigation of resources” as the balance of supply and demand tightens. 

Andrew Copland, economist at ISO-NE, said at the July MC meeting that the RTO still plans to include the pivotal supplier test in its prompt market tariff changes, adding that “developing a new mitigation framework falls outside the scope” of the CAR project. 

He said ISO-NE plans to “conduct a more general evaluation of mitigation in the capacity market after completing the CAR project.” 

Copland also provided details on the cost workbooks that suppliers are required to submit to show the costs included in their capacity offers and the use of an IMM offer floor price to mitigate buyer-side market power. 

Resource Qualification

In a prompt capacity market, ISO-NE plans to hold resource qualification activities “as close as possible to the annual auction and monthly trading activities to increase opportunities for new projects to participate,” said Matt Brewster, senior manager of capacity requirement and qualification at ISO-NE. 

For new resources, this will require the RTO to end its practice in the forward capacity market of monitoring the progress of non-commercial projects that have gained capacity supply offers. 

Brewster said ISO-NE plans to continue its existing critical path schedule (CPS) monitoring approach until June 30, 2028. After that deadline, ISO-NE would return non-commercial capacity financial assurance for non-commercial resources that cleared in FCA 18 and non-commercial resources that cleared in earlier FCAs if their “CPS milestones are substantially complete.” 

It would not return the financial assurance if a resource triggers termination before the deadline or is not meeting its CPS milestones. 

Some stakeholders expressed concern that this approach could incentivize non-commercial resources that otherwise would withdraw to refrain from doing so until after the deadline.  

For in-service resources, Brewster said ISO-NE still is considering adjustments to the resource audit requirements and how to estimate qualified capacity for resources with limited data on their performance. 

The audit requirements in the new auction framework would be based on resource class and intended to determine a resource’s qualified capacity and verify it is in service. 

Resource Reactivation

For retired resources, ISO-NE proposes removing the investment requirement for resource reactivation and requiring cost-of-service agreements retaining retiring resources to include “claw back” provisions which would take effect if a resource re-enters the market after its COSA expires. 

“In all other ways, a reactivation project would have the same interconnection, qualification and mitigation review treatment as any other new resource for entry and participation in the market,” Brewster said. 

Brewster noted that the existing investment requirement may deter re-entry or encourage unnecessary investments to meet the threshold and added that eliminating the investment requirement would “support the potential cost-effective and timely re-entry of previously deactivated resources.” 

Meanwhile, requiring claw-back provisions in COSAs would prevent incentives for resources owners to fish for out-of-market resource retentions, Brewster said. 

Next Steps

The RTO plans to present tariff changes for its qualification rules, annual auction mechanics, market power mitigation requirements and resource deactivations at the MC in August. It aims to vote on the changes in October and submit the filing to FERC before the end of the year.  

The second phase of the CAR project, focused on seasonal auction changes and resource accreditation, will continue throughout 2026. 

MISO Ready to Discontinue Seams Stakeholder Group

MISO appears poised to eliminate its Seams Management Working Group (SMWG) after about 15 years.

The Market Subcommittee voted via a simple majority at a July 10 meeting to sunset the group. MISO’s Steering Committee is set to vote at its Aug. 5 meeting to confirm or deny the cancellation.

Group chair Terry Jarrett, of the Missouri Joint Municipal Electric Utility Commission, said topics have dried up since 2023, with “minimal content due to most major seams topics being covered in other forums” and fewer seams data points provided by MISO to the group. Jarrett also noted that transmission planning at the seams has become a more attention-grabbing topic than seams management.

Jarrett said the “participation rate has dwindled over the years” to a dozen or two dozen attendees when other stakeholder committees attract a hundred or more.

Jarrett said from his tracking since 2022, there have been 13 SMWG meetings scheduled, with just two containing substantive discussions. Eight covered only “minimal content and participation” while three either were cancelled or downgraded from meetups into documents that MISO posted to its website for review, he said.

Jarrett added that the group has been lacking a vice chair since late 2022 due to low interest among the stakeholder community.

“There’s really nothing going on for the SMWG to do, and nothing on the horizon,” Jarrett said.

Jarrett said discussions on MISO’s seams issues should be transferred to Market Subcommittee meetings.

