October 30, 2024

NYC to Fall 446 MW Short for 2025, NYISO Reports

New York City faces a reliability margin shortfall of up to 446 MW in 2025 due to plant retirements and the delayed completion of the Champlain Hudson Power Express, NYISO said Friday in its Short-Term Assessment of Reliability (STAR) for the second quarter.

The STAR report for the five-year period ending April 15, 2028, forecasts rising loads due to increased electrification of transportation and buildings, continued economic growth following the pandemic and the expected retirement of generators under the state Department of Environmental Conservation’s “peaker rule,” which took effect in May.

NYISO CEO Rich Dewey told the New York State Reliability Council Executive Committee Friday that the ISO is projected to fall short of its transmission security margin, a measure of the power system’s ability to withstand disturbances such as short circuits or unanticipated loss of a generator or transmission line, while continuing to supply and deliver electricity. Dewey said the CHPE, which will deliver hydroelectric power to New York from Quebec, “would solve this problem, but its in-service date slipped to the spring of 2026.”

DEC’s peaker rule, approved in 2019, is intended to limit nitrogen oxides (NOx) emissions from simple-cycle combustion turbines.

As of May, 1,027 MW of affected peakers have deactivated or have limited capacity, while an additional 590 MW of Zone J peakers are expected to be impacted by the DEC’s rule beginning May 1, 2025.

Under baseline weather conditions (95 degrees Fahrenheit) in 2025, the ISO said the higher bound of expected demand will result in a deficiency of 446 MW over nine hours. The deficiency would be “significantly greater” if the city experiences a heat wave (98 F) or an extreme heatwave (102 F), the ISO said.

If the CHPE experiences further delays, more fossil fuel plants become unavailable, energy demands exceed forecasts or significant extreme weather events elevate loads, reliability margins could “continue to be deficient for the 10-year planning horizon,” the report said.

New York state’s growing electric system demand threatens future security margins. | NYISO

Because the DEC anticipated that peakers may need to remain online longer than required, it authorized NYISO to order a two-year extension through 2027 and an additional two-year extension through 2029, should these plants be needed for reliability.

Both Dewey and the report, however, emphasized that keeping the peakers online is a “sub-optimal solution” and would  be used only after NYISO exhausts all other possibilities.

Dewey said NYISO will work with transmission owner Consolidated Edison to develop solutions and will evaluate proposed solutions that will be solicited from developers throughout the summer. NYISO will review submissions, which could include generation and demand response, in the fall and decide on the best way forward during November.

Dewey confirmed that NYISO likely would return to the July 25 Electric System Planning Working Group with a more comprehensive statement regarding the near-term reliability need.

Con Ed said it is reviewing the STAR report and “remains committed to providing reliable, safe service for to customers, and supporting the state’s important clean energy transition.”

The report notes that although CHPE will help reliability in the summer, “the facility is not expected to provide any capacity in the winter.”

Statewide Shortages?

The Q2 STAR also found that New York could face a statewide deficiency of up to 145 MW by 2025, which could remain through 2033, because of the assumed unavailability of power plants complying with the peaker rule.

The ISO said additional large load interconnection projects in western and central New York are expected to increase 2025 demand by 764 MW. “If CHPE does not begin operation, the statewide system margin is projected to be deficient for all years 2025 through 2033 when considering the additional large loads,” according to the report.

During the NYSRC EC meeting, attendees worried about the Q2 STAR’s findings and questioned how projected deficiencies might impact NYISO’s future planning considerations.

Two attendees inquired about the peaker rule and whether it was simply easier or more economically viable to allow these emissions-producing plants to stay online.

Zach Smith, NYISO vice president of system and resource planning, again confirmed that extending the peaker rule was a “last resort,” and responded that this option would be selected only after “NYISO considers the backstop solution Con Ed is required to provide and reviews all solicited proposals.”

Mark Younger, president of Hudson Energy Economics, asked if NYISO has been providing adequate market demand signals to its resources and would reconsider current price signals to be based on more long-term forecasts.

Forecasted energy demands for NYC | NYISO

Dewey responded, “I think that that will be the subject of a lot of discussion over the next year and as we undergo the next demand curve reset.” The DCR occurs every four years and updates the assumptions that determine the installed capacity demand curves. (See FERC Accepts NYISO’s 17-Year Amortization Period Proposal.)

Roger Clayton, chair of the NYSRC’s Reliability Rules Subcommittee, asked whether NYISO would give greater consideration to nuclear resources.

Dewey responded that the Climate Leadership and Community Protection Act’s scoping plan included a notice on how nuclear energy should be investigated.  “Nuclear development could be solution for these challenges … but I am curious to see if [nuclear] gets any additional traction in discussions at the … Public Service Commission,” he added. The PSC recently ordered staff to identify technologies, like nuclear or hydrogen, which could keep New York in CLCPA compliance. (See NY Renewable Portfolio May Come up Short on Getting to Net Zero.)

Wes Yeomans, an NYSRC consultant, asked about the STAR’s statewide findings and if that future reliable marginal deficiency requires any immediate action by the ISO.

Smith answered that “the statewide margin is for informational purposes at this point and there is no action to take at this time,” adding, “we’re providing this as information of basically a need possibly to come.”

Gavin Donohue, CEO of the Independent Power Producers of New York, released a statement on the STAR’s findings, saying, “the pace of play is not keeping up with pace of promises, and this report makes that clear.”

“There have been repeated cautions from the NYISO regarding grid reliability, and this report highlights the reality that generator retirement cannot outpace the addition of new generation with the attributes needed by the NYISO to maintain reliability,” he added.

Massachusetts Considers Legislation to Ban Gas in New Buildings

The Massachusetts Joint Committee on Telecommunications, Utilities and Energy (TUE) held hearings last week on several bills that would expand the state’s 10-municipality demonstration project allowing cities and towns to ban fossil fuels in new buildings and major renovations.

The TUE Committee also took public testimony on a range of bills promoting building electrification and targeting fossil fuel consumption in buildings more broadly as the state looks to cut building sector emissions and meet its statutory climate goals.

Climate, public health and environmental justice advocacy groups spoke in favor of bills promoting electrification, while they opposed bills that would promote the use of biomethane or blended hydrogen in buildings.

Representatives from the gas, biofuel, heating oil and real estate industries, along with labor groups representing gas workers and plumbers, generally opposed the electrification bills and supported the inclusion of alternative and low-carbon fuels in building decarbonization programs.

The committee helped to craft an omnibus climate bill in 2022 that created a demonstration project allowing 10 municipalities in Massachusetts to ban fossil fuel combustion in nearly all new buildings. State law prohibits most towns from implementing all-electric building codes, based on a ruling by former state Attorney General Maura Healey (D), who is now governor.

Clean energy advocates are now pushing to expand the 10-town program, with many hoping to expand the option, or even pursue an all-electric code for new buildings, statewide. The 10-town limit agreed upon in the previous session was a political compromise between the legislature and then-Gov. Charlie Baker (R). Advocates hope the changing political makeup of the state, along with the ever-increasing need to reduce emissions, will spur the program’s expansion.