“Working groups are intended to be temporary. It is clear that the SMWG has successfully rallied MISO and the stakeholder community around seams coordination. With seams coordination effectively operationalized at MISO, there isn’t much value left for a dedicated seams working group,” Jarrett said.

Jarrett said at the group’s May meeting, he put a possible sunset of the group to a vote. Jarrett said despite a record 46 participants listening in, only eight individuals voted, resulting in a 4-4 stalemate.

MISO Independent Market Monitor Carrie Milton requested that MISO continue to focus on seams topics, including MISO and PJM’s ongoing effort to revise their 2004 freeze date used to determine flow rights and the issue of sharing capacity near the regional transfer limit between MISO Midwest and MISO South, SPP and other parties.

MISO to Axe Energy Efficiency from Capacity Market

MISO said it no longer will recognize energy efficiency as a capacity resource beginning with the 2026/27 auction. If approved, the action would satisfy a longtime recommendation from the RTO’s Independent Market Monitor.  

The grid operator said it needs to address market participants’ double counting of energy efficiency measures before the next capacity auction in April 2026. It plans to make a filing to FERC in early September to enact the ban by December.  

Research and Development Manager Geoff Brigham said while MISO will deny energy efficiency entry into the capacity auction, it will continue to allow energy efficiency to be reduced from load-serving entities’ coincident peak load forecasts. Brigham said energy efficiency resources often are part of utilities’ integrated resource planning and are recognized by states.  

After FERC proposed a landmark, nearly $1 billion penalty for American Efficient’s apparently bogus programs in PJM and MISO, MISO conducted an audit of all energy efficiency resources offered in the 2025/26 Planning Resource Auction. Brigham said staff found that a “significant portion” of the resources were offered into the auction while already being accounted for in LSEs’ coincident peak load forecast.  

MISO’s tariff stipulates that energy efficiency resources cannot qualify to be auctioned off when they’re already reflected in the RTO’s peak load forecast.  

The RTO said it confirmed with local distribution companies that “all savings derived from state-mandated energy efficiency programs are included in their coincident peak forecasts.” 

Brigham said MISO also found some resources submitted incomplete information that fell short of MISO’s measurement and verification standards. 

“MISO is in the process of adjusting each resource’s accreditation and capacity payments,” he said.  

Monitor David Patton has long said MISO should consider discontinuing energy efficiency capacity payments. He has said the benefits of energy efficiency exist for customers with or without the benefit of the MISO markets.  

At the annual OMS Resource Adequacy Summit in Chicago, Patton said energy efficiency in the capacity markets “has been a bit of a debacle.”  

“I think it’s time we follow through,” Patton said again at the March 2025 Board Week in New Orleans, where he referenced PJM’s move to eliminate energy efficiency from its capacity market. He said energy efficiency isn’t a “legitimate” capacity product.  

“We really believe that energy efficiency serves no purpose in MISO markets,” fellow Monitor Carrie Milton said at a Jan. 16 Market Subcommittee meeting. 

PUCO: Data Centers Must Guarantee Power Purchases from AEP Ohio

The Public Utilities Commission of Ohio has granted AEP Ohio’s request for tariffs requiring data center developers to financially guarantee they will use the electricity they are requesting. 

Customers requesting more than 25 MW of new power for data centers will have to pay for at least 85% of the energy for which they are subscribed — whether they use it or not — for eight years. A ramp-up period of up to four years will be allowed before the eight-year term. 

The July 9 PUCO ruling in 24-0508-EL-ATA is among the first attempts in the U.S. to address the high costs associated with the huge new power demands that may result from data center buildout. 

It seeks to ensure that other ratepayers are not stuck with paying for infrastructure upgrades made to accommodate demand that does not materialize as requested. 

Along with the financial guarantee mechanism, the new tariff will create a sliding scale for small and mid-sized facilities to allow for some flexibility; require data center owners to prove they are financially sound and able to meet the requirements; and impose an exit fee for projects that are canceled or fail to meet the terms of their contract. 

The state is seeing heavy interest in data center development, thanks in part to favorable policies. The Columbus area in the center of the state already has a strong concentration of these facilities. 

In March 2023, AEP placed a moratorium on data center service requests in central Ohio so it could analyze the impacts of this trend. 

In May 2024, it requested the data center-specific tariff, saying it was facing 30 GW of potential new load, some of it from sectors it considered to have elevated risk of not meeting their commitments. (See AEP Ohio Asks PUCO for Data Center-specific Tariffs.) 

Representatives of data centers and other industrial sectors criticized the tariff request as an unprecedented and potentially chilling move. On Oct. 10, 2024, they submitted a settlement proposal. 

AEP said some details in that proposal were problematic while other important details were omitted. On Oct. 23, the utility submitted its own settlement agreement, which revised or deleted some aspects of its original request. (See AEP Ohio Proposes Revised Data Center Tariff.) 

Signing on to the submission were PUCO staff, the state consumer utility advocate, an organization for large industrial ratepayers and a coalition of 54 community energy advocacy agencies. 

PUCO’s unanimous ruling adopts AEP’s settlement proposal, with some modifications to exit fees and other details. It directs AEP to file updated tariffs and lift the moratorium as soon as possible. 

“Today’s order represents a well-balanced package that safeguards non-data center customers on an industrial and residential level while establishing a dependable and reasonable environment for data centers to continue to thrive within Ohio,” PUCO Chair Jenifer French said in a news release. 

The industry membership group Data Center Coalition, which was an intervening party in the case, continues to maintain that no one industry or class of customer should be singled out for disparate rate treatment by a utility. 

“The decision is a stark departure from solutions enacted in other key data center markets and, more consequentially, is a deviation from the long-established, sound ratemaking principles that have carried both Ohio and the nation through periods of electricity demand growth and flat demand,” DCC Director of Energy Policy Lucas Fykes said in a statement. 

“The data center industry is committed to paying its full cost of service. DCC will continue to advocate for evidence-based solutions in Ohio and across the country that support data center development and advance an affordable and reliable electricity grid for all customers.” 

In a news release, AEP Ohio President Marc Reitter said the ruling would support the state’s growing tech sector and keep the industry in the U.S. while protecting other customers from shouldering the costs of providing power to it. 

“I am grateful for the collaboration of all the parties involved in this filing, which ultimately brings clarity and certainty for infrastructure planning,” he said. “We are looking forward to ending the moratorium and continuing to support development of more data centers in our service territory.” 

U.S. Clean Energy Sector Faces Cuts and Limitations

The winners and losers in the energy sector are delineated clearly by the One Big Beautiful Bill Act engineered by President Donald Trump.

But it remains to be seen how big the losses will be for wind and solar power, and how many caveats accompany the wins scored by fossil fuels.

On July 7, three days after he signed OBBBA into law, Trump issued an executive order with strict-sounding directions for carrying out the bill’s provisions targeting wind and solar energy, with critical details to be determined in weeks and months to come.

His on-again-off-again tariff threats — not least the 50% levy on copper imports he announced July 8 — could impose significant costs on the fossil fuel industry, which OBBBA clearly was intended to benefit.

What is clear now is that development of wind and solar power — which provided 14% of utility-scale generation in the United States in 2023 and accounted for 78% of capacity additions in 2024 — will become significantly more expensive.

New projects will need to begin construction by July 5, 2026, or be placed in service by Dec. 31, 2027, to qualify for the generous investment and production tax credits of the 2022 Inflation Reduction Act — a much earlier sunset than specified by the IRA but not as fast a termination as was sought by the strongest critics.

Wind and solar developers also will need to follow complex rules pertaining to fire-walling their projects’ finances from FEOCs — foreign entities of concern, particularly in China. (Norton Rose Fulbright needed more than 3,200 words for a FEOC explainer it published July 8. The Bipartisan Policy Center needed nearly 3,000.)

Peter Fox-Penner, an energy policy and strategy expert and a principal at The Brattle Group, told RTO Insider that the energy provisions of the 800-page OBBBA are a clear and significant threat to wind and solar power development, both of which are frequent verbal targets for Trump.

“I’m struck by what a direct assault this is, in particular on wind and solar, talking about the supply side of electricity,” Fox-Penner said. Combined with measures targeting residential energy efficiency and electric vehicles, OBBBA is a major change for many aspects of the energy sector, he added, as well as for the economy, domestic manufacturing, electricity ratepayers and the environment.