“We all know the urgency of action,” said Northampton City Councilor Alex Jarrett. “On Monday, I stood next to a farmer as she watched her equipment and her crops get washed away by what looks to be the third-highest flood event since 1950 on our local Mill River. All of her effort for the season was gone in a few minutes.”

Representatives of cities including Northampton, Salem, Somerville and Worcester expressed their desire to join the demonstration project, but they worried they will be unable to if it is not expanded. The demo gives priority to the 10 municipalities that pursued local bans prior to the 2022 law. Nine of the 10 municipalities are likely to be included in the project, leaving one open spot for additional applicants. And Boston also has expressed its interest in joining.

“It doesn’t make sense to build new buildings that will need to be retrofitted before the useful life of their heating, cooling and cooking infrastructure is through,” Jarrett said.

Advocates argued that it is unfair to allow disproportionately wealthy, white communities to participate in the demonstration project while lower-income communities of color are excluded.

“We’re a major environmental justice community; we shouldn’t have to wait,” said Worcester City Councilor Etel Haxhiaj, noting that the impacts of climate change disproportionately impact vulnerable low-income, nonwhite and disabled residents.

“Without state authorization to restrict new fossil fuel infrastructure in our city, we are completely unable to address our most significant source of emissions: our buildings,” Haxhiaj said.

Along with the need to reduce emissions, advocates for expanding the program cited the public health risks of burning fossil fuels like natural gas and propane in buildings.

Climate advocates from Mothers Out Front and Gas Transition Allies testify to legislators. | Massachusetts Joint Committee on Telecommunications, Utilities and Energy

“The evidence for the harms of gas stoves in homes related to pediatric childhood asthma is robust and has been well known for quite some time, with an increased risk of 42% in children that live in homes with gas stoves,” said Dr. Wynne Armand, associate director of the MGH Center for the Environment and Health and assistant professor at Harvard Medical School.

Armand highlighted a recent study that found gas stoves release significant levels of the carcinogenic chemical benzene during combustion, as well as a 2022 study that found uncombusted gas in the Boston area contained 21 chemicals known to be toxic to humans.

“This is an equity issue,” Armand said, speaking about her experience practicing primary care in Chelsea. “I see this every day, where my community has one of the highest rates of asthma in children, as well as the worst asthma outcomes and higher [emergency department] visits.”

Sen. Mike Barrett (D), chair of the TUE Committee, expressed his support for expanding the demonstration project and said he was in favor of allowing more towns to join during last year’s legislative session.

“Ten isn’t arbitrary, and it wasn’t the number favored by original proponents; it was what we could get,” Barrett said, adding that the legislation promoting the demonstration project originated in the Senate and that proponents may face greater opposition in the House of Representatives.

Meanwhile, those opposing the demo’s expansion include National Grid; the Propane Gas Association of New England; the Massachusetts Energy Marketers Association; the real estate association NAIOP; the Homebuilders and Remodelers Association of Massachusetts (HBRAMA); the Northeast Hearth, Patio and Barbecue Association; Plumbers & Gasfitters UA Local 12; and United Steelworkers Local 12012.

“We urge you to think twice and go slow before expanding the 10-community fossil fuel ban program because of the difficulties that already homebuilders are running into trying to electrify our homes,” said Benjamin Fierro, a lobbyist testifying on behalf of HBRAMA.

Fierro highlighted the results of an industry-sponsored report from the Wentworth Institute of Technology, Massachusetts Institute of Technology and HBRAMA that found that the state’s ‘municipal opt-in specialized stretch energy code’ — which features strict energy-efficiency standards but stops short of mandating electrification of new buildings — could increase the total costs for the construction of single-family homes by 1.8 to 3.8%.

Andrew D’Angelo, executive director of the Greater Boston Plumbing Contractors Association, argued that his organization was not coming to legislators “as shills to the fossil fuel industry or large corporations. We come here as working people and contractors that employ those people with concerns that some legislation, while well intended and altruistic, will come with some unintended consequences for families across the state.”

Tim Fandel of Local 12 advocated for an “all-of-the-above approach” to reducing emissions.

“In the absence of utilizing every option we have at our disposal, there is a real risk in not achieving the intended objectives — and yes, natural gas will play a role in our energy portfolio for many years to come,” Fandel said.

Kevin O’Shea, director of government affairs at National Grid, echoed this position, opposing the expansion of the 10-town demonstration project along with legislation that would impose a clean heat standard on the state’s gas utilities. The proposed standard would not allow utilities to comply using fuels like biomethane or blended hydrogen.

“It is too early to take viable decarbonization off the table that may be needed to meet the 2050 net-zero targets,” O’Shea said.

Ben Butterworth, director of climate, energy and equity analysis at the Acadia Center, argued that blending biomethane — also known as renewable natural gas (RNG) — and hydrogen into the gas network “would significantly impair the state’s ability to cost-effectively decarbonize the building sector.”

Citing the “optimistic” estimates of the American Gas Foundation, Butterworth said biomethane from waste sources could cover only about 5% of current U.S. gas demand.

“Increasing RNG production beyond this level would require the use of highly controversial resources including energy crops and gasification of agricultural and forest residues. These forms of RNG production that rely on the intentional production of methane simply shouldn’t be on the table,” Butterworth said, citing the “lack of any clear GHG-reduction benefit and tradeoffs associated with land, water use and food production, to name a few.”

As legislators consider a clean heat standard bill, the Massachusetts Department of Environmental Protection (DEP) has also begun developing a clean heat standard while soliciting public feedback featuring many of the arguments that played out in the TUE hearings. (See Mass. Stakeholders Debate the Scope of Clean Heat Standard.)

Opponents of the legislation argued that the development of the standard should be left to the DEP, while advocates said the bill would provide important guardrails for which compliance pathways are included in the standard.

SPP Markets and Operations Policy Committee Briefs: July 10-11, 2023

Members Endorse Winter Resource Adequacy Requirement for 2024/25

OMAHA, Neb. — SPP stakeholders last week endorsed a tariff revision request that adds a winter resource adequacy requirement for load-responsible entities (LREs) bound by the grid operator’s recent planning reserve margin (PRM) increase.

However, the measure approved by the Markets and Operations Policy Committee during its July 10-11 meeting is likely to encounter headwinds from SPP’s state regulators and the Board of Directors when they hold their quarterly meetings next week.

The revision request (RR549) applies the same level of validation, study and assessment requirements to the winter season (December through March) that currently applies to the summer season, including a deficiency payment for capacity shortfalls. The measure also assigns an annual deficiency payment to prevent duplicate payments for the same capacity within an annual timeframe.

The tariff change met MOPC’s 66% averaged approval threshold at 67.2%, with 87.5% of transmission owners and 47% of transmission users voting for the revision. It is effective for the 2024/25 winter.

MOPC chair and ITC Holdings’ Alan Myers (middle) guides the discussion flanked by SPP’s Emily Pennel and Lanny Nickell. | © RTO Insider LLC

Director Steve Wright signaled to committee members that RR549 almost assuredly will meet resistance before the Regional State Committee and board next week. He said he was concerned about modified language that American Electric Power offered during the discussion and was accepted by the sponsoring stakeholder group as a friendly amendment. He said adding the PRM’s calculation to the tariff “exposes it to litigation at FERC.”