Not everyone is unhappy with OBBA.

Some other emissions-free technologies — geothermal, hydropower, storage — do not face the same rapid and drastic tax credit cutbacks as wind and solar.

And the fossil fuel sector — oil, natural gas, coal — has much to smile about.

“This is the most important energy bill in a generation,” American Petroleum Institute CEO Mike Sommers said in a news release. “President Trump has delivered on his promise to unleash American energy by unlocking opportunities for investment, supporting global competitiveness and opening lease sales onshore and offshore from the Gulf of America to Alaska.”

But many entities in the renewable energy and environmental advocacy sectors are not smiling at all:

    • “A vote that will live in infamy.” — Greenpeace
    • “This stands to be the biggest job-killing bill in the history of this country.” — North America’s Building Trades Unions
    • “This bill will be a major step backwards on energy security, prices and jobs in communities across the country.” — Clean Energy Business Network
    • “Ceding the race to build the clean energy economy of tomorrow to China.” — Sierra Club
    • “The clean energy provisions in the legislation President Trump championed will prove devastating.” — Environmental Defense Fund
    • “Congress has turned its back on the very industries that are adding the majority of the new electricity generating capacity to the grid.” — Solar Energy Industries Association
    • “Whatever promises the White House may have made when twisting the arms of some House Republicans, the Treasury Department has a duty to administer the law fairly, in a way that provides certainty to the businesses relying on these tax credits.” — National Resources Defense Council

The NRDC comment pertains to Trump’s July 7 executive order, in which he orders the strictest possible enforcement of OBBBA’s provisions on construction start dates, safe harboring and FEOCs.

And it alludes to Trump’s reported promise to the House Freedom Caucus — which was unhappy with even the limited leeway being given to wind and solar — that his administration would use its executive powers to the maximum extent in limiting wind and solar subsidies.

On July 3, U.S. Rep. Ralph Norman (R-S.C.), a founding member of the caucus, explained this in a CNBC interview.

A day after Trump’s executive order, Norman posted on Facebook: “This order dismantles the green energy giveaways pushed under the Biden administration — programs that propped up costly, inconsistent sources like wind and solar while leaving taxpayers on the hook and our grid exposed to instability.”

So what will Trump do now?

His executive order was strongly worded. But he often speaks in strong terms, and he changes his stance often.

Trump has long followed what is sometimes called the Trump Uncertainty Principle, keeping everyone guessing about his strategy so they cannot counter it.

He is hardly the first president with such an approach — President Richard Nixon had the Madman Theory — but Trump has embraced it more openly than most.

For the offshore wind industry, struggling to build momentum in the United States, the uncertainty presented merely by Trump’s re-election was enough that multiple developers paused their U.S. projects.

For the established solar and onshore wind industries, OBBBA presents a more nuanced challenge, particularly with projects that are not ready to break ground and might not qualify for subsidies under terms that may be revised or re-interpreted.

Some projects will be delayed or canceled because the financial calculations on which they are based will change for the worse.

Some of the domestic manufacturing facilities that were to be a legacy of the IRA will not be built. E2 counts $15.5 billion worth of cancellations from January through May, and that is just the publicly announced cancellations.

This in turn means continued reliance on foreign manufacturing that is potentially subject to Trump’s tariffs and OBBBA’s FEOC rules.

And there’s that word again — “potentially.” The beauty of creating uncertainty through vague wording and implied threat is that general trepidation cannot be challenged in court the way a stop-work order or funding clawback could be. The profit-driven private sector is left to ponder the odds as it weighs investment decisions.

“I do think we see some of that, in the sense that the developers and the financial community that finances the developers [are] aware of the uncertainties and the unpredictability of the federal policies now,” Fox-Penner said. “And I do think that has an incremental effect on them. I can’t quantify it, but I think it is there.”

He added: “It is, I think, part of a conscious policy to try and slow [wind, solar and EV adoption] down.”

Princeton University’s ZERO Lab projects $500 billion in lost capital investments through 2035 because of OBBBA and calculates Americans’ annual energy expenditures will be $52 billion higher in 2035. It projects that clean energy production will continue to increase but will be 820 TWh lower in 2035 because of OBBBA than it would have been in mid-range projections under Biden-era policies.