“That was a tough discussion with respect to whether to move forward now or try to perfect the resolution,” Wright said. “The discussion is there; the debate is there; the members came to a decision. Rather than adding a process requirement regarding the calculation of the PRM with a fairly vague standard and putting that into the tariff … I think that deserves a lot more discussion. For me, it takes us in a different direction. I hope there will be a continued discussion in the next two weeks.”

Richard Ross, AEP | © RTO Insider LLC

MOPC Chair Alan Myers, with ITC Holdings, said the Cost Allocation Working Group’s (CAWG) original version of the tariff change could be offered up to the RSC and board. Staff secretary Lanny Nickell said the time between the MOPC and RSC meetings will give staff and legal an opportunity to develop alternatives to the amended language.

AEP’s revisions require transmission providers to detail the methodology used in loss-of-load expectation studies and to determine the final PRM value based on their results. It said it was concerned the CAWG’s proposed language facilitates PRM changes without providing LREs adequate time to comply and that neither the tariff nor the planning criteria provide a transparent process for stakeholders to validate SPP’s determination or, on their own, forecast future PRM values.

“‘The final results of the LOLE study’ implies it is a simple formulaic result, when in fact it requires the application of judgment among many results,” AEP’s Richard Ross said.

The PRM was raised last summer and added to SPP’s planning criteria despite pushback from members. (See SPP Board, Regulators Side with Staff over Reserve Margin.)

The summer requirement already is in place this year. According to SPP’s 2023 resource adequacy report, all LREs complied with the summer RAR. Sixty LREs met the new 15% PRM requirement passed last year, and one met the 9.89% PRM requirement because its capacity is at least 75% hydro-based generation.

SPP’s Market Monitoring Unit supports a winter RAR but recommended remanding RR549 back to the CAWG to address its concerns. The MMU said that, as written, the tariff doesn’t include language requiring a reasonable expectation of availability for resources used toward RAR; it doesn’t achieve the policy’s goal for the deficiency payment; and the deficiency calculation does not send the appropriate signal to improve available accredited capacity.

MMU Comments Bypassed in Order 881 Compliance

MOPC endorsed a tariff change that SPP legal staff believe complies with FERC Order 881, which directs transmission providers to use ambient-adjusted ratings (AARs) for short-term transmission requests — 10 days or less — for all lines that are affected by air temperature. Seasonal ratings will be required for long-term service. (See FERC Orders End to Static Tx Line Ratings.)

RR565 is a response to FERC’s deficiency letter in May. The commission ruled SPP was noncompliant and directed it to use AARs for any seams-based transmission service; explain its timelines for calculating or submitting AARs; and address systems and procedures so TOs can update their line ratings at least hourly (ER22-2339).

The MMU said the measure does not address some of FERC’s determinations and recommended its own edits. It proposed replacing three sentences approved by the Operating Reliability Working Group (ORWG) with six paragraphs that it said address line ratings’ and methodologies’ “transparency and accuracy.” It also recommended adding transparency indicating the market processes that will use the line ratings.

However, MOPC declined to consider the edits. It passed the ORWG’s recommended version with a 95.56 average.

ORWG Vice Chair Jeff Wells, with Grand River Dam Authority, agreed that the measure’s language doesn’t address all that was required by FERC. He said a procedure manual will outline the process for implementing AARs and “address the unknown.”

“We were trying to keep the tariff concise, to be concise with the wording and what’s required by the tariff,” Wells said, adding that “accommodations” were made to give TOs the flexibility they need to adhere to the requirements “without being burdensome beyond what was required.”

Addressing concerns over the validation process, Keith Collins, vice president of the MMU, said Order 881 requires market monitors to be included. He said SPP will ensure appropriate line ratings or replacements up front, with the MMU taking over after the fact to look at gaming opportunities or market inefficiencies.

MMU’s Keith Collins (right) explains the monitor’s position on Order 881 compliance as SPP’s Yasser Bahbaz listens. | © RTO Insider LLC

“FERC requires the market monitors to validate and have a role in the process. It’s not optional,” Collins said.

He said RR565 likely will be on the board’s consent agenda when it meets next week. MMU staff will evaluate whether to ask that it be pulled off and considered separately, Collins said. The Monitor also could intervene at FERC, which it has done in the past.

“That’s our general practice,” he told RTO Insider. “However, if we’re going to raise a concern with FERC, we would like to ensure that the board has had an opportunity to understand our concerns.”

The commission has granted the RTO an extension to Aug. 1 to make its second compliance filing.

GI Backlog Halfway Completed

SPP celebrated the halfway point of clearing its generator interconnection queue by issuing a press release highlighting its mitigation strategies as paving the way “for the construction of dozens of new resources.”

The RTO credited the backlog mitigation plan with executing GI agreements that will add more than 14.5 GW of new generation to the system over the next four years. SPP has added almost 28 GW of capacity to the system since 2017, when the backlog began.

FERC approved SPP’s backlog mitigation plan, designed to simplify and reduce study timelines, in January 2022. It has completed two cluster studies since, with the five remaining clusters on track to be finished next year. (See “GI Backlog Plan Approved,” FERC Denies Co-ops’ $79M Complaint vs. SPP.)

The queue still has 561 active requests for 112 GW of generation (108 GW of renewable resources) left, with about 220 of the requests submitted last year.

MOPC separately approved RR493, which consolidates language from several existing business practices and the Definitive Interconnection System Impact Studies (DISIS) manual into a standalone GI manual. It also adds GI special studies to the manual and a fuel-based dispatch option to the second study phase.

The measure revises the existing fuel-based dispatch methodology to dispatch non-legacy ITP generators without firm transmission service at the same percentage as non-ITP generators with higher queue priority.

Staff said they had some concerns about RR493’s additional responsibilities in resolving the queue’s backlog, but they supported the measure and would provide a more thorough impact assessment during MOPC’s January meeting.

“SPP staff can support this particular motion because it baselines the manual. … We’re going to have to go through an exercise to determine the overall impact,” said Casey Cathey, SPP’s director of grid asset utilization. “We have actually doubled the very next DISIS, so we’re kind of going into it with eyes wide open.”

SPP Self-reports to FERC

Nickell drew some smiles when he told the committee SPP had filed a self-report with FERC in March. The smirks turned into chuckles when he admitted he had forgotten to pass along the information during the committee’s April meeting.

“My mistake. I’m just now catching up,” he said.

Staff discovered this year that in 2020, they had incorrectly assigned Kansas City Board of Public Utilities (KCBPU) as a transmission-owning member in its electronic ballot tool, rather than as a transmission-using member. Staff reviewed the votes taken since then and discovered the error affected only one vote: approving the PRM’s increase to 15% during the October MOPC meeting. (See “Members Address Resource Adequacy,” SPP Markets and Operations Policy Committee Briefs: Oct. 10-11, 2022.)

MOPC votes require a two-thirds vote, equally weighted between TOs and TUs, for approval. The PRM measure passed with 66.29% approval, with KCBPU voting “yes” as a TO. Nickell said had the utility been assigned correctly as a TU, the PRM vote would have failed at 65.63%.

The board and state regulators approved the PRM’s increase last July. The October vote simply endorsed RR516 as implementing the increase.

“We think the outcome is inconsequential,” Nickell said. However, because staff changed the vote, SPP reported the change to FERC.

SPP General Counsel Paul Suskie said the industry makes similar self-reports “all the time.”

20-year Tx Assessment Endorsed

Stakeholders unanimously endorsed a 20-year assessment of long-range extra-high-voltage (EHV) transmission needs that says SPP will need between 900 and 1,200 miles of new EHV lines that could enable carbon dioxide reductions of up to 93%.

The study team evaluated 463 solutions during its 35-month analysis. It found the solutions could cost as much as $1.55 billion in engineering and construction costs across its reference case and emerging technologies cases, with a benefit-to-cost ratio of $1.57 billion to $4.35 billion. The assessment does not request notifications to construct, but it did recommend 13 new transmission projects to resolve congestion and other constraints.

The study was due before the end of last year. The next 20-year assessment is targeted for 2027.

“For us to really realize the [20-year assessment’s] value, we’ve got to do these much faster,” said David Kelley, vice president of engineering. “This becomes much more valuable information because, as we all know, our industry is changing much faster than any of us thought was ever possible just a few years ago.”

After receiving feedback from members about media reports that focused on the assessment’s costs, SPP staff clarified that the 20-year study is intended to develop a long-range EHV (considered 300 kV or more) transmission road map for the SPP region. It also identifies projects that economically deliver energy and addresses future industry uncertainty; the identified projects will provide candidates that inform shorter-term planning assessments.

Winter Models to Reflect Uri

The Transmission Working Group updated MOPC on its discussions with the Economic Studies Working Group over the 2024 ITP’s winter weather assessment.

A strike team decided that regional winter models should be more reflective of the February 2021 winter storm (also known as Uri), which had a large impact on the natural gas supply and limited renewables’ production.

Stakeholders have chosen accuracy over precision in using historical data to model the effects on the footprint’s different subregions, similar to a load-forecast approach.

Several other stakeholder groups also briefed the committee:

    • The Project Cost Working Group has created an in-service date delay report that will be added to the quarterly project tracking report and list network upgrades with estimated in-service dates at least one year past. Staff will review the new report with the working group each quarter and provide updates to MOPC and other stakeholder groups as needed. The increased awareness already has resulted in 18 completed and previously delayed upgrades at a cost of $146 million, said group Chair Brian Johnson, with AEP.
    • The Strategic and Creative Re-engineering of Integrated Planning Team’s Consolidated Planning Process Task Force is drafting a white paper to “button up” the first phase of its proposed consolidated planning process following “a lot of healthy discussion,” SPP’s Sunny Raheem said. The stakeholder group still must determine an entry fee rate-structure design for cost-sharing and recovery and transition plan recommendations, and continue developing phase 1 policy recommendations.

Zonal Criteria Voting Changed

Members unanimously approved its consent agenda, but not before National Grid Renewables Energy Marketing pulled RR557 for separate consideration. The measure, which passed with opposing votes from National Grid and two other transmission users, updates the zonal planning criteria voting process so absent and abstention votes no longer are counted as “no” votes and are not included in the final tally.

National Grid’s Margaret Kristian said the smaller denominator creates a low bar for approval with abstentions or absent votes. “We think that the recording of approval should really be in the affirmative on the new policy, and that the kind of default action should not necessarily be to approve without the majority,” she said.

The consent agenda included scope updates to the 2024 ITP that document a new vendor for the long-term natural gas pricing outlook and defining extreme winter weather model scenarios needs; endorsement of a sponsored upgrade study for 161-kV work in Omaha; and nine additional RRs that would:

    • RR521: clarify that market participants registering auxiliary load must ensure that it is consistent with any legal or regulatory requirements applicable to the auxiliary load or the entity serving the load.
    • RR542: define aggregator of retail customers (ARC) and differentiate between certification and attestation requirements for ARCs and other aggregators registering under FERC Order 719.
    • RR543: require market participants registering demand response resources (DRRs) to verify that critical load is not being registered as a DRR and that the registered capacity does not exceed the load’s hourly maximum within the previous year; and clarify the dispute process between the market participant, retail provider and relevant retail regulatory authority for DRRs.
    • RR547: eliminate the need for the MMU to pass an annual revision request updating the variable operations and maintenance escalation index that can be computed from publicly available Bureau of Labor Statistics data.
    • RR548: eliminate the rarely used screening study processes for long-term service requests (LTSR) and delivery point transfers (DPT) and incorporate the DPT into the consolidated planning process.
    • RR552: do away with the ITP manual’s requirement removing the firm service requirement for resource inclusion in the base reliability power-flow models.
    • RR553: ensure all uncertainty product revision requests (RR449, RR496, RR535) are implemented correctly.
    • RR561: clarify the overall multiday reliability assessment (MDRA) process and how the day-ahead market will consume its commitments, how they are compensated through settlements and which resource offer costs are used for recovery.
    • RR569: correct the settlements protocols to ensure multiday minimum run time and settlement calculation cleanup are implemented accurately.

DC Circuit Sends SEEM Back to FERC

The D.C. Circuit Court of Appeals on Friday remanded FERC’s approval of the Southeast Energy Exchange Market (SEEM) back to the commission for additional proceedings.

The three-judge panel agreed that FERC was wrong to deny initial requests for rehearing of the approval because of the dates on which they were filed, but Judge Neomi Rao split with her two colleagues in a partial dissent and agreed with the commission’s reasoning on two of the specific rules that came before the court.

SEEM members include Associated Electric Cooperative, Duke Energy, Southern Co., Tennessee Valley Authority and others in the Southeast. The market has an algorithm to match excess supply with free transmission every 15 minutes, enabling more frequent transactions among its members. It ran into opposition from parties who argued it was anti-competitive compared to the Western Energy Imbalance Market, let alone a full ISO/RTO.

FERC was unable to agree on whether to approve the SEEM proposal, splitting 2-2, which allowed the SEEM tariff to go into effect automatically. Now it returns to another iteration of the commission with four votes, though with acting Chair Willie Phillips instead of former Chair Richard Glick. (See SEEM to Move Ahead, Minus FERC Approval.)

The case presented a test of a recent change to the Federal Power Act that made such split decisions reviewable by the courts. One issue was whether parties had submitted their required rehearing requests to the commission on time. FERC argued that it had to rule on the case by Oct. 10, 2021, which started the 30-day countdown for rehearing that would end Nov. 9.

However, Oct. 10, 2021, was a Sunday, and it was followed by Columbus Day on Oct. 11, when FERC was shut down. Thirty days after was Veterans Day, which meant FERC was closed again. Advanced Energy United and other parties sought rehearing in filings submitted Nov. 12.

The court ruled in 1989 that deadline dates exclude Saturdays, Sundays and federal holidays, which made Nov. 12 the due date for rehearing requests.

“Accordingly, the commission erred in finding the petition for rehearing of the deadlock order untimely below, and the related orders finding as such are therefore vacated,” the court said.