Fox-Penner agrees: Solar and wind generation will continue to be built. Not as much as there would have been, he said, and not enough to meet the growing U.S. demand for power, but dozens of new gigawatts still will come online, despite OBBBA.

Wind and solar are so much faster and cheaper to build than other types of generation that they will carry on, albeit at a slower pace, he explained.

“We have done some analysis at Brattle Group and others have done some analysis that shows that wind and solar construction will be adversely affected substantially by this bill. But at the same time, it will continue at a significant pace in parts of the country even without these subsidies, because it remains the cheapest form of raw kilowatt hours,” Fox-Penner said.

In regions where electricity is expensive, wind and solar still could be economical without federal subsidies, he added.

The problem in some of those expensive electricity markets is that the cost of energy development also is expensive, and there is no quick replacement at the state or regional level for the disappearing federal tax credits.

New York is such a place — it has grand ambitions for renewable energy and is placing much of the cost of decarbonizing the grid on ratepayers who already have some of the most expensive electricity in the nation. Further subsidies would be a hard decision to make.

The New York State Energy Research and Development Authority, which helps manage the state’s clean energy transition, told RTO Insider it has not fully analyzed the impacts of OBBBA but implied that they would be considerable.

A spokesperson said: “The new law puts thousands of jobs at risk and could cut billions in funding and impact overall market momentum. This bill undermines New York state’s demonstrated leadership in advancing clean energy technologies as a part of an all-of-the-above energy strategy including investments in wind, solar, hydroelectric and nuclear power to create a clean, affordable and reliable energy grid.”

Fox-Penner said there is no quick way to refill the pipeline and meet rising demand with other technologies if solar and wind projects are cancelled.

The backlog on large gas turbine orders is several years long, and construction of new nuclear generation may not scale up before the mid-2030s. Few observers expect anything beyond delayed retirements for coal, either.

“We do not see evidence of any significant expansion in coal to date, nor do we think it makes economic or environmental sense,” Fox-Penner said.

BPA Sued in 9th Circuit over Day-ahead Market Decision

A group of nonprofits sued the Bonneville Power Administration on July 10 in the 9th Circuit Court of Appeals over the agency’s decision to join SPP’s Markets+ instead of CAISO’s Extended Day-Ahead Market, saying the move will drive up costs and risk reliability in violation of federal statutes.

Represented by Earthjustice, the organizations asking the 9th Circuit to review and vacate BPA’s record of decision (ROD) include NW Energy Coalition, Idaho Conservation League, Montana Environmental Information Center, Oregon Citizens’ Utility Board and the Sierra Club.

The group alleges BPA rushed into its day-ahead market decision without considering the environmental impacts of its decision. The agency also now risks increasing costs for customers while ignoring its obligations to prioritize conservation and renewable power.

The group asks the court to vacate the day-ahead market decision and brings claims under the National Environmental Policy Act, the Pacific Northwest Electric Power Planning and Conservation Act, and the Administrative Procedure Act.

“Bonneville’s decision on markets will affect the transmission and generation of electric power across the West and is exactly the type of major federal action that should first consider the harms it could cause to our air quality, grid system reliability, fish and wildlife, etc.,” Jaimini Parekh, senior attorney with Earthjustice, said in a statement. “This is exactly why Congress enacted NEPA — to examine the consequences before acting. Here, however, the agency has completely ignored its obligations under federal law.”

The allegations will sound familiar to those who have followed BPA’s day-ahead market process.

In a news release, the group cites an analysis by state agencies in Washington and Oregon using BPA’s data that found the agency could have saved its customers $4.4 billion through 2035 by joining EDAM.

Those arguments follow a production cost study by Energy and Environmental Economics (E3) commissioned by BPA in 2024 that showed participation in EDAM could deliver the agency up to $106 million in greater benefits than Markets+. (See BPA Sticks to Markets+ Leaning Despite Study Showing EDAM Benefits.)

Proponents of EDAM have pointed to the E3 study and another by The Brattle Group — not commissioned by BPA — that found by 2032, the agency could earn $65 million in benefits from participating in EDAM versus an $83 million net loss in Markets+. (See Brattle Study Finds EDAM Gains, Markets+ Losses for BPA, Pacific NW.)