FERC will have to deal with the rehearing requests’ merits on remand, the court said.

While FERC was split on the order approving SEEM, it was able to vote out a related order on the market’s nonfirm energy exchange transmission service (NFEETS); it also rejected requests for rehearing of that order. The court was able to weigh the merits of those requests. (See FERC Again Rejects Efforts to Overturn SEEM.)

SEEM requires that entities transacting in it have a source and sink inside its footprint, which goes against FERC’s pro forma open-access transmission tariff from Order 888. The old bilateral market was different from the pro forma tariff as well, but the new SEEM rules excluded 65 existing bilateral trading partners that cannot participate in the new market.

SEEM’s backers argued that the geographic limits were needed to implement the 15-minute trades, but the court noted that they could have designed the system differently to more efficiently handle such requests.

“The creation of a new service that — by its design — excludes existing market participants evokes the discriminatory practices against third-party competitors by monopoly utilities that prompted the commission’s adoption of Order No. 888,” the majority said.

It ruled that FERC failed to offer a good enough explanation on how the rules are better than the pro forma tariff and that it will have to explain that better, or explore rule changes, on remand.

Opponents argued that under Order 888, NFEETS made SEEM a loose power pool, which is required to be open to nonmembers. Order 888 qualifies loose power pools as arrangements between more than two utilities where they offer discounted power, specifically mentioning “non-pancaked” rates as a discount.

SEEM charges only one transmission rate for power to cross all of its members’ systems, so the majority found that FERC failed to adequately explain why it was not a loose power pool.

Rao dissented on the NFEETS issue, finding that SEEM’s backers had compelling technical reasons to limit participation to entities within its footprint and that FERC correctly determined it was not a loose power pool.

“NFEETS does not limit access to any currently existing service,” Rao wrote. “Rather, it provides an entirely new service that facilitates valuable short-term energy transactions, resulting in substantial cost savings across the Southeast. The tariff revisions are thus strictly preferable to the existing tariffs.”

She also agreed with FERC that SEEM did not qualify as a loose power pool because it creates the opportunity for new transactions; it does not “in any sense result in a discounted or special rate from existing arrangements.”

“SEEM provides a valuable service by establishing a new market for utilities in the Southeast to engage in short-term energy transactions,” Rao said. “FERC reasonably approved the no-cost transmission service necessary to implement SEEM.”

Regulators Propose New Independent Western RTO

PORTLAND, Ore. — The competition for organized markets in the West grew Friday as the Bonneville Power Administration launched a process to choose between day-ahead markets proposed by CAISO and SPP and regulators from five Western states urged the establishment of a new, independent RTO covering the entire West.

“This group proposes the creation of an entity that could serve as a means for delivering a market that includes all states in the Western Interconnection, including California, with independent governance,” regulators from Arizona, California, New Mexico, Oregon and Washington wrote to the chairs of the Western Interstate Energy Board (WIEB) and the Committee on Regional Electric Power Cooperation (CREPC).

The entity “could provide a full range of regional transmission operator services, utilizing a contract for services” with CAISO including eventual “assumption” of CAISO’s proposed Extended Day Ahead Market (EDAM) and its real-time Western Energy Imbalance Market (WEIM).

The letter cited studies that have shown the greatest economic and environmental benefits for the West would come from a single Western RTO. A state-led market study in 2021 found that development of an RTO covering the entire U.S. portion of the Western Interconnection could save the region $2 billion a year in energy costs by 2030.

“We have identified a common commitment in seeking the benefits shown in multiple studies that demonstrate the most favorable electricity market for consumers is one that includes a West-wide market footprint,” the letter said. “Such a market would avoid the issue of ‘seams’ from separate markets across major portions in the West and result in optimized use of resources to meet loads across the entire interconnection.”

“In announcing our commitment, the group is inviting all Western states and associated stakeholders to join the effort and help shape the approach,” it said.

The planning process will begin this year, and implementation will start in early 2024 “with the formation of the independent entity, the seating of an initial founding board of directors, exploration of the relationship with CAISO for future services and the expectation of a small independent staff being put in place,” the letter said.

‘A Breakthrough’

The prospect of a single West-wide RTO has been growing less likely as CAISO and SPP compete for market share for their proposed day-ahead offerings, and SPP is making inroads on the development of a Western version of its Eastern RTO called RTO West. (See Western Day-Ahead Markets Debated at CREPC-WIRAB.)

At the same time, the latest legislative effort to allow CAISO to become a Western RTO appears to have stalled. Assembly Bill 538 was held by its author in committee in May because of staunch opposition from powerful labor unions in California.

The bill would let CAISO create a governing body free from oversight by California politicians. Currently, the state governor appoints members to the ISO’s Board of Governors, and the state Senate approves them. (See CAISO Regionalization Bill Put on Hold.)

In the past, lawmakers have refused to relinquish control of CAISO, and other Western states have said they will not join an RTO dominated by Californians.

The regulators’ proposal could offer a way out of the stalemate and an alternative to Western entities thinking of joining SPP’s RTO West. “The letter represents a breakthrough in efforts to advance the regions’ energy landscape and is key to creating a market that fosters collaboration, improved reliability and economic growth,” Advanced Energy United, a national clean-energy trade group, said in a statement. AEU is part of a coalition of business and environmental groups called “Lights on California” that advocates for creation of a Western RTO.

The Environmental Defense Fund also is a coalition member.

“The positive thing to me is that this is the loudest signal to date that the West is organizing, and that is extraordinarily exciting and encouraging,” said Michael Colvin, who leads EDF’s work on California energy policy. “It’s an alternative to the SPP front. Whether it goes this way or the CAISO way, it recognizes that the most affordable and reliable way to achieve our energy goals and to decarbonize is through collaboration.

“It is a signal to all the folks that are thinking of jumping ship to SPP that the West is here for you.

In a statement to RTO Insider, CAISO CEO Elliot Mainzer said, “We are pleased that utility regulators from around the West have come together to discuss how they can work more closely together to enhance reliability and benefit ratepayers throughout the region. … CAISO stands ready to support their efforts and work with a broad range of stakeholders to develop a long-term approach that meets the needs of California and the entire Western U.S.”

SPP Vice President of Markets Antoine Lucas struck at diplomatic note in his comments on the development, saying the RTO understands that Western regulators want to “explore every available option” in their efforts to ensure that regionalization occurs with the interests of ratepayers in mind.

“SPP is confident in its ability to provide an independently governed market designed such that it will help states ensure electric reliability, reach their renewable goals, and enable equitable trade across the Western Interconnection,” Lucas said. “We stand ready to prove the integrity and value of our proposed Markets+ service and to meet the needs of Western stakeholders.” 

BPA: Markets+ vs. EDAM

The commissioners’ letter came just hours after BPA kicked off a public process at its Portland headquarters to determine whether it will participate in a day-ahead market and, if so, which option to choose: SPP’s or CAISO’s.

BPA operates about 70% of the transmission in the Northwest and is the region’s largest electricity supplier.

Friday’s workshop was to be the first of five such meetings to be held every other month through the beginning of next year, with each followed by a public comment period. BPA plans to propose a “record of decision” on the issue shortly after SPP files its Markets+ tariff with FERC in February 2024. It expects to conclude with a final workshop to discuss its decision and address the last round of feedback.

“This is an open-ended process; BPA has not decided to join a day-ahead market,” Russ Mantifel, BPA’s director of market initiatives, told workshop participants Friday.

But multiple sources involved in Western regionalization efforts, who asked not to be quoted because they’re not authorized to speak for their organizations, told RTO Insider that BPA is leaning toward Markets+. They cite a number of factors that put BPA in the SPP camp, including more favorable treatment for hydroelectric generation in Markets+, a CAISO bias in favor of California load that restricts wheel-throughs in the ISO during critical periods and the unresolved issues around the lack of independent governance for CAISO.

Governance is an especially intractable issue for BPA, which, as a federal power marketing agency, cannot cede its authority to a state-run organization, prohibiting it from participating in a CAISO-run RTO that is not overseen by an independent board.

And while membership in a full RTO is not on the table, Mantifel pointed to the importance of joining a day-ahead market that eventually can integrate more functions — such as resource adequacy — as conditions evolve in the West.

“One of the things we think about [regarding] governance, market design, etc., is which options create the opportunity to create more verticality, potentially going to an RTO or adding these functions as part of it, and which ones have had that sort of limitation,” Mantifel said.

Alex Swerzbin, director of transmission and markets for PNGC Power, a Portland-based generation and transmission cooperative owned by 16 utilities in seven Western states, agreed on the need for “verticality.” He encouraged BPA to consider the “end state” of its decision, which is future participation in an RTO. Swerzbin said the WEIM can be viewed as “sunk cost to a degree” because real-time trading still constitutes a small percentage of the market.

“Once we move to a day-ahead market, that is a much larger footprint. It is much harder to transition from one day-ahead market to a separate [market] to get to an RTO/ISO,” Swerzbin said.

But Fred Heutte, a senior policy analyst with the Northwest Energy Coalition, urged BPA to put aside an “A-to-B” comparison between EDAM and Markets+ in favor of considering the “big-picture question” of whether to have one or two markets in the West.

“The issue is going to be delivered value,” Heutte said. “If we have two markets, the likelihood, at least initially, from what we can see, is to have a significant reduction in delivered value in terms of cost, in terms of reliability and in terms of longer-term issues” such as transmission planning and resource adequacy, “no matter how good each of the market offers may be.”

Heutte said “the really big picture” is the impact of two markets on the diversity inherent in the Western Interconnection.

“If you look forward with the changing resource mix, with changes in extreme weather conditions, the changes in demand profile, as we see more large loads and more decarbonization load coming on the system, the resource and the load diversity of the West is a really critical factor,” he said.

“The more diversity, the fewer seams you have, the more effective [a market is] going to be — I can’t disagree with that,” Mantifel said. “I think … the other reality is what it takes to get there, and sort of the sacrifices and compromises people are willing to make in order to achieve that, and whether that’s ultimately viable.”

BPA has scheduled its next day-ahead market workshop for Sept. 11-12.

BPA expects to conclude its process for deciding on a day-ahead market early next year. | Bonneville Power Administration

CAISO is expected to file tariff language with FERC on EDAM next month. It has been promoting the day-ahead market among potential participants as it faces stiff competition from SPP.

On Thursday, CAISO said it would co-host a market forum on EDAM with NV Energy, PacifiCorp and others in Las Vegas on Aug. 30.

“The forum, which aims to foster a dialogue on the evolution of the EDAM in the West, will bring together leadership from regional utilities to discuss and share their thoughts on the factors and processes in considering their participation, as well as utility regulators from across the West, who will share their perspective on the next step in market evolution and how they are actively engaging in its development,” CAISO said.

OMS-MISO RA Survey Signals Potential for 9-GW Shortfall by 2028

MISO and the Organization of MISO States’ 10th annual resource adequacy survey warned that a more than 9-GW shortfall could loom by the decade’s end, though it painted an adequate supply picture for the coming year.

MISO and OMS found the footprint will have 1.5 GW of residual capacity beyond the summer planning reserve margin requirement in the 2024/25 planning year.

However, survey results in the four subsequent years are light on reassuring news.

The organizations said that without swift action, a 2.1-GW total shortage is possible the summer of the 2025/26 planning year, a 3.4-GW deficit by the 2026/27 planning year, a 4.8-GW gap in the 2027/28 planning year and a 9.5-GW shortfall by the 2028/29 planning year.

According to the survey, MISO Midwest’s potential capacity deficits start in the summer of the 2025/26 planning year, while MISO South shows a potential deficit brewing by winter 2027/28. MISO and OMS said so far, the seasons outside of summer show sufficient — yet declining — capacity.

MISO said about 90% of its generating fleet responded to this year’s survey.

This year, the survey was divided by season to reflect MISO’s new seasonal format and projected capacity values across four seasons for the next four years. Results were delayed by more than a month because of MISO’s monthlong auction delay on a FERC show-cause order.

MISO and OMS are betting that demand grows at a clip of 0.8 GW or 0.68% per year on average and the planning reserve margin requirements climb from 7.9% in the 2024/25 timeframe to 9.2% in 2028/29. MISO used its loss-of-load modeling to predict margin requirements.

The two also said the survey showed potential capacity additions of as much as 6.9 GW in the 2025/26 planning year, 13 GW in 2026/27, 17.1 GW in 2027/28 and 20.7 GW in 2028/29, which could offset the potential shortages. Historically, MISO grants grid access to about 2.5 GW per year on its system. As of last month, MISO’s generator interconnection contained 1,412 active projects totaling almost 241 GW.

“These results continue to illustrate the reliability risk we face and reinforce the need for dispatchable, long-duration resources to be maintained and brought online to manage the transition to weather-dependent, low-carbon resources,” MISO CEO John Bear said in a press release.

This survey’s potential deficits are marginally better than those from last year’s OMS-MISO survey, which projected the footprint could experience as much as a 2.6-GW capacity deficit below the 2023 planning reserve margin requirement. The 2022 survey showed possible capacity deficits thereafter of 4.4 GW in the 2024/25 planning year, 6.5 GW in 2025/26, 7.4 GW in 2026/27 and nearly 11 GW by 2027/28. (See OMS-MISO RA Survey Says Supply Deficits Could Top 10 GW by 2027.)

While last year’s results were affected by MISO’s 1.2-GW capacity deficit across all Midwestern local resource zones, this year’s survey results were influenced by the fact that all zones were resource-adequate starting June 1 and through May 30, 2024, according to the spring capacity auction. (See 1st MISO Seasonal Auctions Yield Adequate Supply, Low Prices.)

“With so many moving pieces involved with the changing electricity mix, regional assessments such as this one are becoming increasingly important to fully understand how the region will maintain reliable and affordable electricity delivery to customers,” Organization of MISO States President and Michigan Public Service Commission Chair Dan Scripps said in the release. “The increased transparency that comes with the seasonal granularity of this survey will undoubtably prove useful to state commissions, utilities and other market participants as they look to firm up their future resource plans to provide reliable and affordable electricity.”