The suit argues that because EDAM provides a larger market footprint, BPA’s customers will miss out on significant cost savings, improved energy reliability and greater access to clean energy resources. EDAM also is “more geographically contiguous, its market participants include more of Bonneville’s historic trading partners and, consequently, the transmission system is better developed than is the case for Markets+,” the group claims.

“Moreover, Bonneville’s day-ahead market decision will likely require regional electricity providers to construct additional power generation facilities and/or increase operation of existing facilities, including natural gas, and coal plants, as a consequence of Bonneville’s participation in the smaller and less efficient, less diverse Markets+,” the suit states.

By joining Markets+, BPA also is leaving CAISO’s Western Energy Imbalance Market (WEIM) and will lose the benefits of participating in that real-time market, the organizations say.

Meanwhile, BPA has argued consistently its day-ahead markets process has been conducted with significant stakeholder input, noting in its final market decision issued in May that other electric utilities that have taken steps to join either Markets+ or EDAM have done so “without public process or transparency.” (See BPA Chooses Markets+ over EDAM.)

As for the production cost studies, the agency has contended those failed to factor in other key issues, like governance. BPA says the SPP market’s governance structure is “superior” to that of EDAM, despite ongoing efforts by the West-Wide Governance Pathways Initiative to relax the state of California’s oversight for CAISO’s EDAM and WEIM.

Still, the plaintiffs in the underlying suit claim BPA has prioritized governance over other obligations the agency is required to consider under law, such as protecting wildlife and promoting renewable energy.

The organizations also bring up the seams likely to arise after the launch of the two separate day-ahead markets, claiming BPA is contributing to the creation of artificial barriers to trade that will require complex negotiations between parties to ensure effective trade can continue.

However, BPA staff have noted throughout various public meetings that the agency is not solely responsible for creating seams and already manages a non-contiguous balancing authority area that spans six states that is adjacent to 18 other BAAs. BPA staff also noted the agency has more than 75 years of experience managing operations across seams, while acknowledging that day-ahead markets will add a new layer of complexity.

Reaction was swift:

“BPA’s decision to join Markets+ is inconsistent with its responsibility to maximize customer benefits in accordance with sound business principles,” said a statement released by Seattle City Light and attributed to Dawn Lindell, CEO and general manager. “Seattle City Light is deeply disappointed in the agency’s decision. BPA’s own record and analysis shows that Markets+ will increase costs for BPA and its customers. At a time when City Light and other utilities throughout the region are working to contain rising costs to meet growing energy needs, BPA’s disregard for the economic impacts associated with its day-ahead market decision is alarming. Our ratepayers will bear the burden of this decision as it increases energy costs $20 million to $40 million every year.”

When asked for a response, BPA said it doesn’t comment on active litigation.

SPP released a statement from Carrie Simpson, vice president of markets: “SPP is aware that a legal challenge has been filed regarding Bonneville Power Administration’s decision to participate in Markets+. We remain confident in the integrity of BPA’s decision-making process but respect the right of all stakeholders to have their concerns heard, and we trust the judicial process to appropriately consider the issues raised. We stand committed to working with BPA and others across the West to deliver reliable, efficient, and transparent market solutions that benefit the entire region.”

Stakeholders Mixed on Massachusetts Energy Affordability Bill

At a pair of recent events, clean energy advocates and a range of stakeholder groups expressed support for a sweeping energy bill introduced by Massachusetts Gov. Maura Healey while offering suggestions for avoiding “unintended consequences.”

The legislation is intended to provide immediate and long-term rate relief in the wake of high winter energy prices and amid concerns about high costs associated with the clean energy transition.

“Energy advocates have embraced many of the proposals in this bill, but as with any major piece of legislation, concerns have also surfaced about some of the particular provisions,” Tim Snyder of the Alliance for Climate Transition, a clean energy trade group, said during a webinar held by Advanced Energy United on July 8.

Snyder praised the Healey administration for taking a comprehensive and collaborative approach to addressing energy affordability in the bill and for being receptive to input and concerns.

“As the federal government guts financial support for renewable energy, it is essential that places like Massachusetts continue to set policy in a way that ensures the continued viability of the energy transition,” Snyder added.