MISO said this year’s survey reflected actions market participants took since becoming aware of the capacity deficit in the 2022/23 planning year, which included delaying unit retirements and making additional capacity available to the footprint. However, the grid operator warned that “these actions may not be repeatable in the future. It said the survey once again “highlights the need for additional resources and other solutions — such as market changes — to avoid potential capacity deficits in the future.”

During a Friday stakeholder teleconference to discuss results, Scripps stressed that the survey isn’t a carved-in-stone future, but an “aggregation of all the information that is available to us today.” He said it was “undeniable” that market participants’ reactions to last year’s shortfall moved capacity projections from in the red to black for the coming year.

“That said, this is a one-year response,” Scripps said, adding that the temporary remedies are not a substitute for long-term solutions for increasingly scarce capacity.

On the same call, Senior Resource Adequacy Engineer Nick Przybilla said MISO’s supply picture could improve if MISO makes headway on ushering projects through its interconnection queue faster, if supply chain snarls improve and if future planning reserve margins turn up lower than expected.

MISO also cautioned that “resource accreditation will continue to evolve based on performance during high-risk periods.” MISO is resolved to adopt a new marginal capacity accreditation style that values availability during forecasted hazardous periods and stands to lower many resources’ capacity values. (See MISO Intent on Marginal Accreditation and Requirements Based on Risky Hours.)

Do Batteries or Transmission Produce Greater Benefits?

Adding battery storage to wind and solar resources increased generator revenues more than expanding transmission, especially in CAISO and ERCOT, but transmission expansion could relieve congestion in rural areas with plentiful wind and solar capacity, a recent study by the Lawrence Berkeley National Laboratory found.

The first-of-its-kind study assessed the benefits and drawbacks of transmission expansion and adding batteries to renewables in areas with transmission congestion. It looked at the findings from the perspectives of grid operators and generation owners.

“Both storage and transmission can increase grid flexibility, which is critical to the task of balancing system demand with uncertain variable renewable energy supply in real time, though they engage in different types of arbitrage,” the authors wrote.

“Storage shifts energy over time,” they noted. Optimally, batteries charge when electricity is cheap and discharge when prices rise. “Transmission shifts energy from one place to another,” moving lower-cost electricity to where it is needed to meet demand.

“Congestion occurs when transmission limits are reached and prevents low-cost resources from being fully utilized,” the study said. “Even [renewable energy resources], which have extremely low marginal costs of generation, curtail their output due to negative prices in some locations.”

Renewable resources and storage each affect transmission value, and “transmission capacity affects the commercial viability of generation and storage projects,” the study said. “So, understanding the dynamics of interplay between these asset types is essential to effectively plan for the changing grid.”

That is especially important because renewable generation and storage “are increasingly being built at the same locations in hybrid configurations,” it said.

For example, in CAISO, 99% of solar capacity entering the interconnection queue in 2021 was coupled with storage, it noted.

“These changes raise critical questions such as, ‘Will the shift towards hybrid plant deployment reduce congestion on the nearby transmission grid or will the shift necessitate additional actions to alleviate congestion?’” it said.

‘VRE-rich’ Areas

The study analyzed data from 23 locations on the U.S. bulk power system that experience significant congestion and have standalone solar and wind plants. The locations were in CAISO, ERCOT, ISO-NE, MISO, NYISO, PJM and SPP.

The findings from a grid operator’s perspective include:

    • Standalone wind and solar generators typically alleviate congestion near urban load centers and exacerbate congestion in rural areas with a high number of variable renewable energy (VRE) generators, which the study calls “VRE-rich” areas.
    • Standalone storage plants reduce transmission congestion in all areas.
    • Hybrid resources with renewable generation and storage alleviate congestion near load centers, but in VRE-rich areas, they can have different effects depending on their exact location and factors, such as whether batteries can charge from the grid.

For generation owners, the study found that:

    • Transmission expansion is generally a financial detriment to standalone wind and solar plants in load centers and a benefit to those in VRE-rich areas.
    • For hybrid resources in VRE-rich areas, expanding transmission typically increases revenue, but there are exceptions.
    • In VRE-rich areas, wind plants stand to gain “significantly more from transmission expansion,” while solar plants would benefit more from adding batteries.

“Solar plants in VRE-rich areas [could] expect to benefit from transmission expansion, but this benefit is dwarfed by the potential opportunity from installing storage, especially in CAISO and ERCOT, suggesting solar developers would be more invested in policies promoting hybridization than those focused on transmission,” the study said.

The solar plants in the study with the greatest per-MW revenue increase were in ERCOT ($200,000 to $380,000/MW-year) and CAISO ($50,000 to $91,000/MW-year) — both markets with a large share of solar generation.

The study’s authors said the results highlight the “different stakes that solar and wind developers have in local transmission expansion and how their priorities depend on a plant’s location and configuration.”

The results also “reveal previously unexplored ways in which policy, technology and contract terms related to hybrids can reduce the cost of congestion in local transmission systems,” the study said. “For example, policies incentivizing batteries at congested generation nodes may reduce congestion, since building storage alongside new VRE generators (either in hybrid or standalone configurations) is better, from a congestion perspective, than the standalone generator.

“Further, policies that allow hybrids to charge their storage component from the grid, instead of only from the VRE generator, result in lower costs due to congestion.”

ERCOT Sets New Demand Mark, Will be Short-lived

ERCOT appears to have set another peak demand record on Monday, but if the grid operator’s projections hold out, the mark will be short-lived.

Demand averaged 81.56 GW on Monday during the interval ending at 5 p.m., according to preliminary data. That would break ERCOT’s current unofficial high for demand, when it averaged 81.41 GW July 13.

The grid operator’s six-day forecast indicates it will exceed 86 GW Tuesday, with average demand exceeding 83 GW through Friday. A high-pressure ridge and expanding heat dome have returned to the region and the southern U.S., diverting the jet stream away. Temperatures were forecast to be 5 to 15 degrees Fahrenheit above normal in much of Texas as excessive-heat advisories affect more than 100 million people from Washington state to Florida.

ERCOT says it expects to have sufficient generation to meet forecasted demand. It hasn’t called for voluntary conservation since June 20 and had more than 6.6 GW of operating reserves Monday afternoon. It did issue its third weather watch of the summer for Sunday through Tuesday due to the forecasted temperatures, electrical demand and potential for lower reserves.

The grid operator has averaged more than 80 GW demand for 18 intervals this summer. It reached the mark just once last year, setting a record that has been eclipsed 14 times already.

The clear skies again have led to near-record solar and renewable generation. Sun-powered resources averaged more than 12 GW for much of the afternoon; together with wind resources, they provided more than a third of ERCOT’s fuel mix for much of the day.

The U.S. Energy Information Administration says ERCOT’s solar and wind capacity will double by 2035, but it noted that without upgrades to the transmission system, its analysis finds wind and solar generation increasingly will be curtailed.

ERCOT had almost 10 GW of thermal outages on July 12. Staff use 8.3 GW as a high number in their modeling scenarios.

MISO Monitor Again Sounds Alarm on Long-range Tx Planning

CARMEL, Ind. — MISO Independent Market Monitor David Patton appeared at this week’s Market Subcommittee meeting to again criticize the future resource mix assumptions the RTO is using to craft a second long-range transmission plan (LRTP) for its Midwest region.

Stakeholder reactions to his advice were mixed.

Patton has voiced concerns in this year’s State of the Market report over the capacity expansion model MISO is using to inform the portfolio, which could run the region several billion dollars. He said MISO isn’t considering enough future battery storage, hybrid resources, other dispatchable resource additions and grid-enhancing technologies as alternatives to an expensive transmission buildout. (See “LRTP Doubts,” MISO IMM Zeroes in on Tx Congestion in State of the Market Report.)

At the MSC’s meeting Thursday, Patton said battery storage is going to become “remarkably economic over time to reduce congestion caused by renewables.” He said MISO’s second transmission planning future’s projection that it will have 466 GW of mostly renewable nameplate capacity by 2042 is unrealistic. (See MISO Modeling Line Options for 2nd LRTP Portfolio.) MISO is anticipating having 31 GW of battery storage and 10 GW of storage-plus-renewable hybrid resources in that timeframe.

“Future 2 has almost no chance of happening, and yet we’re using it to plan tranche 2” of the LRTP, Patton said.

This is the first time Patton has raised concerns related to transmission planning in his report. MISO’s Board of Directors has wondered whether it’s appropriate for the Monitor to recommend a change in direction on transmission planning. Patton has argued that markets and transmission planning are inextricably linked.

American Transmission Co.’s Bob McKee and ITC Holdings’ Brian Drumm said Future 2 represents years of stakeholder debate and collaboration.

McKee asked whether Patton attended the stakeholder meetings to hash out the future planning assumptions. Patton said he “unfortunately” did not and wish he had.

“I’m all for consensus, but you can’t confuse consensus with fact. You can’t ignore that solar will have declining capacity value, and you can’t just imagine you’re going to keep building it and building it,” Patton said.

Michelle Bloodworth, of coal lobby group America’s Power, said she shared Patton’s concerns and that the second future should contemplate a realistic future resource mix.

Invenergy’s Sophia Dossin asked whether Patton has suggestions on how MISO can incent construction on batteries and hybrid resources.

Patton said the simple economics of MISO’s more attractive capacity accreditation for batteries, hybrid resources and natural gas plants will spur developers to build. He added that he isn’t expecting future bans on building new gas plants in every state in the footprint.

MISO will make a formal response to the recommendations in this year’s State of the Market report in December.

Nevada Exits US Climate Alliance

Gov. Joe Lombardo has removed Nevada from the U.S. Climate Alliance, saying the group’s objectives conflict with his goal of developing a diverse energy portfolio for the state that includes natural gas.

The decision came to light as Arizona Gov. Katie Hobbs announced this week that the Grand Canyon State had joined the Alliance. Lombardo made no official announcement of Nevada’s exit from the Alliance, but Nevada’s absence from the group’s membership roster was noticed following Hobbs’ announcement.

“While the goals of the U.S. Climate Alliance are ambitious and well-intentioned, these goals conflict with Nevada’s energy policy objectives,” Lombardo said in a July 5 letter to U.S. Climate Alliance Executive Director Casey Katims, stating his decision to leave the coalition.

“These objectives are focused on developing and maintaining a diverse energy supply portfolio and utilizing a balanced approach to electric and natural gas energy supply and transportation fuels that emphasizes affordability and reliability for consumers,” Lombardo wrote.

Lombardo laid out his energy policies in a March executive order, including the state’s “advancement of energy independence.” (See New Governor Seeks Shift in Nevada Energy Policy.)

Nevada’s previous governor, Steve Sisolak, brought the state into the Alliance in 2019. Sisolak, a Democrat, was defeated in his reelection bid last year by Lombardo, a Republican.

Lombardo’s office didn’t respond to a request for comment.

Falling Short of GHG Targets

Formed in 2017, the U.S. Climate Alliance is now a bipartisan coalition with 25 members. Alliance members have agreed to work toward the Paris Agreement goal of keeping global temperature rise at less than 1.5 degrees Celsius. They collectively set a target to reduce greenhouse gas emissions by at least 26% by 2025 and 50% by 2030, compared with 2005 levels, and reaching net zero in 2050.

The GHG reduction goals are similar to those included in Nevada’s greenhouse gas inventory, an annual report required by state Senate Bill 254 of 2019.

The most recent GHG report, released this year, shows Nevada slipping further from those targets. The report details the state’s GHG emissions through 2020, with projections through 2042.

Nevada’s targets used as a benchmark in the report are a 28% reduction in GHG emissions by 2025 relative to 2005 levels; a 45% reduction by 2030; and zero or near-zero emissions by 2050. But the report projects only a 21.4% reduction in GHG emissions by 2025 and a 22.7% reduction by 2030.

And those reductions are slightly less than projections in the state’s GHG inventory from a year earlier, which forecast a 22.5% reduction in GHG emissions by 2025 and a 23.9% reduction by 2030.

In 2020, Nevada’s net GHG emissions totaled 37.3 million metric tons of CO2 equivalent, a 24.4% reduction from 2005 levels. GHG emissions in 2020 were less than the 2019 levels of 40.6 million metric tons. The report attributes the 2020 decrease to impacts of the COVID-19 pandemic, particularly on the transportation sector.

The transportation sector was the largest contributor to GHG emissions in Nevada, accounting for 32% of gross emissions in 2020, followed by electricity generation, which accounted for 31%.

For projecting future GHG emissions, the report makes several assumptions, including future retirements of natural gas-fired electric generating units. But the Public Utilities Commission of Nevada this year approved NV Energy’s request to postpone retirements of several gas-fired plants, as well as construction of a new 400-MW gas-fired peaker plant. (See NV Energy Rejected on Plan to Replace Coal Plant with Storage.)

Next year’s GHG inventory will likely factor in the recent PUCN decisions.

‘Door is Open’

Evan Westrup, communications director for the U.S. Climate Alliance, said Lombardo’s decision to leave the Alliance was disappointing, but “our door is open” if he changes his mind.

“As unprecedented wildfire smoke, record heat and catastrophic floods sweep across the country, we need every state and every governor — no matter their politics — confronting this crisis,” Westrup said in an email.

Westrup noted that newly elected governors in other Alliance states have opted to remain in the coalition, including the governors of Massachusetts, Hawaii, Oregon, Maryland and Pennsylvania.

Christi Cabrera-Georgeson, co-deputy director of the Nevada Conservation League, credited Lombardo for signing bills this year that will create more accountability and transparency in utility planning and promote clean energy.

But Lombardo’s decision to leave the U.S. Climate Alliance “contradicts these efforts and cedes Nevada’s leadership on clean energy and climate,” she said.

“This was a choice to prioritize utilities and their profits over everyday Nevadans who are already struggling to pay their energy bills amid record-breaking temperatures,” Cabrera-Georgeson said in an email. “By not prioritizing clean energy investments to diversify our job market and reduce greenhouse gas emissions, Nevada’s economy and environment will also suffer.”