Michael Judge, undersecretary of energy for the Massachusetts Executive Office of Energy and Environmental Affairs (EEA), said the administration has “generally received a pretty positive reaction to the overall thrust and direction of the bill.” He said the bill is a “starting point” for discussions, noting it has a long way to go in the legislative process.

“We want to engage with people and get this right, and so, where there are opportunities to make some adjustments, let’s talk through that,” Judge said.

The bill includes multiple policy changes, including an overhaul of clean energy procurements, authorization of new financing mechanisms for infrastructure investments and electrification upgrades, a reduction in net metering credits for public net metering facilities and the phaseout of the state’s Alternative Portfolio Standard (APS). The administration has estimated the legislation will save ratepayers in the state more than $10 billion over the next decade. (See Mass. Gov. Healey Introduces Energy Affordability Bill.)

Some of the most vocal concerns about the bill have come from the solar industry, which has opposed reducing net metering credits for projects that are already in development, along with a proposal to require all net metering projects to qualify for the state’s Solar Massachusetts Renewable Target (SMART) program.

During the webinar, Judge said the net metering changes are focused on reining in rates for public net metering facilities, which must be owned, operated or procured by a municipality or government entity. He said the changes would not affect residential, rooftop or community solar projects, which “would still receive roughly the same compensation that they receive today.”

At a lengthy legislative hearing on June 25, Valessa Souter-Kline of the Solar Energy Industries Association stressed that “all changes should be prospective to ensure that businesses and consumers who have made decisions based on what’s in place … don’t have retroactive changes.”

Jessica Robertson of New Leaf Energy said the proposed changes to net metering compensation and eligibility criteria, which would apply to projects that have not interconnected by Jan. 1, 2026, would affect those that have been stuck in the interconnection process for years.

Robertson said the company is developing two public net metering projects that submitted interconnection applications in 2018 and 2019 but “have been subject to yearslong interconnection delays.”

“Those projects finally have their interconnection agreements, but they won’t actually be interconnected until 2027 at best because of how long it takes to build those grid upgrades,” Robertson said. “Under the current bill language, these projects would have the rug pulled out from under them.”

She said retroactive changes would hurt investor confidence in the state and recommended that the changes should only apply to projects that submit their interconnection agreements after the bill was filed.

Ally Niphakis of SRECTrade said the bill’s requirement for all net metered systems to enroll in the SMART program could impose significant new costs associated with deploying the metering equipment needed to participate.

Also at the hearing, Clean Fuels Alliance America and the Massachusetts Energy Marketers Association, which represent the alternative fuels industry in the state, said the APS should not be repealed until the state implements its longstanding proposal for a clean heat standard.

“While electrification is an important pathway to reducing carbon emissions, it cannot be the only pathway,” said Stephen Dodge of Clean Fuels. “The APS program is currently the most cost-effective way to reduce carbon emissions immediately from the thermal heat sector.”

The state released a draft program framework for the CHS in 2023 and had announced plans to finalize the standard in late 2025, with the program taking effect in 2026. However, the administration has walked back this timeline; at the hearing, EEA Secretary Rebecca Tepper said there is no implementation timeline for the CHS, adding that “we continue to look at it, but right now it’s not ready.”

In contrast to the biofuels advocates, representatives of climate organizations applauded the proposal to eliminate the APS, arguing that the program, which includes support for combined heat and power systems, is not aligned with the state’s decarbonization targets.

Judge said the APS was “designed to support mostly natural gas-powered combined heat and power facilities” but has been expanded to support additional technologies, including fuel cells and heat pumps. He said recent analysis indicates the program is “not really driving a lot of new projects” and supports some projects with minimal climate benefits.

The legislation would also repeal the requirement for any new nuclear facilities in the state to be approved by a statewide ballot measure. This provision received a mixed response at the legislative hearing, with major climate groups largely refraining from weighing in on the issue.

“We want to be able to look at new nuclear technologies, particularly small modular reactors, as a solution to both our clean energy needs and energy affordability,” Judge said during the webinar. “We just see this as an unnecessary barrier to building these projects; these projects would still have to go through a very robust permitting process at the federal and state levels.”